Building Materials Wholesale, Inc. v. Triad Drywall, LLC

653 S.E.2d 115, 287 Ga. App. 772, 2007 Fulton County D. Rep. 3159, 2007 Ga. App. LEXIS 1095
CourtCourt of Appeals of Georgia
DecidedOctober 10, 2007
DocketA07A0932
StatusPublished
Cited by18 cases

This text of 653 S.E.2d 115 (Building Materials Wholesale, Inc. v. Triad Drywall, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Materials Wholesale, Inc. v. Triad Drywall, LLC, 653 S.E.2d 115, 287 Ga. App. 772, 2007 Fulton County D. Rep. 3159, 2007 Ga. App. LEXIS 1095 (Ga. Ct. App. 2007).

Opinion

JOHNSON, Presiding Judge.

Triad Drywall, LLC sued Building Materials Wholesale, Inc. (“BMW”) for breach of contract. A Fulton County jury awarded Triad $160,000 in damages and $14,480 in attorney fees. BMW appeals from the judgment entered in accordance with the verdict. For the reasons that follow, we reverse and remand for a new trial on the issue of damages for breach of contract and Triad’s attorney fees claim.

Viewed in the light most favorable to the jury’s verdict, 1 the evidence shows that Triad is in the business of installing drywall, metal studs, and acoustic ceilings in commercial and large residential building projects. Triad purchased materials from a number of suppliers, including BMW.

*773 In May 2003, Triad received a letter from Aviation Constructors, Inc. in which Aviation expressed its intent to hire Triad as a subcontractor on the Bartow Center, Phase I, Floyd College project (the “Project”), conditioned upon Aviation receiving a construction contract for the Project. As part of its job preparation, Triad solicited quotes from material suppliers. Through its salesman, David Dye, BMW submitted a “project quotation” for the “Floyd College Campus Phase I” which, along with a price schedule, indicated a “Bid Date: 10/22/2003,” “Expires: 4th quarter 2004,” and notation at the bottom that “Prices good until next manufacturer[’]s increase.” Triad’s operation manager, Ziv Gal, contacted Dye and told him that Triad would be purchasing its material through BMW.

According to Dye, BMW’s price quote was good until the end of the fourth quarter of 2004. Dye agreed that the verbal notification from Triad was an acceptable method of notifying BMW that Triad accepted the proposal, and typical in the industry. Dye also agreed that BMW expected, based on Triad’s commitment, that Triad would purchase the materials.

During the second week of January 2004, Dye informed Gal that there was a shortage of materials and market prices were going up. Dye asked Gal to place an order for the materials so that BMW could, in turn, buy the materials and avoid a cost increase to BMW. On January 20, 2004, Triad submitted a purchase order specifying the quantity of materials it needed for the Project, which further stated: “As you requested, this is the material list for Floors 1 & 2. Please stock it and we will take delivery mid-February.”

On January 29, 2004, BMW principal Mike Gist submitted an adjusted price schedule to Gal, stating that manufacturer price increases for building materials made the adjustments necessary and asking whether Triad wanted BMW to proceed with the order based on the adjusted prices. Gal responded that Triad expected BMW to honor its commitment to sell the material at the originally quoted prices. Gist reiterated BMW’s position in a letter dated February 9, 2004, and Dye, Gal, and Gist subsequently met at Triad’s office to discuss the matter. Gal informed Gist and Dye that Triad would ask Aviation for an increase in BMW’s contract price to defer the rise in material costs, but otherwise Triad expected BMW to honor the original quote. After the meeting, Gist and Dye discussed “why we should sell [the material] for this amount when we can sell it for more to someone else.”

Triad started work on the Project during the first week of March 2004 performing the jobs that it could while waiting for delivery of the majority of the materials. Before that time, BMW obtained liability insurance and a performance and payment bond in accordance with its agreement with Aviation.

*774 On March 15, 2004, Aviation’s project manager wrote to Triad declining Triad’s request for additional monies for steel studs, and expressing his irritation at Triad for having brought the subject up after the request had been previously discussed. Aviation then indicated that Triad could sign its subcontract agreement that day and provide written confirmation of the steel stud delivery date, or Aviation would contract with another company to do the work.

Triad maintained daily contact with Dye to check on the status of the materials, which BMW received on March 17, 2004. After the materials were delivered to BMW, Gal called Aviation to schedule a delivery to the job site, but there was a delay due to several days of rain. Triad informed BMW that it was not ready for the materials, but never said that it did not want the materials. Three or four days later, BMW sold the materials to another drywall company, AFM Interior Systems, Inc., for over $48,000 more than had been originally quoted to Triad. Triad was unable to do its work on the Project without the materials, and Aviation awarded the Project subcontract to AFM.

Evidence showed that BMW knew that when it submitted its price quote that the materials ordered by Triad were intended for the Project, that by January 2004 the lead time for ordering the materials was approaching eight weeks and growing, and that BMW knew that there were shortages that would cause Triad to have a “tough time” obtaining the materials from another supplier.

1. In its first claim of error, BMW challenges the jury’s $160,000 damage award on the ground that “Triad never got a subcontract for the Floyd College project through no fault of BMW.” In presenting its argument BMW does not cite to any supporting authority, as required by Court of Appeals Rule 25 (a) (3), and we have difficulty in discerning the particular issue or issues which BMW wishes to assert. It is apparent, however, that BMW contends that the evidence was insufficient to support a recovery for consequential damages for breach of the contract between BMW and Triad arising out of Triad’s inability to perform its agreement with Aviation. 2 “[A] jury verdict, after approval by the trial court, and the judgment thereon will not be disturbed on appeal if supported by any evidence, in the absence of any material error of law.” 3

The evidence shows that Triad never signed its subcontract with Aviation. BMW argues that Triad never had a signed subcontract *775 with Aviation because Aviation resisted Triad’s attempts to “blackmail” Aviation for more money, and that Triad’s loss of the subcontract could not be attributed to BMW. As to BMW’s “blackmail” accusation, the evidence did not demand that the jury conclude that Aviation’s decision to award the subcontract to Triad’s competitor was due to Aviation’s irritation at Triad’s request for more money. Triad’s request for more money from Aviation in connection with the cost of the metal studs was consistent with Ziv Gal’s promise to Gist to ask Aviation for additional money to defer the increased costs of material to BMW, and not “blackmail,” and central to Aviation’s demand that Triad sign the subcontract was that it confirm a delivery date for the metal studs. Evidence also showed that it was customary in the construction business for a subcontractor to start work after receipt of the letter of intent but before the actual subcontract is executed, and Triad started its work on the Project without a signed subcontract in this instance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medhi Nateghi v. Beauford Properties, LLC
788 S.E.2d 909 (Court of Appeals of Georgia, 2016)
EZ Green Associates, LLC v. Georgia-Pacific Corp.
770 S.E.2d 273 (Court of Appeals of Georgia, 2015)
Double View Ventures, LLC v. Nathaniel Polite
Court of Appeals of Georgia, 2014
Double View Ventures, LLC v. Polite
757 S.E.2d 172 (Court of Appeals of Georgia, 2014)
Willie Leon McGee v. Pamela Patterson
Court of Appeals of Georgia, 2013
McGee v. Patterson
746 S.E.2d 719 (Court of Appeals of Georgia, 2013)
Alea London Limited vs America Home Services, Inc.
638 F.3d 768 (Eleventh Circuit, 2011)
Mariner Health Care Management Co. v. Sovereign Healthcare, LLC
703 S.E.2d 687 (Court of Appeals of Georgia, 2010)
Green v. KEY CUSTOM HOMES, INC.
692 S.E.2d 56 (Court of Appeals of Georgia, 2010)
Triad Drywall, LLC v. Building Materials Wholesale, Inc.
686 S.E.2d 364 (Court of Appeals of Georgia, 2009)
Sunstate Industries, Inc. v. Vp Group, Inc.
679 S.E.2d 824 (Court of Appeals of Georgia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
653 S.E.2d 115, 287 Ga. App. 772, 2007 Fulton County D. Rep. 3159, 2007 Ga. App. LEXIS 1095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-materials-wholesale-inc-v-triad-drywall-llc-gactapp-2007.