Chong v. REEBAA CONST. CO., INC.

645 S.E.2d 47, 284 Ga. App. 830, 2007 Fulton County D. Rep. 1032, 2007 Ga. App. LEXIS 349
CourtCourt of Appeals of Georgia
DecidedMarch 23, 2007
DocketA06A2308, A06A2309
StatusPublished
Cited by10 cases

This text of 645 S.E.2d 47 (Chong v. REEBAA CONST. CO., INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chong v. REEBAA CONST. CO., INC., 645 S.E.2d 47, 284 Ga. App. 830, 2007 Fulton County D. Rep. 1032, 2007 Ga. App. LEXIS 349 (Ga. Ct. App. 2007).

Opinion

Bernes, Judge.

Reebaa Construction Company, Inc. filed the instant lawsuit against Chang Sop Chong, seeking recovery of funds allegedly owed for construction and renovation services that it performed at Chong’s home. Chong filed an answer and counterclaim. Following a jury trial, the jury found in favor of Reebaa Construction in the amount of $154,954.63 on its breach of contract claim and $140,112 on its attorney fees claim, plus prejudgment interest. The trial court entered judgment based on the verdict, and denied Chong’s motion for new trial.

In Case No. A06A2308, Chong appeals, arguing that (1) the evidence was insufficient to sustain the verdict and entry of judgment; (2) a trial witness for Reebaa Construction was erroneously allowed to testify and refresh his recollection using documents that *831 had not been produced during discovery; and (3) the award of attorney fees was erroneous. In Case No. A06A2309, Reebaa Construction cross-appeals, contending that the trial court erred (1) in granting Chong’s motions for directed verdict as to its claims for defamation and slander per se, tortious interference with business relationships, and punitive damages; (2) in failing to find Chong in contempt or to issue a protective order for Chong’s harassment and intimidation of witnesses; and (3) in failing to grant Reebaa Construction’s motions for attorney fees. For the reasons that follow, we affirm in part and reverse in part.

Case No. A06A2308

1. Chong contends that the trial court should have granted his motion for new trial on the ground that the evidence was insufficient to sustain the verdict. “We apply the ‘any evidence’ standard in reviewing a trial court’s judgment on a motion for new trial and construe the evidence most favorably toward the party opposing the motion.” James E. Warren, M.D., P.C. v. Weber & Warren Anesthesia Svcs., 272 Ga. App. 232, 237-238 (3) (612 SE2d 17) (2005).

So viewed, the evidence adduced at trial shows that in February 2003, the parties entered into an oral agreement whereby Reebaa Construction agreed to renovate and finish the basement level of Chong’s residence. James Wang, the president of Reebaa Construction, met with Chong to discuss the project. Wang asked Chong to sign a written contract for the project, but Chong, a licensed attorney, refused and stated that they should instead base their agreement on “honor” and “trust.”

In the beginning, Chong requested a simple construction, consisting of plain sheetrock walls, standard ceilings, and inexpensive cabinets for the basement kitchen. Chong approved Reebaa Construction’s “Construction Memo and Job List,” reflecting a total construction fee of $96,208, and instructed Reebaa Construction to begin work on the project.

Almost immediately after the construction began, Chong began to order substantial changes and upgrades, which delayed completion and increased costs for the project. Although Reebaa Construction did not inform Chong of specific costs associated with the alleged work, it did advise that the change orders and upgrades would cause additional expense and time. Chong informed Reebaa Construction representatives that “money [was] no[ ] object” and instructed them to do the work and bill him when the project was complete.

As the project progressed, Chong expressed satisfaction with the work, and while he later complained about the timeliness of the project’s progression, he never complained about the quality of the *832 workmanship. Through the course of the project, Chong made periodic payments to Reebaa Construction totaling $108,000.

In the late summer of 2003, the relationship between the parties declined. In September 2003, Reebaa Construction departed from the job site, but requested to return to complete minor punchlist work. Chong refused to allow Reebaa Construction’s workers back onto the property.

On October 31, 2003, Reebaa Construction submitted an invoice to Chong for the balance due on the contract. The invoice reflected a total construction price of $236,982 and a balance due of $128,982. Chong did not pay the bill, but instead requested additional repairs. Reebaa Construction hired an engineer to inspect the items which Chong sought to have repaired. The engineer testified that he had observed some defects, but upon further inquiry, Chong had responded that there was no problem with several of his other requested repair items.

When Chong failed to render payment of Reebaa Construction’s invoice, the instant collection suit was instituted. Following trial, Reebaa Construction’s claim was submitted to the jury on alternate theories of breach of contract and quantum meruit. The jury returned a verdict in Reebaa Construction’s favor on the breach of contract claim.

(a) Breach of Contract. Chong claims that the evidence was insufficient to sustain the verdict as to the breach of contract claim. Specifically, Chong argues that the evidence failed to demonstrate that there was a mutual assent by the parties as to price. 1 We agree.

Here, it is undisputed that Reebaa Construction failed to inform Chong of a specific price for the change orders and upgrades prior to performance. While Chong agreed to pay upon being billed for this additional work, the evidence shows that no specific price was quoted and agreed upon. “[A] contract is not complete and enforceable until there is a meeting of the minds as to all essential terms.” Lifestyle Family, L.P. v. Lawyers Title Ins. Corp., 256 Ga. App. 305, 308 (1) (568 SE2d 171) (2002), rev’d on other grounds, Mitchell Realty Group v. Holt, 266 Ga. App. 217 (596 SE2d 625) (2004). “[A]s price is an essential element of a valid contract, an alleged contract on which *833 there is no firm agreement as to the price is unenforceable.” Bell-South Advertising &c. Corp. v. McCollum, 209 Ga. App. 441, 444 (2) (433 SE2d 437) (1993). See also Progressive Life Ins. Co. v. Reeves, 89 Ga. App. 900, 902-903 (1) (81 SE2d 519) (1954). Since the trial record reflects that the parties failed to assent to an agreed price for the change orders and upgrades, there was insufficient evidence to sustain the verdict on the breach of contract claim. Id.; Lifestyle Family, L.P., 256 Ga. App. at 308-309 (1). Accordingly, the trial court’s denial of Chong’s motion for new trial must be reversed.

(b) Quantum Meruit. Upon retrial of the case, Reebaa Construction also is entitled to seek recovery under the alternative theory of quantum meruit. See Lifestyle Family, L.P., 256 Ga. App. at 309 (2). “[F]or a plaintiff to recover on a claim for quantum meruit, the jury must find that the plaintiff performed services valuable to the defendant and that the defendant accepted those services.” (Emphasis omitted.) Langford v. Robinson, 272 Ga. App. 376, 379 (1) (612 SE2d 552) (2005). “When the value of the goods and services was not agreed upon prior to performance,” the action is properly one for quantum meruit, and “the measure of damages is the reasonable value of [the] services or goods delivered.” Zampatti v. Tradebank Intl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Southwest Express Co. v. Great American Insurance Co. of New York
665 S.E.2d 878 (Court of Appeals of Georgia, 2008)
Chong v. REEBAA CONST. CO., INC.
665 S.E.2d 435 (Court of Appeals of Georgia, 2008)
American Southern Insurance Group, Inc. v. Goldstein
660 S.E.2d 810 (Court of Appeals of Georgia, 2008)
Reebaa Construction Co. v. Chong
657 S.E.2d 826 (Supreme Court of Georgia, 2008)
Franklin v. AUGUSTA DODGE, INC.
652 S.E.2d 862 (Court of Appeals of Georgia, 2007)
Harris v. Baker
652 S.E.2d 867 (Court of Appeals of Georgia, 2007)
Building Materials Wholesale, Inc. v. Triad Drywall, LLC
653 S.E.2d 115 (Court of Appeals of Georgia, 2007)
Jones v. Equipment King International
652 S.E.2d 811 (Court of Appeals of Georgia, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
645 S.E.2d 47, 284 Ga. App. 830, 2007 Fulton County D. Rep. 1032, 2007 Ga. App. LEXIS 349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chong-v-reebaa-const-co-inc-gactapp-2007.