Gustine Uniontown Associates, Ltd. Ex Rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc.

892 A.2d 830, 2006 Pa. Super. 12, 2006 Pa. Super. LEXIS 24
CourtSuperior Court of Pennsylvania
DecidedJanuary 24, 2006
StatusPublished
Cited by37 cases

This text of 892 A.2d 830 (Gustine Uniontown Associates, Ltd. Ex Rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gustine Uniontown Associates, Ltd. Ex Rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc., 892 A.2d 830, 2006 Pa. Super. 12, 2006 Pa. Super. LEXIS 24 (Pa. Ct. App. 2006).

Opinion

BOWES, J.:

¶ 1 Gustine Uniontown Associates, Ltd., a Pennsylvania Limited Partnership, by and through Gustine Uniontown, Inc., general partner, (“Gustine”) questions the propriety of the dismissal of Architectural Services Group, Inc. (“ASG”) from this breach of contract and tort action. We affirm.

¶ 2 In 1992, Gustine acquired thirty-five acres in South Union Township, Fayette County, in order to construct Cherrytree Square Mall (the “mall”), a retail shopping center. The mall was built over a non-functioning coal mine. Before construction of the shopping center commenced, Gustine was informed that the subterranean characteristics of the acreage could result in earth movement, which, in turn, could result in structural damage to buildings located on the surface.

¶ 3 On May 17, 1992, Gustine executed a contract 1 with ASG, the architect for the project. Gustine entered separate contracts with various contractors for site preparation, investigation, and construction. The contract between ASG and Gus-tine provided that ASG would intermittently visit the construction site to generally familiarize itself with the progress and quality of completed work and to determine whether that work, when completed, was in accord with the contract documents. ASG did not, however, assume the duty to make exhaustive or continuous inspections nor the responsibility over construction means, methods, techniques, sequences, or procedures. The contract also stated specifically that ASG was not responsible for any particular contractor’s failure to carry out work in accordance with the contract documents and that ASG did not have control over acts or omissions of the contractors.

*833 ¶4 The contract between Gustine and ASG also contained the following pertinent provision:

Causes of action between the parties to this Agreement pertaining to acts or failures to act shall be deemed to have accrued and the applicable statutes of limitations shall commence to run not later than either the date of Substantial Completion for acts or failures to act occurring prior to Substantial Completion, or the date of issuance of the final Certificate for Payment for acts or failures to act occurring after Substantial Completion.

Contract, Article 9.3.

¶ 5 On September 8, 1993, ASG issued certificates that all structures in the mall were substantially completed. In April 1995, floor slabs in retail stores in the mall began to buckle, and cracks appeared in walls, sidewalks, and parking lots. Gus-tine averred that it was informed soon thereafter that these events were attributable to normal settlement routinely occurring in new construction. However, Gus-tine was aware that some of the April 1995 movement, specifically the heaving of a slab in a floor of one of the retail stores, probably was caused by subterranean earth movement. This admission is contained in paragraph 138 of its complaint. By early 1998, every building, sidewalk, and parking area in the mall had experienced damage from subsurface earth movement. In 1999, Gustine also discovered that certain contract specifications had not been met during the construction of one of the retail stores.

¶ 6 On July 30, 1999, Gustine instituted this action by writ of summons. Six months later, it filed a 357-paragraph complaint containing thirty counts against thirteen defendants involved in either pre-construction subsurface investigation, mall construction or both. The allegations included causes of action sounding in breach of contract and tort. Gustine sought damages for lost profits and for the cost of structural repairs to the mall. Some of the defendants, including ASG, filed preliminary objections based on application of the statute of limitations, arguing that the breach of contract claims were governed by a four-year statute of limitations and that the tort claims were governed by a two-year statute of limitations. Gustine countered that actions for latent defects involving contracts governing real estate construction were subject to a six-year statute of limitations. It also raised allegations against all of the defendants seeking dismissal on statute-of-limitations grounds that any applicable statute had been tolled by the discovery rule. As to some of those defendants, Gustine claimed that the repair doctrine also tolled the statute.

¶ 7 On July 18, 2000, the trial court entered an order rejecting the application of a six-year statute of limitations to the contract counts, but it specifically overruled all but one of the defendants’ requests to dismiss. That one defendant was ASG. In this July 18, 2000 order, the trial court observed that dismissal of all those defendants, except ASG, was unwarranted because the court could not determine, without further evidence, whether the discovery rule or repair doctrine operated to toll the applicable limitation periods. Thus, the trial court specifically reserved ruling on the merits of the statute-of-limitations defense as it realized that the two tolling doctrines might render the actions timely as to those defendants.

¶ 8 On that same date, the court entered a separate order regarding ASG. Based on the language in Article 9.3 of ASG’s contract with Gustine, ASG was dismissed outright as a party defendant. The trial court concluded that Article 9.3 fixed the *834 accrual date for both tort and contract claims by Gustine against ASG at September 8, 1993. Since this action was instituted after September 8,1997, the court ruled that the statute of limitations for claims against ASG had expired. In so ruling, the court implicitly found that neither tolling doctrine applied to ASG.

¶ 9 Gustine asked that the trial court certify its two July 18, 2000 orders for immediate appeal pursuant to Pa.R.A.P. 341(c). The court vacated its July 18, 2000 dismissals pending its consideration of the certification request. On September 14, 2000, the court reinstated its July 18, 2000 orders and also amended the orders to include a determination that an immediate appeal of both orders would facilitate resolution of the entire case, as required by Rule 341(c).

¶ 10 This Court accepted certification as to both orders and affirmed in part, reversed in part, and remanded. Gustine Uniontown Associates, Ltd. ex rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc., 786 A.2d 246 (Pa.Super.2001). We affirmed to the extent that the trial court applied a two-year limitations period to all counts involving fraud and negligence but reversed on the contract claims and held that a six-year statute-of-limitations period applied to contract actions alleging latent real estate construction defects. This ruling rendered the action timely as to ASG since it was commenced within six years of the September 8, 1993 certifications. We therefore did not ad-, dress the trial court’s conclusion that Gus-tine could not invoke the discovery or repair doctrines against ASG due to Article 9.3.

¶ 11 Our Supreme Court reversed as to the statute of limitations applicable to the contract counts, see Gustine Uniontown Associates, Ltd. v. Anthony Crane Rental, Inc., 577 Pa. 14,

Related

Boyle, E. v. Main Line Health
2025 Pa. Super. 148 (Superior Court of Pennsylvania, 2025)
Rahul Telang v. NVR Inc
Third Circuit, 2024
Pizza Zone, LLC v. Catalina Partners, L.P.
Superior Court of Pennsylvania, 2023
TELANG v. NVR, INC.
W.D. Pennsylvania, 2023
Com. v. Ledbetter, P.
Superior Court of Pennsylvania, 2023
Com. v. Jordan, H.
Superior Court of Pennsylvania, 2023
Com. v. Rickrode, W.
Superior Court of Pennsylvania, 2023
FARHANGUI v. GROSSINGER
E.D. Pennsylvania, 2021
RIAD v. WELLS FARGO BANK, N.A.
E.D. Pennsylvania, 2020
Com. v. Shareef, H.
Superior Court of Pennsylvania, 2020
Murray, K. v. American LaFrance,LLC
2020 Pa. Super. 149 (Superior Court of Pennsylvania, 2020)
Com. v. Dridi, M.
Superior Court of Pennsylvania, 2020
Quivers, S. v. Manzetti, G.
Superior Court of Pennsylvania, 2019
Charter Homes at Mill Creek v. Charlan Group
Superior Court of Pennsylvania, 2019
MR Hotels, LLC v. LLW Architects, Inc.
Court of Appeals of Tennessee, 2016
Carmen Enterprises, Inc. v. Murpenter, LLC
Superior Court of Pennsylvania, 2015
Opielski, B. v. Teeling, D.
Superior Court of Pennsylvania, 2015
Angino & Rovner, PC v. Santander Bank
Superior Court of Pennsylvania, 2015

Cite This Page — Counsel Stack

Bluebook (online)
892 A.2d 830, 2006 Pa. Super. 12, 2006 Pa. Super. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gustine-uniontown-associates-ltd-ex-rel-gustine-uniontown-inc-v-pasuperct-2006.