Gulf States Util. v. La. Pub. Serv. Com'n

689 So. 2d 1337, 1997 WL 76815
CourtSupreme Court of Louisiana
DecidedFebruary 25, 1997
Docket96-2046
StatusPublished
Cited by7 cases

This text of 689 So. 2d 1337 (Gulf States Util. v. La. Pub. Serv. Com'n) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf States Util. v. La. Pub. Serv. Com'n, 689 So. 2d 1337, 1997 WL 76815 (La. 1997).

Opinion

689 So.2d 1337 (1997)

GULF STATES UTILITIES COMPANY
v.
LOUISIANA PUBLIC SERVICE COMMISSION.

No. 96-2046.

Supreme Court of Louisiana.

February 25, 1997.

*1339 L. Richard Westerburg, Jr., Baton Rouge, J. Wayne Anderson, Margot Gallup Augustin, Stephen Thomas Perrien, Kimberly H. Despeaux, Kathryn J. Lichtenberg, New Orleans, for Applicant.

Laurie A. Barcelona, New Orleans, Brian Andrew Eddington, Baton Rouge, Michael R. Fontham, Wayne Lee, New Orleans, for Respondent.

CALOGERO, Chief Justice.[*]

This is a direct appeal by Gulf States Utility Company from a district court judgment which affirmed the Louisiana Public Service Commission's ordering $8.716 million in refunds to Gulf States' Louisiana-jurisdictional customers. The judgment of the district court, favoring the Commission, affirmed their Order No. U-20647 which commanded Gulf States to refund approximately $27.548 million to its Commission-jurisdictional customers. Of that amount, $13.7 million consists of a refund for overcharges from March 1, 1990 through March 31, 1994, ordered by this Court in Gulf States Utilities Co. v. Louisiana Pub. Serv. Comm., 92-CA-1185 (La.3/17/94), 633 So.2d 1258 [hereinafter NISCO]. Gulf States paid $13.1 million of that $13.7 million, but contests the remaining $600,000 [hereinafter $.6 million]. Of the other $13.848 million refund ordered, Gulf States contests $8.116 million,[1] consisting of $5.82 million in alleged fuel adjustment overcharges between October 1, 1988 and March 1, 1990, $1.85 million in imprudence disallowances, and $.446 million in interest on previously-refunded overcharges. *1340 The district court affirmed the Order, holding that Gulf States "failed to meet its hefty burden of proof and did not prove that the actions of LPSC were arbitrary, capricious or an abuse of authority." For the reasons that follow, we uphold the Commission's disallowance of $5.82 million in fuel adjustment overcharges for the period from October 1, 1988 to March 1, 1990, as well as the Commission's calculation on remand of the refund due for fuel adjustment overcharges from March 1, 1990 through March 31, 1994 at $13.7 million ($.6 million of which is contested by Gulf States). We further uphold the $1.85 million in imprudence disallowances assessed by the Commission. We reverse the Commission as to its order of $.446 million in interest on past refunds.

Background

In NISCO, this Court held that Gulf States had improperly obtained a double recovery of its investment in two gas-fired generation units that had been built in 1959 at a cost of $38 million. Of that $38 million investment, Gulf States had recovered approximately $29 million from its ratepayers through base rates by the year 1986, leaving a depreciated book value of approximately $9 million. In 1986, Gulf States sold the units to the Nelson Industrial Steam Co. ("NISCO") for a price that required payment by NISCO (and the receipt by Gulf States) of $127 million, $6.35 million per year over 20 years.

NISCO is a joint venture created in 1986 between Gulf States and three of its industrial customers. Pursuant to the joint venture agreement, Gulf States would still operate the units and be compensated therefor; NISCO would buy the steam and Gulf States the electricity which the units were to produce. The primary advantage to Gulf States in that transaction, aside from keeping the industrial customers' load on the Gulf States system, was that the units were to be converted, solely at the expense of the industrial participants, from the use of natural gas into a "fluidized bed combustion plant capable of burning certain solid fuels, particularly petroleum coke which was abundantly available in the area." NISCO, 633 So.2d at 1260. Fuel costs, and thus overall capacity costs, would thereby be lower as a result of the conversion. Though the costs of the conversion were borne entirely by the three industrial partners, Gulf States was nevertheless granted 1% ownership in the converted units.

In return for that 1% equity ownership in the units, Gulf States obligated itself to purchase the electricity produced by the same two units, using the electricity to serve Gulf States' customers (including the three industrial participants). The price to be paid for the electricity by Gulf States to NISCO included an annual "asset fee," by which Gulf States reimbursed NISCO for the amount NISCO paid to purchase the units. Pursuant to a complex pricing agreement, the cost of the electricity purchased by Gulf States from the NISCO partnership, including the "asset fee" paid by Gulf States to NISCO, was charged to ratepayers through Gulf States' fuel adjustment clause. So Gulf States' receipt of $6.35 million for each of 20 years (largely from the sale of the two units), coupled with their already having depreciated all but approximately $9 million of the $38 million cost of the two gas-fired generating units, represented a double recovery. In other words, Gulf States' ratepayers did not receive that portion of the $6.35 million per year representing Gulf States' gain on the transaction.[2]

Upon application by Gulf States, as required by Commission Order No. U-14964,[3]*1341 the Commission unanimously approved the NISCO contract in 1987 by Order No. U-17414, because it sought to avoid a rate increase for Gulf States' customers that would inevitably have resulted from the loss of the industrial partners' load on Gulf States' system, and because the contract allowed Gulf States to enjoy new technology and consequent lower capacity costs using low cost, locally-abundant fuel without having to bear any of the costs of the units' conversion to coke.

However, in a later, independent ratemaking proceeding prompted by Gulf States' request for a rate increase for expenses associated with a facility unrelated to the NISCO units,[4] the Commission determined that the NISCO transaction provided Gulf States with an impermissible double recovery of its investment in the two generators. According to the Commission, Gulf States impermissibly recovered its investment twice by charging to its ratepayers, through the fuel adjustment clause, the $6.35 million so-called "asset fee" [remember that this "asset fee" represents an annual reimbursement to the NISCO partnership of the annual amount it was to pay to purchase the units], after the ratepayers had already paid all but approximately $9 million of the units' depreciation through the base rates by the year 1986. By Order No. U-17282-H, the Commission required that the portion of the $6.35 million annual payment representing the "gain," calculated as described in footnote 2 hereinabove, received by Gulf States on the sale of the generating units be prospectively eliminated from the fuel adjustment clause in the rates charged to ratepayers. In the Order, the Commission explained its action:

The company [GSU] has recovered the vast majority of the costs associated with the Nelson units over their useful life through the inclusion of those units in rate base and recognition of the operating costs as cost of service expenses for ratemaking purposes. Gulf States is paying NISCO for all of the costs associated with the production of electricity from those plants. Included within those costs are the annual $6.35 million payments by the industrial customers to Gulf States. Therefore, although GSU is receiving payments of $6.35 million per year, its ratepayers are the ones actually absorbing that cost. Ratepayers are being penalized by this transaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Austal USA, LLC
195 So. 3d 980 (Court of Civil Appeals of Alabama, 2015)
Still v. Banktrust
88 So. 3d 845 (Court of Civil Appeals of Alabama, 2011)
Gordon v. Council of City of New Orleans
9 So. 3d 63 (Supreme Court of Louisiana, 2009)
Gordon v. Council of the City of New Orleans
977 So. 2d 212 (Louisiana Court of Appeal, 2008)
Entergy Gulf States v. LPSC
730 So. 2d 890 (Supreme Court of Louisiana, 1999)
Entergy Gulf States v. PUBLIC SERV. COM'N
726 So. 2d 870 (Supreme Court of Louisiana, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
689 So. 2d 1337, 1997 WL 76815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-states-util-v-la-pub-serv-comn-la-1997.