Grp. III Mgmt., Inc. v. Suncrete of Carolina, Inc.
Opinion
KONDUROS, J.:
*784**146Suncrete of Carolina, Inc. appeals the circuit court's order altering the previous circuit court order, which had granted Suncrete's motion to modify the arbitration award on the basis that the arbitrator erroneously relied on South Carolina law **147instead of North Carolina law when determining attorney's fees. We affirm.
FACTS/PROCEDURAL HISTORY
In October of 2012, Group III Management, Inc. entered into a construction contract with the Army Corps of Engineers for repairs, renovations, and upgrades to the Legion Pool Complex at Fort Jackson. The contract included removal of an existing swimming pool, construction of a new pool and deck, and construction of a building and other improvements. In November of 2012, Group III entered into a contract (the Contract) with Suncrete, which was doing business as Crystal Pools, for Suncrete to build the new swimming pool and deck for $339,960. The Contract included an arbitration clause, which specified the Federal Arbitration Act (FAA) applied to the agreement to arbitrate. The Contract also stated it was governed by North Carolina law. It further provided:
Should either party employ an attorney to institute suit or demand arbitration to enforce any of the provision hereof, to protect its interest in any matter under this Agreement, to collect damages for the breach of the Agreement, or to recover on a surety bond given by a party under this Agreement, the prevailing party shall be entitled to recover reasonable attorney's fees, costs, charges, and expenses expended or incurred therein.
Problems arose during construction, and Group III terminated Suncrete in March of 2013. On September 19, 2013, Group III filed a demand for arbitration against Suncrete, seeking to recover damages in the amount of $252,313.71 plus any other amounts to which it may be entitled from Suncrete's failure to complete work required by the Contract. Suncrete filed a counterclaim, alleging Group III owed it a balance under the Contract. Arbitration hearings were held in July of 2014. The arbitrator determined Suncrete was entitled to additional costs for certain services totaling $15,324.74, which were not included in Suncrete's counterclaim. The arbitrator determined Suncrete owed Group III a net amount of $81,138.03 after deducting the amount Group III owed Suncrete. Following the final hearing, the parties submitted affidavits regarding attorney's fees. On August 18, 2014, the arbitrator issued its determination, finding in favor of Group **148III in the amount of $197,304.09, of which $116,165.86 was for attorney's fees.1 The arbitrator did not award Suncrete damages for its counterclaim.
On September 8, 2014, Suncrete filed a motion with the arbitrator to modify the award to reduce or eliminate the attorney's fees portion of the award because the arbitrator failed to apply North Carolina law. The arbitrator denied the motion, finding "[t]he parties submitted to the [a]rbitrator the issue of determining the 'prevailing party' and the amount of reasonable attorney's fees that should be awarded to that party. That decision was carefully considered and made as set forth in the Award."
Group III filed a motion to confirm the arbitration award, but Suncrete filed a motion to vacate or modify the award; both motions were filed in the circuit court. Judge J. Ernest Kinard, Jr. heard the motions on February 6, 2015, and requested proposed orders. Judge Kinard issued an order dated April 23, 2015, granting Suncrete's motion to *785vacate the attorney's fees because under North Carolina law Group III was not the prevailing party because it did not recover at least 50% of the amount of damages it sought. There was a delay in the filing of the order, and Judge Kinard passed away on May 19, 2015, the day after the order was filed.2
Group III filed a motion to alter or amend pursuant to Rule 59(e), SCRCP, and Judge Tanya A. Gee heard the motion as the successor judge. Judge Gee determined she did not need to reach Suncrete's argument about whether North Carolina law would bar the attorney's fees based on the standard of review provided by the FAA requiring manifest disregard by the arbitrator, which must be more than a showing the arbitrator misconstrued the law. Judge Gee granted the motion and amended Judge Kinard's order to deny Suncrete's motion to modify or vacate the arbitration award and confirmed the arbitration award in full. This appeal followed.
**149LAW/ANALYSIS
I. Standard of Review of an Arbitration Award
Free access — add to your briefcase to read the full text and ask questions with AI
KONDUROS, J.:
*784**146Suncrete of Carolina, Inc. appeals the circuit court's order altering the previous circuit court order, which had granted Suncrete's motion to modify the arbitration award on the basis that the arbitrator erroneously relied on South Carolina law **147instead of North Carolina law when determining attorney's fees. We affirm.
FACTS/PROCEDURAL HISTORY
In October of 2012, Group III Management, Inc. entered into a construction contract with the Army Corps of Engineers for repairs, renovations, and upgrades to the Legion Pool Complex at Fort Jackson. The contract included removal of an existing swimming pool, construction of a new pool and deck, and construction of a building and other improvements. In November of 2012, Group III entered into a contract (the Contract) with Suncrete, which was doing business as Crystal Pools, for Suncrete to build the new swimming pool and deck for $339,960. The Contract included an arbitration clause, which specified the Federal Arbitration Act (FAA) applied to the agreement to arbitrate. The Contract also stated it was governed by North Carolina law. It further provided:
Should either party employ an attorney to institute suit or demand arbitration to enforce any of the provision hereof, to protect its interest in any matter under this Agreement, to collect damages for the breach of the Agreement, or to recover on a surety bond given by a party under this Agreement, the prevailing party shall be entitled to recover reasonable attorney's fees, costs, charges, and expenses expended or incurred therein.
Problems arose during construction, and Group III terminated Suncrete in March of 2013. On September 19, 2013, Group III filed a demand for arbitration against Suncrete, seeking to recover damages in the amount of $252,313.71 plus any other amounts to which it may be entitled from Suncrete's failure to complete work required by the Contract. Suncrete filed a counterclaim, alleging Group III owed it a balance under the Contract. Arbitration hearings were held in July of 2014. The arbitrator determined Suncrete was entitled to additional costs for certain services totaling $15,324.74, which were not included in Suncrete's counterclaim. The arbitrator determined Suncrete owed Group III a net amount of $81,138.03 after deducting the amount Group III owed Suncrete. Following the final hearing, the parties submitted affidavits regarding attorney's fees. On August 18, 2014, the arbitrator issued its determination, finding in favor of Group **148III in the amount of $197,304.09, of which $116,165.86 was for attorney's fees.1 The arbitrator did not award Suncrete damages for its counterclaim.
On September 8, 2014, Suncrete filed a motion with the arbitrator to modify the award to reduce or eliminate the attorney's fees portion of the award because the arbitrator failed to apply North Carolina law. The arbitrator denied the motion, finding "[t]he parties submitted to the [a]rbitrator the issue of determining the 'prevailing party' and the amount of reasonable attorney's fees that should be awarded to that party. That decision was carefully considered and made as set forth in the Award."
Group III filed a motion to confirm the arbitration award, but Suncrete filed a motion to vacate or modify the award; both motions were filed in the circuit court. Judge J. Ernest Kinard, Jr. heard the motions on February 6, 2015, and requested proposed orders. Judge Kinard issued an order dated April 23, 2015, granting Suncrete's motion to *785vacate the attorney's fees because under North Carolina law Group III was not the prevailing party because it did not recover at least 50% of the amount of damages it sought. There was a delay in the filing of the order, and Judge Kinard passed away on May 19, 2015, the day after the order was filed.2
Group III filed a motion to alter or amend pursuant to Rule 59(e), SCRCP, and Judge Tanya A. Gee heard the motion as the successor judge. Judge Gee determined she did not need to reach Suncrete's argument about whether North Carolina law would bar the attorney's fees based on the standard of review provided by the FAA requiring manifest disregard by the arbitrator, which must be more than a showing the arbitrator misconstrued the law. Judge Gee granted the motion and amended Judge Kinard's order to deny Suncrete's motion to modify or vacate the arbitration award and confirmed the arbitration award in full. This appeal followed.
**149LAW/ANALYSIS
I. Standard of Review of an Arbitration Award
"The [FAA] evidences the well-established federal policy favoring the arbitration of disputes." Trident Tech. Coll. v. Lucas & Stubbs, Ltd. ,
"[T]he scope of judicial review for an arbitrator's decision 'is among the narrowest known at law because to allow full scrutiny of such awards would frustrate the purpose of having arbitration at all ....' " Three S Del., Inc. v. DataQuick Info. Sys., Inc. ,
**150"Generally speaking, '[a]n award within the scope of submission is conclusive on fact issues and interpretation of law.' " Id. at 111,
"This circumscribed scope of review means that 'in reviewing [an arbitration] award, a district or appellate court is limited to determine whether the arbitrators did the job they were told to do-not whether they did it well, or correctly, or reasonably, but simply whether they did it.' " UBS Fin. Servs., Inc. ,
"Moreover, the arbitrators need not specify their reasoning or the basis of the award, ... so long as the factual inferences and legal conclusions supporting the award are 'barely colorable.' " Trident Tech. Coll. ,
"[A]n arbitration award fails to draw its essence from the agreement at issue 'when an arbitrator has disregarded or modified unambiguous contract provisions or based an award upon his own personal notions of right and wrong.' "
*787Choice Hotels Int'l, Inc. v. SM Prop. Mgmt., LLC ,
"Consequently, a court 'may vacate or modify an arbitration award only if one of the grounds specified in
(1) ... the award was procured by corruption, fraud, or undue means;
(2) ... there was evident partiality or corruption in the arbitrators, or either of them;
(3) ... the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced; or
(4) ... the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.
**153(a) ... there was an evident material miscalculation of figures or an evident material mistake in the description of any person, thing, or property referred to in the award.
(b) ... the arbitrators have awarded upon a matter not submitted to them, unless it is a matter not affecting the merits of the decision upon the matter submitted.
(c) ... the award is imperfect in matter of form not affecting the merits of the controversy.
II. Exceeding Authority
Suncrete maintains Judge Gee erred by granting the motion for reconsideration of Judge Kinard's order. It asserts the arbitrator's award exceeded the jurisdiction of the arbitrator because the arbitrator failed to apply the plain language of the agreement-to apply North Carolina law. We disagree.
"The question of whether the arbitrators exceeded their power relates to the arbitrability of the underlying dispute. An arbitrator exceeds his powers and authority when he attempts to resolve an issue that is not arbitrable because it is outside the scope of the arbitration agreement."
The Contract provided for attorney's fees. Accordingly, the decision to award attorney's fees was within the scope of the agreement between the parties. Therefore, the arbitrator did not exceed its powers in doing so. See Trident Tech. Coll. ,
III. Manifest Disregard
Suncrete contends Judge Gee erred in confirming the award because the arbitrator manifestly disregarded the law in awarding *788attorney's fees. It contends North Carolina law defines a prevailing party more strictly than South Carolina as a party who has obtained a judgment equal to at least 50% of his or her monetary claim and only a prevailing party can recover attorney's fees. Rather than decide if attorney's fees would be allowed under North Carolina law in the situation here, we instead look to whether the award of attorney's fees rises to the level of manifest disregard by the arbitrator. We find that it does not.
"Courts may vacate or modify an arbitration award only under the limited circumstances listed in the [FAA] or under the common law if the award 'fails to draw its essence from the contract' or 'evidences a manifest disregard of the law.' " UBS Fin. Servs., Inc. ,
In evaluating whether an arbitrator has manifestly disregarded the law, we have heretofore concluded that "a court's belief that an arbitrator misapplied the law will not justify vacation of an arbitral award. Rather, appellant is required to show that the arbitrators were aware of the law, understood it correctly, found it applicable to the case before them, and yet chose to ignore it in propounding their decision."
**156Three S Del., Inc. ,
A party challenging an arbitration award solely on the arbitrator's interpretation of applicable law does not meet the *789burden of demonstrating the arbitrator manifestly disregarded the law. Jones ,
In Trident Technical College , the appellant asserted "courts have not hesitated in appropriate cases to vacate an arbitration award" when a manifest disregard or perverse misconstruction of the law has occurred.
Suncrete maintains section 44A-35 of the North Carolina Code completely bars the recovery of attorney's fees in this case because Group III did not recover at least 50% of the amount of damages it sought. Section 44A-35 provides:
In any suit brought or defended under the provisions of Article 2 or Article 3 of this Chapter ,[4 ] the presiding judge may allow a reasonable attorney['s] fee to the attorney representing the prevailing party. ... For purposes of this **157section, "prevailing party " is a party plaintiff or third[-]party plaintiff who obtains a judgment of at least fifty percent (50%) of the monetary amount sought in a claim or is a party defendant or third[-]party defendant against whom a claim is asserted which results in a judgment of less than fifty percent (50%) of the amount sought in the claim defended .
N.C. Gen. Stat. Ann. § 44A-35 (2017) (emphases added).
Suncrete asserts North Carolina courts have applied section 44A-35 to cases other than for surety claims. See Terry's Floor Fashions, Inc. v. Crown Gen. Contractors, Inc. ,
Group III also points to the North Carolina statute regarding the award of attorney's fees in arbitration, which indicates: "An arbitrator may award reasonable expenses of arbitration if an award of expenses is authorized by law in a civil action involving the same claim or by the agreement of the parties to the arbitration proceeding."
The Contract provided that if a party utilized "an attorney to institute suit or demand arbitration to enforce any of the provision hereof ... [or] to collect damages for the breach of the Agreement, ... the prevailing party shall be entitled to recover reasonable attorney's fees, costs, charges, and expenses expended or incurred therein." Therefore, the Contract allowed the recovery of attorney's fees and it was within the arbitrator's authority to award them. See Eljer Mfg., Inc. v. Kowin Dev. Corp. ,
Judge Gee did not err in granting Group III's motion for reconsideration and reinstating the arbitrator's award of attorney's fees. The federal courts have vacated arbitration awards when the arbitrator demonstrates a manifest disregard of the law. Therefore, we need only determine whether **159the arbitrator manifestly disregarded the law in light of section 44A-35, which provides a prevailing party can be awarded an attorney's fee and defining a prevailing party as a plaintiff who recovers 50% or more of monetary damages sought or a defendant who is found liable for less than 50% of the damages sought. Because section 44A-35 begins with the statement "[i]n any suit brought or defended under the provisions of Article 2 or Article 3 of this Chapter," which apply to liens and state bonds, Group III's argument this section would not apply to the case here is reasonable. See § 44A-35. Thus, the legal principle Suncrete contends the arbitrator failed to apply is not clearly defined and is subject to reasonable debate. See Jones ,
If the arbitrator erred by not applying North Carolina law or applying North Carolina law incorrectly, such error does not rise to the level of manifest disregard of the law.
*791See Trident Tech. Coll. ,
IV. Reduction in Attorney's Fees
Suncrete also contends North Carolina law does not allow a party to recover attorney's fees exceeding the monetary damages award. It argues that because the award of attorney's fees was more than the damages recovered, the award violates section 6-21.6(b). However, at oral arguments, Suncrete stated it was no longer arguing this statute on appeal because it was instead relying on its argument the attorney's fees should not have been awarded at all because Group III was not a prevailing party.
At the time of arbitration, section 6-21.6(b) provided in part, "In any suit, action, proceeding, or arbitration primarily for the recovery of monetary damages, the award of reasonable attorney['s] fees may not exceed the monetary damages awarded."
Because Suncrete abandoned at oral arguments its contention that subsection 6-21.6(b) limits the amount of attorney's **161fees to the amount recovered in damages, we do not address whether the arbitrator's decision to award attorney's fees more than the amount of damages in light of this statute rises to the level of manifest disregard. See State v. Oglesby ,
CONCLUSION
Judge Gee's granting Group III's motion to reconsider and reinstating the arbitration award is
AFFIRMED.
LOCKEMY, C.J., and WILLIAMS, J., concur.
Footnotes
819 S.E.2d 781 (Grp. III Mgmt., Inc. v. Suncrete of Carolina, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.