Haines Kibblehouse v. Balfour Beatty Contruction, In

Court of Appeals for the Third Circuit·Decided February 3, 2014·No. 11-2826·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 11-2826

HAINES & KIBBLEHOUSE, INC., Appellant

v.

BALFOUR BEATTY CONTRUCTION, INC.

On Appeal from the United States District Court for the Eastern District of Pennsylvania District Court No. 5-08-cv-05505 District Judge: The Honorable Stewart Dalzell

Submitted Pursuant to Third Circuit L.A.R. 34.1(a)

January 10, 2014

Before: SMITH, SHWARTZ, and SCIRICA, Circuit Judges

(Filed: February 3, 2014)

OPINION

SMITH, Circuit Judge.

Haines & Kibblehouse, Inc. (“H&K”) appeals from an order of the District Court dismissing its complaint pursuant to the doctrine of judicial estoppel. For the reasons expressed below, we will affirm.

This case comes before us after traversing a complex procedural path, which the District Court aptly characterized as “labyrinthian.” Balfour Beatty Construction, Inc. (“Balfour”) contracted with the Commonwealth of Pennsylvania’s Department of Transportation (“PennDOT”) to be the general contractor for the construction of the Route 222 Bypass project (the “Project”). On April 21, 2004, Balfour entered into a subcontract with H&K to perform certain paving, subbase, and utility work for the Project. Although the terms of the contract between Balfour and PennDOT required that the Project be completed by September 18, 2006, significant delays pushed the eventual completion date back to late 2007.

On September 18, 2006 (the original date the Project was to be completed), H&K filed a five-count complaint against Balfour in the Court of Common Pleas of Montgomery County, Pennsylvania (“Haines I”), alleging, inter alia, that Balfour’s failure to complete certain predecessor work with diligence caused H&K to incur significant additional costs and other damages. Balfour removed Haines I to the United States District Court for the Eastern District of Pennsylvania and filed a motion to dismiss. On June 7, 2007, the District Court dismissed four of H&K’s claims without prejudice and remanded the only remaining claim, one for declaratory relief, back to state court.

The District Court’s decision to dismiss certain counts of the Haines I

complaint was based on its determination that, under the terms of the Subcontract, H&K could not pursue its claims against Balfour unless (or until) Balfour first sought compensation from PennDOT—a predicate event which had not yet occurred. In reaching this decision, the District Court relied on Article 2.2.20 of the Subcontract, explaining:

The plain meaning of Article 2.2.20 is that any claim that the subcontractor [H&K] has for performing extra work or arising out of a delay or any other claim, whether it be against PennDot or [Balfour]

must first be compensated by the Owner (PennDot) to the Contractor [Balfour] before [H&K] can bring suit against [Balfour].[1]

Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No. 2:06-cv-4807, slip op. at 4 (E.D. Pa. June 7, 2007) (emphasis in original).

Following entry of the dismissal order, H&K filed a motion for

1 Article 2.2.20 provides in full:

Condition Precedent. Contractor’s receipt of payment from Owner for each progress payment, final payment, change, extra work, delay, claim or each and every other request for payment or compensation by Subcontractor shall be an absolute condition precedent to any duty or obligation of Contractor to make any payment to Subcontractor pursuant to any application for payment or compensation. Such payment by Owner to Contractor is further an absolute condition precedent to Subcontractor filing or bringing against Contractor any action for nonpayment of any request for payment or compensation by way of arbitration, mediation, Federal or State Court action, or through any other forum for resolution of disputes.

Contractor and Subcontractor hereby expressly acknowledge and agree that the Contractor’s surety is an intended third party beneficiary of the Article.

In the event any action is asserted by Subcontractor against Contractor or its surety for nonpayment, this Article shall be a complete defense to nonpayment by Contractor and surety pending the occurrence of payment from Owner to Contractor.

reconsideration and simultaneously requested permission to take an interlocutory appeal. Both requests were denied. H&K then filed a Notice of Appeal with the Third Circuit on August 22, 2007. Upon receipt of the Notice of Appeal, the Clerk of Court instructed the parties to comment on the Court’s jurisdiction, and, more specifically, to discuss whether the District Court had issued a final order subject to appellate review. In a letter brief dated September 5, 2007, H&K responded that the District Court’s dismissal was indeed final. H&K claimed that it was “stand[ing] on the allegations in the [Haines I] Complaint” because there was “no way for [it] to cure the ‘defect’ that the District Court found.” Further, H&K claimed that the condition precedent, as the District Court defined it, “will never be achieved” because Balfour has no legal avenue to seek compensation from PennDOT for its own breach of the Subcontract. Accordingly, H&K asserted that it “will never be able to re-file its Complaint.”

On January 30, 2008, this Court issued an order stating its intention to address the jurisdictional question during its review of the case on the merits. 2 The Court, however, did not immediately issue a briefing schedule because the parties were engaged in our Circuit’s mandatory mediation program. After nearly eight

2 Although the Court determined that it was not appropriate to immediately dismiss the appeal based on a jurisdictional defect, the Court cautioned that its decision did “not represent a finding that the Court has jurisdiction to hear the appeal in this case.” Order, Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No 07-3520 (3d Cir. Jan. 30, 2008).

months of mediation, H&K sought to terminate the mediation process and to proceed with its appeal. In response, this Court issued a briefing schedule.

Before either party submitted an appellate brief, however, H&K voluntarily dismissed its Haines I appeal and, in its place, filed a new (second) complaint in the Montgomery County Court of Common Pleas (“Haines II”).3 H&K’s complaint in Haines II named the same parties, asserted the same claims, and involved exactly the same set of facts alleged in Haines I. On November 24, 2008, Balfour removed Haines II to United States District Court for the Eastern District of Pennsylvania, and then moved to dismiss based on claim preclusion and judicial estoppel. Significantly, Balfour argued that H&K was barred by the doctrine of judicial estoppel from claiming that the District Court had not issued a final order in Haines I, particularly in light of H&K’s decision to stand on its complaint in the Haines I appeal and its representations to this Court that it would “never” be able to re-file its complaint.

In response, H&K argued that its representations regarding the finality of the

District Court’s dismissal in Haines I were made before it discovered that Balfour 3 H&K filed its complaint in Haines II on November 4, 2008, while Haines I was still pending before the Third Circuit. On November 5, 2008 (the day after Haines II was filed), H&K sent a two-sentence letter to the Office of the Clerk informally seeking to “withdraw” its Haines I appeal. However, because this effort was procedurally improper, the Court did not take any action on H&K’s request. Balfour subsequently moved to dismiss the Haines I appeal on December 3, 2008. Acknowledging its mistake, H&K then appropriately filed a motion to voluntarily dismiss its appeal, which this Court granted on January 22, 2009. Thus, the two actions were pending concurrently for a period of at least two-and-a-half months.

Free access — add to your briefcase to read the full text and ask questions with AI

Haines Kibblehouse v. Balfour Beatty Contruction, In, (3d Cir. 2014).

Haines Kibblehouse v. Balfour Beatty Contruction, In (Haines Kibblehouse v. Balfour Beatty Contruction, In) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related