John Stewart Gentry and Diana Gentry Breen d/b/a Richland Farm Partnership v. Northeast Louisiana Electric Power Cooperative, Inc.

CourtLouisiana Court of Appeal
DecidedOctober 1, 2025
Docket56,453-CA
StatusPublished

This text of John Stewart Gentry and Diana Gentry Breen d/b/a Richland Farm Partnership v. Northeast Louisiana Electric Power Cooperative, Inc. (John Stewart Gentry and Diana Gentry Breen d/b/a Richland Farm Partnership v. Northeast Louisiana Electric Power Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Stewart Gentry and Diana Gentry Breen d/b/a Richland Farm Partnership v. Northeast Louisiana Electric Power Cooperative, Inc., (La. Ct. App. 2025).

Opinion

Judgment rendered October 1, 2025. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 56,453-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

JOHN STEWART GENTRY AND Plaintiffs-Appellants DIANA GENTRY BREEN DOING BUSINESS AS RICHLAND FARM PARTNERSHIP

versus

NORTHEAST LOUISIANA Defendant-Appellee ELECTRIC POWER COOPERATIVE, INC.

Appealed from the Fifth Judicial District Court for the Parish of Richland, Louisiana Trial Court No. 46,023

Honorable Stephen Gayle Dean, Judge

JOHN C. LAIRD, APLC Counsel for By: John Carlton Laird Plaintiffs-Appellants

BREITHAUPT, DUBOS & WOLLESON, LLC By: Michael Lee DuBos Adam Roger Karamanis K. Lamar Walters, III JAMES WILLIS BERRY Counsel for Defendant-Appellee

COOK, YANCEY, KING & GALLOWAY, APLC By: Herschel Erskine Richard, Jr. John Tucker Kalmbach David Jonathan Hemken William Drew Burnham

KEAN MILLER LLP Counsel for By: Troy John Charpentier Defendant-Appellee, Energy Transfer Crude Oil Company, LLC

Before COX, HUNTER, and MARCOTTE, JJ. HUNTER, J.

Plaintiffs, John Stewart Gentry and Diana Gentry Breen, d/b/a

Richland Farm Partnership, appeal a district court’s judgment sustaining

exceptions of lack of subject matter jurisdiction, no cause of action, and no

right of action filed by defendant, Northeast Louisiana Electric Power

Cooperative, Inc. For the following reasons, we affirm in part, reverse in

part, and remand to the district court for further proceedings.

FACTS

Plaintiffs, John Stewart Gentry and Diana Gentry Breen, d/b/a

Richland Farm Partnership, are the owners of 260 acres of farmland located

at the corner of Louisiana Highway 183 and Mitchner Road in Richland

Parish. Northeast Louisiana Electric Power Cooperative, Inc. (“NELPCO”)

is an electrical power cooperative which supplies electricity to individuals,

families, and businesses in Northeast Louisiana.

On March 21, 1950, H. A. Gentry, plaintiffs’ predecessor in title,

granted to NELPCO a right of way servitude to “place, construct, operate,

repair, maintain, relocate, and replace” an electric transmission or

distribution line “including all anchors, anchor stubs and guy wires

necessary or advisable for the construction, operation, repair, and

maintenance of the said electric transmission or distribution in system[.]”

The servitude further provided, “In granting this easement, it is understood

that at pole locations, only a single pole and appurtenances will be used, and

that the location of the poles will be such as to form the least possible

interference to farm operations.” Thereafter, NELPCO constructed, and has

operated and maintained an electrical power line (“original Distribution

Line”) to distribute electricity to its customers. The distribution circuit was suspended along a line of wooden poles above and across plaintiffs’ property

(along La. Hwy 183 and Mitchner Road). For decades, the electrical system

was sufficient to meet the needs of the customers in the area.

In 2014, Energy Transfer Crude Oil Company, L.L.C. (“ETC”), began

constructing a new crude oil pipeline pumping facility in Epps, Louisiana.

The new facility requires a high voltage system, i.e., 115-kv, to supply

electricity to two 6,000 horsepower pumps. In 2015, NELPCO and ETC

entered into a “Cost Reimbursement Agreement,” whereby NELPCO would

construct, own, and operate the electrical power system upgrades necessary

to supply ETC’s facility with high voltage electricity. The reimbursement

agreement described the estimated costs for the design and construction of

the project, and ETC agreed to reimburse NELPCO for the costs. The

parties specifically agreed that NELPCO would own the facilities, and ETC

would own and be responsible for its own equipment and fixtures.

The plans for the services to ETC and the Agreement to Purchase

Power were submitted to the Louisiana Public Service Commission

(“LPSC”). The LPSC approved the service and issued a special tariff to

NELPCO for the sale of electricity to ETC’s facility. Pursuant to the tariff,

NELPCO agreed to “deliver services to the meter on [ETC’s] premises.”

The upgraded system, which was completed in 2016, begins at a new

NELPCO electric substation built in Holly Ridge, Louisiana, ends at ETC’s

facility in Epps, Louisiana, and it runs along the route of the existing right of

way on plaintiffs’ property. The distance between ETC’s facility, where the

meter is located, and NELPCO’s substation is 13 miles long. The relevant

upgrades included constructing new and taller metal power poles, which are

interspaced by shorter wooden power poles. Regarding plaintiffs’ property, 2 at some locations, the new poles were placed farther away from the highway,

some of which are as much as 12 feet from the centerline of the old wooden

poles. However, even with the addition of new metal poles, the upgraded

system remains a “single-pole system” and does not utilize “H frames” or

multi-footed utility towers.

On June 29, 2016, after construction of the new system commenced,

NELPCO and ETC entered into an Agreement for Purchase of Power.

Under this agreement, NELPCO would sell and deliver to ETC high-voltage

electricity necessitated by its pumping station in Epps. The rate schedule

was submitted to the LPSC and was later incorporated into the tariff

imposed by the LPSC. In accordance with the agreement and the tariff, the

“point of delivery” for NELPCO’s electrical services to ETC was the meter

installed at NELPCO’s substation in Holly Ridge.

On September 29, 2016, NELPCO began using the upgraded system

to deliver high-voltage electricity to ETC’s facility in Epps, and the system

has been operational since that date. According to NELPCO, plaintiffs were

aware of its activities, and its general manager remained in contact with

plaintiff, John Gentry, about the project. On August 16, 2016, after

construction was completed, NELPCO’s general manager met with Gentry

and his farmer, and the farmer executed a receipt and release for damage to

the property caused by the construction, including “crop damages” and “land

damages.”

On October 20, 2017, plaintiffs filed a petition for declaratory

judgment, injunctive relief, and damages. According to plaintiffs, the

upgraded system is separate and distinct from the original distribution line,

and the ETC/NELPCO plan required the original distribution line to be 3 replaced by a new 13.8kv distribution line (“New Distribution Line”). The

New Distribution Line and the Transmission Line require separate poles and

facilities, are separately metered, carry different loads (13.8kv, as opposed to

115kv), are subject to different standards, serve different functions, and

service different customers. Additionally, plaintiffs assert that the New

Distribution Line replaced the Original Distribution Line that distributed

electric power to NELPCO customers throughout the network. Contrarily,

the new Transmission Line only serves one customer, ETC, and delivers

electricity at a higher voltage than the Distribution Line. Consequently, the

actions of ETC and NELPCO have resulted in the construction of two lines

(the New Distribution Line and the Transmission Line), rather than one, on

plaintiffs’ property.

Plaintiffs also alleged that they did not authorize NELPCO to install

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skannal v. Bamburg
33 So. 3d 227 (Louisiana Court of Appeal, 2010)
Daily Advertiser v. TRANS-LA, ETC.
612 So. 2d 7 (Supreme Court of Louisiana, 1993)
City of New Orleans v. Bd. of Dir. of State Museum
739 So. 2d 748 (Supreme Court of Louisiana, 1999)
Gulf States Utilities v. PSC
633 So. 2d 1258 (Supreme Court of Louisiana, 1994)
Conoco, Inc. v. LA. PUBLIC SERVICE COM'N
520 So. 2d 404 (Supreme Court of Louisiana, 1988)
Central Louisiana Elec. Co. v. LA. PSC
601 So. 2d 1383 (Supreme Court of Louisiana, 1992)
Badeaux v. Southwest Computer Bureau, Inc.
929 So. 2d 1211 (Supreme Court of Louisiana, 2006)
Wagoner v. CHEVRON USA INC.
55 So. 3d 12 (Louisiana Court of Appeal, 2010)
Thornton v. Carthon
114 So. 3d 554 (Louisiana Court of Appeal, 2013)
Succession of Harrison
129 So. 3d 681 (Louisiana Court of Appeal, 2013)
Campbell v. Nexion Health at Claiborne, Inc.
149 So. 3d 436 (Louisiana Court of Appeal, 2014)
Town of Sterlington v. Greater Ouachita Water Co.
149 So. 3d 952 (Louisiana Court of Appeal, 2014)
Louisiana Workers' Compensation Corp. v. Gilligan
157 So. 3d 1111 (Supreme Court of Louisiana, 2015)
Skannall v. Bamburg, 2010-0707 (La. 5/28/10)
36 So. 3d 254 (Supreme Court of Louisiana, 2010)
Frith v. Southwest Ouachita Waterworks, Inc.
207 So. 3d 1121 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
John Stewart Gentry and Diana Gentry Breen d/b/a Richland Farm Partnership v. Northeast Louisiana Electric Power Cooperative, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-stewart-gentry-and-diana-gentry-breen-dba-richland-farm-partnership-lactapp-2025.