Global NAPs, Inc. v. Verizon New England, Inc.

489 F.3d 13, 67 Fed. R. Serv. 3d 1260, 2007 U.S. App. LEXIS 12445, 2007 WL 1545832
CourtCourt of Appeals for the First Circuit
DecidedMay 30, 2007
Docket06-2095, 06-2120
StatusPublished
Cited by90 cases

This text of 489 F.3d 13 (Global NAPs, Inc. v. Verizon New England, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global NAPs, Inc. v. Verizon New England, Inc., 489 F.3d 13, 67 Fed. R. Serv. 3d 1260, 2007 U.S. App. LEXIS 12445, 2007 WL 1545832 (1st Cir. 2007).

Opinion

LYNCH, Circuit Judge.

This appeal raises issues concerning the release of security when an appellant has previously been ordered to post that security as a condition for obtaining an injunction pending appeal. See Fed.R.Civ.P. 65(c). In this case, the district court released the security after this court had rejected the appeal and dissolved the injunction.

We affirm the district court’s release of $16 million in security to appellee Verizon New England, Inc. (“Verizon”), over the protests of appellant Global NAPs, Inc. (“GNAPs”). In order to maintain the status quo pending appeal, Verizon had been enjoined from terminating its services to GNAPs for failure to pay access fees; GNAPs, in turn, had been ordered to provide security for the costs and damages Verizon would incur during the period of the injunction. Our analysis construes Federal Rule of Civil Procedure 65(c) and adopts standards for the release of security under this rule.

I. BACKGROUND

This marks the third time that aspects of this dispute have appeared in our court. See Global NAPs, Inc. v. Verizon New Eng., Inc. (GNAPs I), 396 F.3d 16 (1st Cir.), cert. denied, 544 U.S. 1061, 125 S.Ct. 2522, 161 L.Ed.2d 1110 (2005); Global NAPs, Inc. v. Verizon New Eng., Inc. (GNAPs II), 444 F.3d 59 (1st Cir.2006). The parties’ underlying litigation pertains to GNAPs’ failure to make payments to Verizon, notwithstanding a December 2002 order from the Massachusetts Department of Telecommunications and Energy (DTE) which required these payments. As reflected in a subsequent interconnection agreement between Verizon and GNAPs, the DTE order had required GNAPs to pay Verizon for Virtual NXX (“VNXX”) calls originated by Verizon’s Massachusetts customers and delivered to GNAPs. 1 See GNAPs II, 444 F.3d at 66.

In GNAPs I, we rejected a particular argument from GNAPs that it did not need to comply with the DTE’s December 2002 order. See GNAPs I, 396 F.3d at 23. *16 This resolved only part of the dispute. In GNAPs II, we rejected GNAPs’ remaining arguments that the DTE’s rulings conflicted with and were preempted by federal law, and so we affirmed the DTE order. See GNAPs II, 444 F.3d at 71-75. The current dispute pertains to a security posted after our decision in GNAPs I, and which was released to Verizon after our decision in GNAPs II.

A. The Remand After GNAPs I

After our ruling in GNAPs I, Verizon notified GNAPs on March 17, 2005 that GNAPs had . accrued more than $42 million in access charges (excluding late payment charges). Verizon further informed GNAPs that it would terminate services to GNAPs on April 19, 2005 if payments were not made. The companies later agreed to postpone the termination date to May 12, 2005, in order to explore settlement possibilities. When the settlement discussions failed, GNAPs moved for a TRO and/or preliminary injunction. to prevent disconnection while it litigated the GNAPs II case. .See id. at 67 n. 6.

On May 12, 2005, the district court indicated that it would maintain the. status quo pending a resolution on the merits of GNAPs’ preemption - argument; the court stated at a hearing that it would grant GNAPs’ motion, subject to GNAPs posting appropriate security. On June 2, 2005, the court entered the preliminary injunction which GNAPs had requested, conditioned on GNAPs providing security- in the amount of $1 million (a condition that GNAPs fulfilled). The court also expedited the briefing schedule for the parties’ cross-motions for summary judgment. On September 21, 2005, the district court denied GNAPs’ motion for partial summary judgment, and it granted Verizon’s and the DTE’s cross-motions for partial summary judgment.

- In light of its success in the district court, Verizon again notified GNAPs (this time by letter dated September 23, 2005) that it would soon terminate service for non-payment. GNAPs sought clarification from the district court on whether the preliminary injunction had been dissolved by the court’s opinion, and the court confirmed that its decision had that effect. GNAPs then stipulated to the dismissal with prejudice of its remaining challenges to the DTE’s decision, thereby freeing GNAPs to pursue an appeal.

B. GNAPs II and the Injunction Pending Appeal

GNAPs next sought an injunction pending appeal, first from the district court, and then from this court, in order to prevent Verizon from terminating service. See id. at 68 n. 8. GNAPs represented to both courts that without such an injunction it would “suffer a fatal revenue loss,” and in its motion to this court it characterized the litigation as an “all-or-nothing dispute.” GNAPs "also represented that it had offered to pay Verizon, over time, the more than $56 million Verizon 1 claimed was now due, which GNAPs asserted “would fully pay the access charges, if Verizon prevails here.”- That offer, according to GNAPs, required only that Verizon agree to refrain from cutting off service, and agree to return the sums paid if GNAPs prevailed on appeal.

The district court denied GNAPs’ request for additional injunctive relief. But this court granted GNAPs’.motion on November 2, 2005, and we enjoined Verizon from terminating service pending GNAPs’ appeal. This injunction was contingent on GNAPs providing “additional security” in an amount to be set by the district court, and we remanded the issue, of the amount and form of the security. In the district court, GNAPs proposed that the court set *17 security — beyond the $1 million GNAPs had already posted as security for the first injunction — in the amount of $16,676,313. GNAPs further stated that it would post that amount by assigning funds that Verizon’s affiliates, most of which operated in other states and were not parties to the underlying suit, had withheld from GNAPs or its affiliates to secure debts in what Verizon claims are unrelated disputes. Not coincidentally, those withheld funds totaled $16,676,313.

The district court ordered GNAPs to post an additional $15 million in security. This was roughly $1.7 million less than the $16,676,313 in additional security that GNAPs had itself proposed as appropriate. Over Verizon’s objection, the district court also permitted GNAPs to satisfy that requirement by assigning funds withheld by Verizon’s affiliates.

On April 11, 2006, this court issued its ruling on the merits in GNAPs II, and we affirmed the district court’s grant of summary judgment. See id. at 61. This court rejected GNAPs’ claim that the Federal Communications Commission, in a decision known as the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
489 F.3d 13, 67 Fed. R. Serv. 3d 1260, 2007 U.S. App. LEXIS 12445, 2007 WL 1545832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-naps-inc-v-verizon-new-england-inc-ca1-2007.