Haines Kibblehouse v. Balfour Beatty Contruction, In

CourtCourt of Appeals for the Third Circuit
DecidedFebruary 3, 2014
Docket11-2826
StatusUnpublished

This text of Haines Kibblehouse v. Balfour Beatty Contruction, In (Haines Kibblehouse v. Balfour Beatty Contruction, In) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haines Kibblehouse v. Balfour Beatty Contruction, In, (3d Cir. 2014).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________

No. 11-2826 _____________

HAINES & KIBBLEHOUSE, INC., Appellant

v.

BALFOUR BEATTY CONTRUCTION, INC.

_____________

On Appeal from the United States District Court for the Eastern District of Pennsylvania District Court No. 5-08-cv-05505 District Judge: The Honorable Stewart Dalzell

Submitted Pursuant to Third Circuit L.A.R. 34.1(a) January 10, 2014

Before: SMITH, SHWARTZ, and SCIRICA, Circuit Judges

(Filed: February 3, 2014) _____________________

OPINION _____________________

SMITH, Circuit Judge.

Haines & Kibblehouse, Inc. (“H&K”) appeals from an order of the District

Court dismissing its complaint pursuant to the doctrine of judicial estoppel. For the

reasons expressed below, we will affirm. This case comes before us after traversing a complex procedural path, which

the District Court aptly characterized as “labyrinthian.” Balfour Beatty

Construction, Inc. (“Balfour”) contracted with the Commonwealth of

Pennsylvania’s Department of Transportation (“PennDOT”) to be the general

contractor for the construction of the Route 222 Bypass project (the “Project”). On

April 21, 2004, Balfour entered into a subcontract with H&K to perform certain

paving, subbase, and utility work for the Project. Although the terms of the

contract between Balfour and PennDOT required that the Project be completed by

September 18, 2006, significant delays pushed the eventual completion date back

to late 2007.

On September 18, 2006 (the original date the Project was to be completed),

H&K filed a five-count complaint against Balfour in the Court of Common Pleas

of Montgomery County, Pennsylvania (“Haines I”), alleging, inter alia, that

Balfour’s failure to complete certain predecessor work with diligence caused H&K

to incur significant additional costs and other damages. Balfour removed Haines I

to the United States District Court for the Eastern District of Pennsylvania and

filed a motion to dismiss. On June 7, 2007, the District Court dismissed four of

H&K’s claims without prejudice and remanded the only remaining claim, one for

declaratory relief, back to state court.

The District Court’s decision to dismiss certain counts of the Haines I

2 complaint was based on its determination that, under the terms of the Subcontract,

H&K could not pursue its claims against Balfour unless (or until) Balfour first

sought compensation from PennDOT—a predicate event which had not yet

occurred. In reaching this decision, the District Court relied on Article 2.2.20 of the

Subcontract, explaining:

The plain meaning of Article 2.2.20 is that any claim that the subcontractor [H&K] has for performing extra work or arising out of a delay or any other claim, whether it be against PennDot or [Balfour] must first be compensated by the Owner (PennDot) to the Contractor [Balfour] before [H&K] can bring suit against [Balfour].[1]

Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No. 2:06-cv-4807, slip

op. at 4 (E.D. Pa. June 7, 2007) (emphasis in original).

Following entry of the dismissal order, H&K filed a motion for

1 Article 2.2.20 provides in full:

Condition Precedent. Contractor’s receipt of payment from Owner for each progress payment, final payment, change, extra work, delay, claim or each and every other request for payment or compensation by Subcontractor shall be an absolute condition precedent to any duty or obligation of Contractor to make any payment to Subcontractor pursuant to any application for payment or compensation. Such payment by Owner to Contractor is further an absolute condition precedent to Subcontractor filing or bringing against Contractor any action for nonpayment of any request for payment or compensation by way of arbitration, mediation, Federal or State Court action, or through any other forum for resolution of disputes. Contractor and Subcontractor hereby expressly acknowledge and agree that the Contractor’s surety is an intended third party beneficiary of the Article. In the event any action is asserted by Subcontractor against Contractor or its surety for nonpayment, this Article shall be a complete defense to nonpayment by Contractor and surety pending the occurrence of payment from Owner to Contractor. 3 reconsideration and simultaneously requested permission to take an interlocutory

appeal. Both requests were denied. H&K then filed a Notice of Appeal with the

Third Circuit on August 22, 2007. Upon receipt of the Notice of Appeal, the Clerk

of Court instructed the parties to comment on the Court’s jurisdiction, and, more

specifically, to discuss whether the District Court had issued a final order subject

to appellate review. In a letter brief dated September 5, 2007, H&K responded that

the District Court’s dismissal was indeed final. H&K claimed that it was

“stand[ing] on the allegations in the [Haines I] Complaint” because there was “no

way for [it] to cure the ‘defect’ that the District Court found.” Further, H&K

claimed that the condition precedent, as the District Court defined it, “will never be

achieved” because Balfour has no legal avenue to seek compensation from

PennDOT for its own breach of the Subcontract. Accordingly, H&K asserted that it

“will never be able to re-file its Complaint.”

On January 30, 2008, this Court issued an order stating its intention to

address the jurisdictional question during its review of the case on the merits. 2 The

Court, however, did not immediately issue a briefing schedule because the parties

were engaged in our Circuit’s mandatory mediation program. After nearly eight

2 Although the Court determined that it was not appropriate to immediately dismiss the appeal based on a jurisdictional defect, the Court cautioned that its decision did “not represent a finding that the Court has jurisdiction to hear the appeal in this case.” Order, Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc., No 07-3520 (3d Cir. Jan. 30, 2008).

4 months of mediation, H&K sought to terminate the mediation process and to

proceed with its appeal. In response, this Court issued a briefing schedule.

Before either party submitted an appellate brief, however, H&K voluntarily

dismissed its Haines I appeal and, in its place, filed a new (second) complaint in

the Montgomery County Court of Common Pleas (“Haines II”).3 H&K’s complaint

in Haines II named the same parties, asserted the same claims, and involved

exactly the same set of facts alleged in Haines I. On November 24, 2008, Balfour

removed Haines II to United States District Court for the Eastern District of

Pennsylvania, and then moved to dismiss based on claim preclusion and judicial

estoppel. Significantly, Balfour argued that H&K was barred by the doctrine of

judicial estoppel from claiming that the District Court had not issued a final order

in Haines I, particularly in light of H&K’s decision to stand on its complaint in the

Haines I appeal and its representations to this Court that it would “never” be able

to re-file its complaint.

In response, H&K argued that its representations regarding the finality of the

District Court’s dismissal in Haines I were made before it discovered that Balfour 3 H&K filed its complaint in Haines II on November 4, 2008, while Haines I was still pending before the Third Circuit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Haines Kibblehouse v. Balfour Beatty Contruction, In, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haines-kibblehouse-v-balfour-beatty-contruction-in-ca3-2014.