Gulf States Utilities v. PSC

633 So. 2d 1258
CourtSupreme Court of Louisiana
DecidedMarch 17, 1994
Docket92-CA-1185
StatusPublished
Cited by19 cases

This text of 633 So. 2d 1258 (Gulf States Utilities v. PSC) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf States Utilities v. PSC, 633 So. 2d 1258 (La. 1994).

Opinion

633 So.2d 1258 (1994)

GULF STATES UTILITIES COMPANY
v.
LOUISIANA PUBLIC SERVICE COMMISSION.

No. 92-CA-1185.

Supreme Court of Louisiana.

March 17, 1994.

*1259 Michael R. Fontham, Paul L. Zimmering, Noel J. Darce, Alex J. Peragine, Stone, Pigman, Walther, Wittman & Hutchinson, New Orleans, Carolyn DeVitis, Baton Rouge, for applicant.

Tom F. Phillips, James L. Ellis, Taylor, Porter, Brooks, & Phillips, Baton Rouge, Richard P. Ieyoub, Atty. Gen., Jack E. Yelverton, Central City, for respondent.

LEMMON, Justice[*].

This is a direct appeal by the Louisiana Public Service Commission (the Commission) from a judgment of the trial court in favor of Gulf States Utilities Company (GSU) reversing and vacating the portion of Order No. U-17282-H of the Commission which excluded GSU's recovery of certain items through the fuel adjustment charges to ratepayers.[1]

Facts

In the early 1980's, CITGO Petroleum Corporation, Conoco, Inc., and Vista Chemical, three industrial customers of GSU, were considering construction of cogeneration facilities for production of electricity and steam, using petroleum coke instead of natural gas as fuel for the generating units.[2] The industrial customers invited GSU to join in the project. Anxious to avoid the tremendous loss in revenue (perhaps $25 million annually) which would be caused by the departure of these industrial customers from the GSU system, as well as the resulting adverse impact on other customers,[3] GSU and the three industrial customers negotiated an agreement for a $200 million cogeneration construction project. Under the contract, GSU agreed to transfer its two oldest gas-fired electricity generation units at the Nelson station in Lake Charles to Nelson Industrial Steam Company (NISCO), a partnership to be formed between GSU and the three customers. In exchange for the transfer of ownership, NISCO obligated itself to pay GSU $6.35 million annually over the next twenty years.[4]

*1260 As part of the undertaking, GSU contracted to operate the units, being compensated for this service by NISCO, and to purchase the electricity produced, using the electricity to serve GSU's customers (including the three industrial participants). The industrial participants bound themselves to purchase their steam from NISCO and their electricity from GSU, and further agreed to invest approximately $150 million to convert the facility into a fluidized bed combustion plant capable of burning certain solid fuels, particularly petroleum coke which was abundantly available in the area.

The contract set forth a complex formula for calculating the price that GSU was to pay to NISCO for the purchase of electricity over the twenty-year period. This purchase price of electricity, which was calculated without reference to the "avoided cost,"[5] included an "asset fee" that represented NISCO's recoupment of the cost of purchasing the two Nelson units from GSU. Because the units had been constructed in 1959 for $38 million and GSU had recovered $29 million, between the time of construction and the 1986 NISCO contract, from ratepayers through depreciation in base rates, the depreciated book value of the units at the time of the transfer was $9 million. Therefore, a major portion of the $48 million purchase price by NISCO represented a "gain" for GSU over the depreciated book value of the units.

The basis of the dispute in this case is GSU's passing along to ratepayers, through the fuel adjustment clause,[6] that part of the "asset fee" which represented GSU's "gain." The Commission characterized this as "double payment" by the ratepayers for the cost of the Nelson units, contending that (1) GSU collected the initial $29 million depreciation from the ratepayers from 1960 to the date of NISCO purchase and (2) GSU was collecting a second time on that portion of the rates paid by ratepayers attributable to the part of the "asset fee" which was a "gain" for GSU from the sale of the units.

Order No. U-17414—Proceedings to Approve the NISCO Contract

In 1986 GSU filed an application with the Commission for approval of the proposed NISCO contract, as required by the Commission's rules governing the purchase of electricity by regulated utilities from qualifying cogeneration facilities.[7] The application, in which the three industrial participants intervened, specifically stated that the Commission's approval and acceptance of the rates for GSU's purchase from qualifying facilities was necessary for inclusion of the rates as a purchase power cost under the Commission's fuel adjustment order. GSU further represented that the arrangements were beneficial to GSU's retail customers and at least were preferable to loss of the three industrial customers. GSU asserted that it did not have the financial resources, by itself, to convert the two units to coke fuel.

The Commission ordered a public hearing before a hearing officer regarding GSU's application for approval of the NISCO contract. GSU's representative asserted that GSU would enjoy three advantages from its participation in the joint venture. First, GSU would retain the revenues that it had been receiving from the three industrial customers. Second, this was an opportunity for GSU to participate in new technology using low cost, locally produced fuel which is a by-product of petroleum refining.[8] Third, GSU *1261 was not required to put any cash into the project or incur any long term debt, since the industrial participants were to pay all costs of modifying the units.[9]

The Commission then conducted an open session meeting in July, 1987, at which discussions focused primarily on the benefits of the joint venture to other ratepayers. A report to the Commission by its economist noted that the rates of other ratepayers would be increased either by self-generation by the industrial participants or by the joint venture, but the latter increase would be offset somewhat by a fall in base rates. The economist noted that the other ratepayers not only would be hurt less in the short run by approval of the joint venture, but also would benefit in the long run from the joint venture.[10] At the end of the meeting, the Commission voted unanimously in favor of the NISCO project and issued Order No. U-17414, granting approval of the contract as written. The parties then executed the contract and began the project.

Order No. U-17282-H—Proceedings in GSU's Rate Application Involving Nuclear Plant

In November, 1989, GSU filed a rate increase application with the Commission relating to expenses associated with its River Bend nuclear plant, a facility unrelated to the NISCO venture. This rate increase application represented the third step of a court-mandated phase-in plan whereby the increases in GSU's rates related to the River Bend nuclear plant were to be implemented in annual increments over a five-year period. In determining the appropriateness of the requested rate increase, the Commission not only looked at the revenue picture for the River Bend nuclear project, but also examined GSU's other revenue, including that from the NISCO transaction.

After public hearings concerning the rate increase application, the Commission issued Order No. U-17282-H which included a requirement that the portion of the $6.35 million annual payment representing the "gain" received by GSU on the sale of the generating units to the NISCO joint venture be eliminated from the fuel adjustment clause in the rates charged to ratepayers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frith v. Southwest Ouachita Waterworks, Inc.
207 So. 3d 1121 (Louisiana Court of Appeal, 2016)
Henry v. Greater Ouachita Water Co.
207 So. 3d 1127 (Louisiana Court of Appeal, 2016)
Town of Sterlington v. Greater Ouachita Water Co.
149 So. 3d 952 (Louisiana Court of Appeal, 2014)
Luther v. Iom Co.
130 So. 3d 817 (Supreme Court of Louisiana, 2013)
Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Igal v. Brightstar Information Technology Group, Inc.
250 S.W.3d 78 (Texas Supreme Court, 2008)
Eagle Water, Inc. v. Louisiana Public Service Commission
947 So. 2d 28 (Supreme Court of Louisiana, 2007)
Showboat Star Partnership v. Slaughter
789 So. 2d 554 (Supreme Court of Louisiana, 2001)
Entergy Gulf States v. LPSC
730 So. 2d 890 (Supreme Court of Louisiana, 1999)
Humphrey v. Robertson
709 So. 2d 333 (Louisiana Court of Appeal, 1998)
Eicher v. LA. STATE POLICE, RIVERBOAT GAMING ENFOR. DIV.
710 So. 2d 799 (Louisiana Court of Appeal, 1998)
Global Tel Link, Inc. v. LA. PUBLIC SERVICE COM'N
707 So. 2d 28 (Supreme Court of Louisiana, 1998)
Gulf States Util. v. La. Pub. Serv. Com'n
689 So. 2d 1337 (Supreme Court of Louisiana, 1997)
Gulf States Utilities v. LA. PUBLIC SERV.
676 So. 2d 571 (Supreme Court of Louisiana, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
633 So. 2d 1258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-states-utilities-v-psc-la-1994.