Green v. KEY CUSTOM HOMES, INC.

692 S.E.2d 56, 302 Ga. App. 800, 2010 Fulton County D. Rep. 925, 2010 Ga. App. LEXIS 236
CourtCourt of Appeals of Georgia
DecidedMarch 11, 2010
DocketA09A1912
StatusPublished
Cited by9 cases

This text of 692 S.E.2d 56 (Green v. KEY CUSTOM HOMES, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green v. KEY CUSTOM HOMES, INC., 692 S.E.2d 56, 302 Ga. App. 800, 2010 Fulton County D. Rep. 925, 2010 Ga. App. LEXIS 236 (Ga. Ct. App. 2010).

Opinion

Adams, Judge.

Robert W and Heather J. Green brought a claim for breach of contract against Key Custom Homes, Inc. d/b/a Key Custom Homes (“KCH”), arising out of the construction of their home. 1 KCH counterclaimed, alleging that it was the Greens who breached the parties’ contract. 2 The jury found in favor of KCH, and the Greens appeal from the trial court’s denial of their motion for new trial.

Michele and Randy Edmondson are the owners and officers of KCH. Prior to the events at issue, the Greens rented a house from the Edmondsons, and the two couples were friends. In 2006, the Edmondsons agreed to sell the Greens land for the construction of a home, and the parties signed a Real Estate Sales Contract for the land on or about June 16, 2006 (the “Sales Contract”). The Sales Contract provided that KCH would “build the Greens[’] home on their lot at the cost of building the house plus 10% ” and further specified that “all costs related to building the home will be disclosed between both parties, the buyer and the seller. ...”

On or about July 18, 2006, the parties entered into a second agreement for the construction of the Greens’ home (the “Construction Agreement”), which provided that the Greens would pay the cost of building and would also pay KCH “for the performance of work and furnishing of materials, under this Agreement the sum of . .. 10% of [the] cost to build [the] house.” The agreement estimated this amount at $17,147.20 to be paid in four installments: (1) 60 percent to be paid after the foundation was poured; (2) 20 percent at the “dry in phase (roof on house w-shingles)”; (3) 10 percent when the sheet rock was hung; and 4) the balance when the county issued *801 the approval on final inspection. The Construction Agreement provided that subcontractors and suppliers would be paid by the Greens from draws on their construction loan. KCH was required to review all invoices before requesting a draw, and the Greens were required to pay KCH within 24 hours in order to comply with “the requirement of the builder to pay the suppliers and the subcontractors on a prompt payment schedule.”

Shortly after construction began, the Greens began to have concerns about how the draw payments were handled. Michele Edmondson worked directly with the Greens on the project, and she submitted the draw requests to them. The Greens asked Michele to provide detailed supplier/subcontractor invoices so they could verify the amount of the draws, but they assert that she was disorganized and inconsistent about providing the back-up documentation. Nevertheless, between the months of June and November 2006, the Greens asserted that they paid KCH a total of $152,758.10.

Michele Edmondson testified that she worked to provide documentation and invoices to support the draw requests, but the Greens wanted detailed information beyond that normally provided by suppliers and subcontractors. Moreover, the Greens were late in paying KCH, and on occasion she had to pay subcontractors out of her own funds or carry balances. For example, the first subcontractor submitted a request on or about August 2 for a $3,000 draw, but the Greens did not pay within the required 24-hour period because they did not want to dip into their savings. Michele paid the subcontractor herself, and was reimbursed later. The Construction Agreement also required the Greens to pay KCH the first installment of 60 percent after the foundation was poured on August 11, 2006, but Michele did not receive payment in full until September 6.

Things came to a head on or about November 9 when the Greens balked at paying a $10,000 draw request without seeing invoices to verify the amount. The Greens contend that because Michele never provided sufficient back-up documentation for the draw, which they assert was a breach of the parties’ contracts, they refused to pay. But Michele said that the Greens would not accept the standard documentation, which is usually priced out by square footage. Instead, the Greens wanted to know “how many screws, how many rolls of tape” and “how many buckets of mud” the drywall contractor intended to use in the house before they would pay anything. Michele attempted to get more detailed information for them, and even personally guaranteed payment for the drywall in order to complete the house. She also allowed the drywall contractor to use water from a lot she owned because the Greens had padlocked the water outlets on their lots to prevent anyone from stealing their water. Moreover, Michele said that the Greens began paying suppliers directly and did *802 not always give her information about what they had paid, resulting in confusion about the amounts outstanding.

When the $10,000 payment was not forthcoming, KCH made a formal written demand on November 21, 2006, for the amounts Michele believed the Greens owed under the Construction Agreement. The Greens, in turn, terminated KCH’s services on November 27. And on November 30, 2006, KCH filed a lien on the Greens’ home because the accounts for the subcontractors were in KCH’s name and Michele Edmondson was unclear as to what had been paid. The Greens filed this lawsuit in March 2007.

At trial, the Greens calculated that KCH had paid $122,938.05 in connection with the construction of their home, and conceded that KCH was entitled to an additional ten percent of that figure, or $12,293.81. Additionally, the Greens paid $60,474.76 directly to subcontractors and suppliers while KCH was working on the house. They acknowledged that under the Construction Agreement, KCH is entitled to ten percent of that amount, or $6,047.48. The Greens contended, therefore, that KCH was entitled to a total of $141,279.34, but because they actually paid KCH $152,758.10, KCH was overpaid and owed them $11,478.76 under the Construction Agreement.

KCH argued, however, that it was entitled to ten percent of the amount spent to complete the house, even after the Greens terminated its services. KCH’s documentation indicated that the Greens’ house cost a total of $273,464.36, entitling them to a fee of $27,346.44. When the payments were netted out and additional damages included for equipment repairs during construction, KCH calculated its damages at $3,937.30.

After the jury awarded KCH $9,047 in compensatory damages, and $23,000 in attorney fees, the Greens moved for a new trial, which the trial court denied following a hearing.

1. The Greens contend that the trial court erred in denying their motion for a new trial because there was no evidence to support the verdict.

Where a jury returns a verdict, the same must be affirmed on appeal if there is any evidence to support it, and the evidence is to be construed in a light most favorable to the prevailing party with every presumption and inference in favor of sustaining the verdict. We review a denial of a motion for a new trial according to this same standard.

(Citations omitted.) R. O. C. v. Estate of Bryant, 279 Ga. App. 652, 653 (1) (632 SE2d 429) (2006). Thus, “a jury verdict, after approval by the trial court, and the judgment thereon will not be disturbed on appeal *803

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KATHY BOONE v. VASCULAR SURGICAL ASSOCIATES, P.C.
Court of Appeals of Georgia, 2024
P&J Beverage Corporation v. the Bottle Shop, LLC
Court of Appeals of Georgia, 2024
Reliance Trust Co. v. Candler
751 S.E.2d 47 (Supreme Court of Georgia, 2013)
Moore v. Stewart
727 S.E.2d 159 (Court of Appeals of Georgia, 2012)
RELIANCE TRUST CO. v. Candler
726 S.E.2d 636 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
692 S.E.2d 56, 302 Ga. App. 800, 2010 Fulton County D. Rep. 925, 2010 Ga. App. LEXIS 236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-v-key-custom-homes-inc-gactapp-2010.