TCC of Charleston, Inc. v. Concord and Cumberland, LLC

CourtCourt of Appeals of South Carolina
DecidedJuly 30, 2025
Docket2021-000272
StatusPublished

This text of TCC of Charleston, Inc. v. Concord and Cumberland, LLC (TCC of Charleston, Inc. v. Concord and Cumberland, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TCC of Charleston, Inc. v. Concord and Cumberland, LLC, (S.C. Ct. App. 2025).

Opinion

THE STATE OF SOUTH CAROLINA In The Court of Appeals

TCC of Charleston, Inc., Appellant/Respondent,

v.

Concord and Cumberland, LLC, Concord & Cumberland HPR, Leo Hall, Diane Hall, Bea H. Smith, Margaret C. Pope, William D. Foster, Jr., Gene G. Foster, Mattison J. MacGillivray, Teresa MacGillivray, Pamela L. Vaughn, Nelia A. Patricio, Trustee of the Nelia A. Patricio Revocable Trust Agreement, Stuart D. Reeves, Edward T. Strom, Barbara K. Henderson, James R. Clarke, Paul A. Brim, Robert K. Seidl, Jennifer M. Seidl, Robert Kenneth Seidl, II, M. Bert Storey, Thomas R. Mather, Edward T. Strom, 304 Concord & Cumberland, LLC, Marion M. Simpson f/k/a Marion Moore McDonald Simpson, Kathy Gardner, Gregory J. Gardner, Freeman Waterfront Properties, LLC, Jo-Ann Cooper, Betty Y. Segal, Robert M. Levin, and Bonita K. Levin, Donald D. Leonard, Betty L. Beatty, Mattellen, LLC, and Thomas R. Debnam, Trustee of the Trust Agreement of Thomas R. Debnam, Respondents,

Of which Concord & Cumberland HPR is the Respondent/Appellant.

Appellate Case No. 2021-000272

Appeal From Charleston County Mikell R. Scarborough, Master-in-Equity

Opinion No. 6106 Heard June 11, 2024 – Filed March 19, 2025 AFFIRMED IN PART, REVERSED IN PART, AND REMANDED

Jaan Gunnar Rannik, of Epting & Rannik, LLC; and Michelle N. Endemann, both of Charleston, for TCC of Charleston, Inc.

F. Cordes Ford, IV, of Womble Bond Dickinson (US) LLP, of Charleston, for Concord and Cumberland, LLC; Leo Hall; Diane Hall; Bea H. Smith; Margaret C. Pope; William D. Foster; Jr., Donald D. Leonard; Mattellen, LLC; Thomas R. Debnam; Gregory J. Gardner; Freeman Waterfront Properties, LLC; Jo-Ann Cooper; Betty Y. Segal; Robert M. Levin; Bonita K. Levin; Robert Kenneth Seidl, II; M. Bert Storey; Thomas R. Mather; 304 Concord & Cumberland, LLC; Marion M. Simpson; Kathy Gardner; Edward T. Strom; Barbara K. Henderson; James R. Clarke; Paul A. Brim; Robert K. Seidl; Jennifer M. Seidl; Gene G. Foster; Mattison J. MacGillivray; Teresa MacGillivray; Pamela L. Vaughn; Nelia A. Patricio; and Stuart D. Reeves.

Robert Andrew Walden, of Womble Bond Dickinson (US) LLP, of Charleston, for Concord and Cumberland HPR.

William Cole Shannon, of Charleston; Edward D. Buckley, Jr. and Russell Grainger Hines, of Clement Rivers, LLP, of Charleston; all for Betty L. Beatty.

W. Siau Barr, Jr., of Clement Rivers, LLP, of Charleston, for 304 Concord & Cumberland, LLC and Betty L. Beatty.

VINSON, J.: TCC of Charleston, Inc. (TCC) appeals the master-in-equity's (the master's) order denying its motions to amend a statement of account and for attorney's fees and granting its motion to confirm an arbitration award. It also appeals the master's order granting the motion for summary judgment, motion for dismissal, motion to deposit funds, and motion for attorney's fees filed by Concord & Cumberland Horizontal Property Regime (the HPR) and individual unit owners of a condominium owned by the HPR. TCC appeals the master's orders granting partial summary judgment and awarding attorney's fees to Betty Beatty, an individual who owned one of the units in the condominium, and awarding attorney's fees to unit owners other than Beatty. TCC argues the master erred in (1) finding TCC's mechanic's lien was not timely served and dissolving the mechanic's lien due to an error on the statement of account, (2) not allowing discovery before dismissing the lien, (3) holding the HPR's deposit of a judgment into court stopped interest from accruing, (4) denying TCC's motion for attorney's fees, and (5) granting attorney's fees to the HPR. The HPR cross appealed, arguing the master erred in granting TCC's motion to confirm the arbitration award, which the HPR asserts occurred after the circuit court erred in failing to vacate or modify TCC's arbitration award, because the arbitration panel disregarded a sworn lien waiver and release when issuing its award to TCC, failed to issue a reasoned award, and allocated a portion of the award to a project that was not part of TCC's claim. We affirm the master's order granting the HPR's motions to dismiss and for summary judgment, granting TCC's motion to confirm the arbitration award, and denying TCC's motions to amend statement of account and for attorney's fees. We also affirm the Master's order granting summary judgment to Beatty. We reverse and remand the master's award of attorney's fees to the HPR and to Beatty. FACTS AND PROCEDURAL HISTORY This appeal arises from a repair project at condominiums located at 175 Concord Street in Charleston. The HPR, which owned the condominiums, hired TCC as the general contractor on the project. On February 27, 2014, the HPR and TCC signed a contract with a guaranteed maximum price (GMP) of $3,923,939.00. Once work on the project began, TCC discovered that the condition of the condominium differed from what TCC contemplated when it submitted its bid, and TCC requested 134 proposed change orders (PCOs) during the course of the work. The HPR paid $1,953,145.00 of the amount billed in the PCOs, which increased the total price of the project to $5,877,084.00 by February 2016. The HPR paid the PCOs on a cost-plus basis.1

1 "Cost-plus" meaning the HPR would pay TCC the cost of its services and an additional amount for profit. On June 6, 2016, TCC filed a complaint for foreclosure of mechanic's lien, breach of contract, and quantum meruit against the HPR. TCC also filed a lis pendens, notice of mechanic's lien, a statement of account, and a motion to compel arbitration. TCC requested $2,385,503.57 plus interest for labor and materials used on the project and unpaid by the HPR. This amount arose from Payment Application 18, a payment application being a request for payment for ongoing work. Both the complaint and the statement of account, which TCC president John David Griffith signed, stated the last day of work on the project was March 17, 2016. On June 10, 2016, TCC filed an amended complaint and notice of mechanic's lien along with the original statement of account against the HPR and the individual unit owners. The amended complaint and statement of account added the unit owners as parties and stated the last day of work on the project was March 17, 2016. An amended lis pendens was filed June 16, 2016. An affidavit of service shows that Beatty was served with the lis pendens, complaint, and notice of the mechanic's lien on June 22, 2016.

The HPR filed an answer to the amended complaint, but it agreed to arbitration pursuant to its contract with TCC. On December 30, 2016, the circuit court entered a consent order staying the action and allowing arbitration to proceed between the HPR and TCC. The arbitration panel conducted a merits hearing in January 2019, and the parties submitted proposed orders. On April 16, 2019, the arbitration panel issued the arbitration award finding TCC "performed additional work outside the scope of the work which was not approved and was not paid," and that TCC was entitled to payment for PCOs 143, 144, 144R, and unpaid retainage. The panel awarded TCC $2,023,074.45 for the claims asserted in the arbitration proceeding.

TCC filed a motion for prejudgment interest, costs of arbitration, and attorney's fees and costs, along with affidavits from its counsel. The HPR filed a motion for reconsideration, arguing the form of the award was improper because the panel failed to issue a reasoned award.2 The HPR also contended no agreements between the parties amended their contract to change its form from a GMP to a cost-plus contract, and therefore "no reliable evidence . . . exists between the

2 Tully Constr. Co./A.J. Pegno Constr. Co., J.V. v. Canam Steel Corp., No. 13 CIV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cat Charter, LLC v. Schurtenberger
646 F.3d 836 (Eleventh Circuit, 2011)
Sealy v. Dodge
347 S.E.2d 504 (Supreme Court of South Carolina, 1986)
Sunrise Savings & Loan Ass'n v. Mariner's Cay Development Corp.
367 S.E.2d 696 (Supreme Court of South Carolina, 1988)
Blumberg v. Nealco, Inc.
427 S.E.2d 659 (Supreme Court of South Carolina, 1993)
Byers v. Westinghouse Electric Corp.
425 S.E.2d 23 (Supreme Court of South Carolina, 1992)
Jackson v. Speed
486 S.E.2d 750 (Supreme Court of South Carolina, 1997)
Capital City Insurance v. BP Staff, Inc.
674 S.E.2d 524 (Court of Appeals of South Carolina, 2009)
Shelley Construction Co. v. Sea Garden Homes, Inc.
336 S.E.2d 488 (Court of Appeals of South Carolina, 1985)
Preferred Savings & Loan Ass'n v. Royal Garden Resort, Inc.
368 S.E.2d 78 (Court of Appeals of South Carolina, 1988)
Zabinski v. Bright Acres Associates
553 S.E.2d 110 (Supreme Court of South Carolina, 2001)
PREFERRED SAVINGS & LOAN ASSOCIATION, INC. v. Royal Garden Resort, Inc.
389 S.E.2d 853 (Supreme Court of South Carolina, 1990)
Gissel v. Hart
676 S.E.2d 320 (Supreme Court of South Carolina, 2009)
Kiriakides v. SCH. DIST. OF GREENVILLE
675 S.E.2d 439 (Supreme Court of South Carolina, 2009)
Griffith v. Griffith
506 S.E.2d 526 (Court of Appeals of South Carolina, 1998)
Strickland v. General Building & Masonry Contractors, Inc.
207 S.E.2d 399 (Court of Appeals of North Carolina, 1974)
Layman v. State
658 S.E.2d 320 (Supreme Court of South Carolina, 2008)
Sides v. Greenville Hospital System
607 S.E.2d 362 (Court of Appeals of South Carolina, 2004)
South Carolina Department of Transportation v. Revels
766 S.E.2d 700 (Supreme Court of South Carolina, 2014)
Laverne Jones v. Bernaldo Dancel
792 F.3d 395 (Fourth Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
TCC of Charleston, Inc. v. Concord and Cumberland, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tcc-of-charleston-inc-v-concord-and-cumberland-llc-scctapp-2025.