Greenwood v. New Hampshire Public Utilities Com'n

527 F.3d 8, 2008 U.S. App. LEXIS 10451, 2008 WL 2057423
CourtCourt of Appeals for the First Circuit
DecidedMay 15, 2008
Docket07-2322
StatusPublished
Cited by16 cases

This text of 527 F.3d 8 (Greenwood v. New Hampshire Public Utilities Com'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenwood v. New Hampshire Public Utilities Com'n, 527 F.3d 8, 2008 U.S. App. LEXIS 10451, 2008 WL 2057423 (1st Cir. 2008).

Opinion

LYNCH, Circuit Judge.

This case was brought by the owner of a small renewable hydroelectricity producing company, Alden Greenwood, who in 2006 sued the New Hampshire Public Utilities Commission (“PUC”) over an order the PUC had issued more than seventeen years earlier in May of 1988 (and declined to reconsider in later orders). The PUC said it issued the order under section 210 of the Public Utility Regulatory Policies Act (“PURPA” or “the Act”) of 1978, 16 U.S.C. § 824a-3. The 1988 order rescinded the final ten years of a thirty-year (1985-2015) rate schedule which the PUC had earlier approved in an order it issued in 1985.

The district court in 2007 enjoined the PUC from enforcing its 1988 order, in effect reinstating the final ten years of the original rate schedule, which had approved terms favorable to Greenwood in its contract with the Public Service Company of New Hampshire. Greenwood v. N.H. Pub. Utils. Comm’n, No. 06-cv-270, 2007 WL 2108950 (D.N.H. July 19, 2007). The underlying amount involved is at least $4.3 million.

We reverse and order dismissal of the case.

I.

In 1978, in the midst of a nationwide energy crisis, Congress passed PURPA, a series of measures designed to reduce the nation’s dependence on fossil fuels. See FERC v. Mississippi, 456 U.S. 742, 745-46, 102 S.Ct. 2126, 72 L.Ed.2d 532 (1982). Section 210 of PURPA sought to “encourage the development of cogeneration and small power production facilities.” Id. at 750, 102 S.Ct. 2126; see 16 U.S.C. § 824a-3(a). Congress felt “that two problems impeded the development of nontraditional generating facilities: (1) traditional electricity utilities were reluctant to purchase power from, and to sell power to, the nontraditional facilities, and (2) the regulation of these alternative energy sources by state and federal utility authorities imposed financial burdens upon the nontraditional facilities and thus discouraged their development.” FERC, 456 U.S. at 750-51, 102 S.Ct. 2126. The Act required the Federal Energy Regulatory Commission (“FERC” or “the Commission”) to promulgate rules implementing the statute, in particular, rules requiring utilities to enter into purchase and sale agreements with qualifying cogeneration and small power production facilities (“QFs”). 16 U.S.C. § 824a-3(a); see id. § 796(17)-(18) (defining QFs). These rules, which regulate the rates of purchase and sale, are to be implemented by state utilities commissions. Id. § 824a—3(f)(1); see FERC, 456 U.S. at 751, 102 S.Ct. 2126. PURPA requires FERC to prescribe rules exempting QFs from certain state and federal energy regulations. 16 U.S.C. § 824a-3(e); FERC, 456 U.S. at 751, 102 S.Ct. 2126. 1

*11 The constitutionality of PURPA, including specifically the role of state agencies in implementing the FERC rules, was upheld by the Supreme Court. See FERC, 456 U.S. at 758-61, 102 S.Ct. 2126.

In 1984, in order to “fulfill[ ] the [PUC’s] responsibility under PURPA to set just and reasonable rates for sales of electric power to public utilities,” the New Hampshire PUC issued a generic rate order “updating and establishing the short term and long term rates to be paid by Public Service Company of New Hampshire ... to small power producers and cogenera-tors.” Re Small Energy Producers and Cogenerators (Order No. 17,104), 69 N.H.P.U.C. 352, 353, 356 (July 5, 1984) [hereinafter “Generic Rate Order”].

In August 1985, the PUC approved Greenwood’s 2 application under the Generic Rate Order for a thirty-year, long-term avoided cost rate structure, from September 13, 1985 through September 13, 2015, for Greenwood’s three 150-kilowatt hydroelectric plants: Waterloom Falls, Otis Falls, and Chamberlain Falls. Alden T. Greenwood d/b/a Alden Eng’g Co. (Order No. 17,814), — N.H.P.U.C. - (Aug. 13, 1985). All three plants are QFs for the purposes of PURPA. As a result of this rate approval, Greenwood and the Public Service Company of New Hampshire (“PSNH”) entered into interconnection agreements under which PSNH agreed to compensate Greenwood for electricity produced by those three plants at the rate provided in the PUC Generic Rate Order and Greenwood’s approval order. This meant PSNH would pay Greenwood approximately $0.06 per kilowatt-hour of electricity generated by his three plants in the first year, and that rate would increase each year, culminating in a rate of $0.7174 per kilowatt-hour in the thirtieth year. 3 PSNH would also pay capacity charges increasing from $56.07 per kilowatt-year in the first year to $367.70 per kilowatt-year in the final year.

In May of 1988, the PUC reconsidered its 1985 order. Re Alden T. Greenwood (Order No. 19,095), 73 N.H.P.U.C. 228 (May 19, 1988). It concluded that it had made a mistake in the 1985 order, and that it had not, as PURPA and the FERC rules required, treated Greenwood’s three QFs in a manner “consistent ... for -facilities that are similarly circumstanced.” Id. at 229. In addition, its 1985 rate design was “not just and reasonable to the electric consumers of the electric utility and in the public interest, as required by PURPA and the FERC rules.” Id. Thus, the PUC’s stated reason for altering the earlier order was that it was required to do so to comply with the federal PURPA statute and the FERC regulations. The PUC rescinded the final ten years of the 1985 rate order applicable to Greenwood’s three plants, reducing it to twenty years. Id. This meant Greenwood lost the previously approved rate for the ten-year period from September 2005 through September 2015 in his contract with PSNH. Greenwood, of course, had no contract with the PUC.

When Greenwood learned of the 1988 rescission order, he moved for reconsideration before the PUC and was given a hearing on November 28, 1988. Following that hearing, the PUC on December 9, 1988 issued Order Number 19,257, denying Greenwood’s motion for reconsideration. Re Alden T. Greenwood, d/b/a Alden Eng’g *12 Co. (Order No. 19,257), 73 N.H.P.U.C. 504 (Dec. 9, 1988). Greenwood did not at that time challenge the authority of the PUC to enter the 1988 rescission order. Nor did he claim the order was preempted by or inconsistent with PURPA. To the contrary, the PUC found that at the hearing Greenwood “conceded that the commission had acted within its authority in issuing the rescission order, and did not contest the merits of the order.” Id. Accordingly, the PUC let stand its 1988 order rescinding the last ten years of Greenwood’s rate order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lamartina v. VMware, Inc.
N.D. California, 2021
United States v. Bryant Pouncy
Eleventh Circuit, 2021
Young v. Perdue
District of Columbia, 2020
Allco Renewable Energy Ltd. v. Massachusetts Electric Co.
208 F. Supp. 3d 390 (D. Massachusetts, 2016)
Riggs v. Curran
196 F. Supp. 3d 338 (D. Rhode Island, 2016)
Mercado v. Government of PR
814 F.3d 581 (First Circuit, 2016)
Randall v. LACONIA, NH
679 F.3d 1 (First Circuit, 2012)
Yacovi v. Rubin & Rudman
411 F. App'x 342 (First Circuit, 2011)
Hecking v. Barger, et al.
2010 DNH 032 (D. New Hampshire, 2010)
Gorelik v. Costin
2008 DNH 217 (D. New Hampshire, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
527 F.3d 8, 2008 U.S. App. LEXIS 10451, 2008 WL 2057423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenwood-v-new-hampshire-public-utilities-comn-ca1-2008.