J.S. Riemer, Inc. v. The Village of Orland Hills

2013 IL App (1st) 120106
CourtAppellate Court of Illinois
DecidedMay 10, 2013
Docket1-12-0106
StatusPublished
Cited by10 cases

This text of 2013 IL App (1st) 120106 (J.S. Riemer, Inc. v. The Village of Orland Hills) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.S. Riemer, Inc. v. The Village of Orland Hills, 2013 IL App (1st) 120106 (Ill. Ct. App. 2013).

Opinion

ILLINOIS OFFICIAL REPORTS Appellate Court

J.S. Riemer, Inc. v. Village of Orland Hills, 2013 IL App (1st) 120106

Appellate Court J. S. RIEMER, INC., Plaintiff and Counterdefendant, v. THE VILLAGE Caption OF ORLAND HILLS, an Illinois Municipal Corporation, Defendant and Counterplaintiff and Third-Party Plaintiff-Appellant (Barclay and Associates, Third-Party Defendant-Appellee; Robert R. Slanker and Associates, Ltd., an Illinois Corporation, and Testing Service Corporation, an Indiana Corporation, Third-Party Defendants).

District & No. First District, Fifth Division Docket No. 1-12-0106

Filed May 10, 2013

Held In a village’s third-party complaint for fraud and breach of contract (Note: This syllabus against the architectural firm involved in the construction of village’s constitutes no part of community center, the trial court properly entered summary judgment for the opinion of the court the architect on the ground that the complaint was barred by the four-year but has been prepared statute of limitations for actions with regard to the design, management by the Reporter of or supervision of construction, notwithstanding the village’s contention Decisions for the that the firm was estopped from raising the statute of limitations and convenience of the fraudulently concealed the village’s cause of action by its reader.) misrepresentations that the excavator caused the building’s floor to sink into the ground, since a reasonable party in the village’s position would have been on notice that was caused by the architectural firm’s authorization of the inadequate excavation.

Decision Under Appeal from the Circuit Court of Cook County, No. 05-L-0595; the Hon. Review Sanjay T. Tailor, Judge, presiding.

Judgment Affirmed. Counsel on Mark Sterk, of Odelson & Sterk, Ltd., of Evergreen Park, and Michael J. Appeal Wall, of Rothschild, Barry & Myers LLP, of Chicago, for appellant.

Thomas B. Orlando, Douglas J. Palandech, and Garrett P. Kern, all of Foran Glennon Palandech Ponzi & Rudloff PC, of Chicago, for appellee.

Panel JUSTICE TAYLOR delivered the judgment of the court, with opinion. Justices Howse and Palmer concurred in the judgment and opinion.

OPINION

¶1 Plaintiff Village of Orland Hills (Village) appeals from the trial court’s grant of summary judgment for third-party defendant Jack Barclay & Associates (Barclay) pursuant to the four- year statute of limitations for actions concerning the design, management, or supervision of construction. ¶2 The Village hired Barclay to perform architectural services for the construction of a new community center building for the Village. The building was substantially completed by July 1, 2001. It is undisputed that the concrete floor of the building is sinking into the ground because it was built over peat, which is being compressed by the weight of the building. ¶3 The Village brought suit against Barclay on December 8, 2006, seeking damages for breach of contract and fraud. Barclay moved for summary judgment on grounds that the Village’s suit was time-barred. The trial court granted its motion. The Village now appeals, contending that Barclay is estopped from raising the statute of limitations because of certain alleged misrepresentations that it made to the Village. For the reasons that follow, we affirm the judgment of the trial court.

¶4 I. BACKGROUND ¶5 The following facts are undisputed for purposes of this appeal. Barclay is engaged in the business of providing professional architectural services. On September 16, 1999, the Village entered into a written contract with Barclay to perform architectural and design services in connection with the construction of a new community center. The contract between the Village and Barclay, which was modeled upon a standard form contract produced by the American Institute of Architects, contains the following provision (hereinafter Article 9.3): “9.3. Causes of action between the parties to this Agreement pertaining to acts or failures to act shall be deemed to have accrued and the applicable statutes of limitations shall commence to run not later than either the date of Substantial Completion for acts or failures to act occurring prior to Substantial Completion or the date of issuance of the final Certificate of Payment for acts or failures to act occurring after Substantial Completion.”

-2- ¶6 Barclay submitted plans and specifications to the Village which, among other things, called for certain excavation work to be done. The Village then hired J.S. Riemer, Inc. (Riemer), to perform the specified excavation work. Riemer excavated the project site on August 10 and 11, 2000. ¶7 The community center was substantially complete by July 1, 2001. However, as shall be detailed further below, it was subsequently discovered that the concrete floor of the building was sinking into the ground because it was built over peat that had not been excavated prior to the construction of the building. ¶8 On January 18, 2005, Riemer brought suit against the Village because it had not been paid in full for its excavation work. (We need not discuss the details of this suit, since Riemer is not a party to the instant appeal, nor is its liability at issue here. The only parties to the instant appeal are the Village and Barclay.) On April 15, 2005, the Village filed a counterclaim against Riemer, alleging that Riemer improperly excavated the project site. The Village also filed counterclaims against Robert R. Slanker & Associates, the construction manager, and Testing Service Corporation (TSC), a company which the Village hired to perform tests on the soil at the project site. ¶9 On December 8, 2006, more than five years after the date of substantial completion for the building, the Village filed a third-party action against Barclay. This action is the subject of the instant appeal. The Village’s second amended complaint, which frames the issues now before us, alleged the following. Under the terms of the parties’ contract, Barclay agreed to prepare drawings, plans, and specifications for the construction of the building, and Barclay also agreed to inspect the construction work in order to make sure that it complied with its plans and specifications. As part of this work, Barclay ordered that various soil tests be performed on the site. These tests showed that the building site contained extensive deposits of peat. However, according to the Village, Barclay’s plans and specifications for the building were defective in that they did not require the removal of all the peat from the site. Additionally, Riemer did not complete all the excavation work required by Barclay’s specifications, and Barclay was allegedly informed of this fact, but Barclay nevertheless gave its approval for the pouring of the concrete floor. ¶ 10 The Village further alleged that in the late summer of 2002, the concrete floor of the building began separating from the foundation walls and appeared to be sinking into the ground. When asked by the Village to give its opinion on the cause of the sinking floor, Barclay told the Village that it was the fault of the excavator Riemer for not compacting the earthwork and fill under the floor. Barclay also called for measurements to be made at various times from November 2002 to February 2005, measuring the depths to which the floor was sinking. A report by the soil testing company in March 2003 stated that the floor was located over “underlying unsuitable soils.” However, according to the Village, Barclay continued to deny that its design was defective and continued to blame Riemer for the problems with the building. The Village additionally alleged that, in reliance upon the expertise of Barclay, it pursued litigation against Riemer and against the construction manager but forbore to bring suit against Barclay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roder v. Equity One Investment Fund
Appellate Court of Illinois, 2026
Harrington v. Miller
2025 IL App (1st) 250004-U (Appellate Court of Illinois, 2025)
Montes v. Gomez-Pietrzyk
2024 IL App (1st) 231433-U (Appellate Court of Illinois, 2024)
Landers Children Family, LLC v. Rees
2024 IL App (4th) 230460-U (Appellate Court of Illinois, 2024)
Dalessandro v. Quinn-Dalessandro
2023 IL App (1st) 211119 (Appellate Court of Illinois, 2023)
Busbice v. Troutman Sanders, LLC
2021 IL App (1st) 200848-U (Appellate Court of Illinois, 2021)
Rocha v. FedEx Corp.
2020 IL App (1st) 190041 (Appellate Court of Illinois, 2021)
Malek v. Malek
N.D. Illinois, 2020
Smith v. Sterling National Bank
2020 IL App (1st) 190940-U (Appellate Court of Illinois, 2020)
Isenbergh v. South Chicago Nissan
2020 IL App (1st) 190849-U (Appellate Court of Illinois, 2020)
Diotallevi v. Diotallevi
2013 IL App (2d) 111297 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 IL App (1st) 120106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/js-riemer-inc-v-the-village-of-orland-hills-illappct-2013.