Gingras v. Avery

878 A.2d 404, 90 Conn. App. 585, 2005 Conn. App. LEXIS 334
CourtConnecticut Appellate Court
DecidedAugust 2, 2005
DocketAC 25714
StatusPublished
Cited by5 cases

This text of 878 A.2d 404 (Gingras v. Avery) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gingras v. Avery, 878 A.2d 404, 90 Conn. App. 585, 2005 Conn. App. LEXIS 334 (Colo. Ct. App. 2005).

Opinion

Opinion

PETERS, J.

This case is an action for specific performance of a real estate contract for the sale of property that was intended to be developed as a subdivision. [587]*587The developers were unable to obtain subdivision approval by the final date for closing that was stated in the contract. Two days later, the landowners formally terminated the contract. Despite their own default, the developers claim that they the are entitled to a decree of specific performance to require a closing to be held. In their view, the landowners’ termination was wrongful because (1) as a matter of contract interpretation, the parties did not intend to make subdivision approval an absolute condition of a timely closing on the closing date and (2) as a matter of substantive law, the landowners’ termination of the contract violated the developers’ right to pursue subdivision approval for a reasonable time after the closing date. The trial court rejected these claims and rendered judgment in favor of the landowners. The developers have appealed. The judgment is affirmed.

On May 6, 2003, two developers, the plaintiffs Gaetan H. Gingras and Thomas J. Carenzo, Jr. (developers), filed a complaint asking the court to compel two landowners, the defendants Jean G. Avery and Julia M. Aveiy (landowners), to convey to them property described in a real estate contract into which the parties had entered on January 4, 2002.1 Crucially, the contract included a provision for a closing to be held “on or before sixty (60) days after subdivision approval, but in no event later than March 15, 2003.”

The court found, and the developers do not dispute, that they did not obtain subdivision approval in time for a March 15, 2003 closing. The court found that, without subdivision approval, the contract did not entitle the developers to compel a closing to be held on March 15. The court also found that the developers had [588]*588failed to prove that they could have obtained subdivision approval within a reasonable period of time after March 15. On the basis of these findings, the court found that the landowners’ termination of the contract was not a breach thereof.

The underlying facts are undisputed. The landowners owned twenty-three acres of land located at Billings Road in Somers. The real estate contract between the parties took the form of a bond for deed with an attached addendum. Several paragraphs of the addendum expressly referred to subdivision approval as a requirement for transfer of the property to the developers, but some paragraphs did not. The parties disagree about whether the contract was enforceable without timely subdivision approval.

The trial court’s memorandum of decision describes the developers’ efforts to obtain the contemplated subdivision approval. The developers submitted a timely application to the Somers’ planning and zoning commission (commission), but they withdrew this application in May, 2002, when they discovered that Somers had a subdivision regulation that did not permit roadways within 800 feet of one another on a collector road. The proposed subdivision road did not meet those requirements. The developers later sought to amend the subdivision regulation, but the commission denied their request.

On March 12,2003, two days before the contemplated closing date of March 15, 2003, the developers purchased an abutting piece of property on which they intended to construct an alternative access road that might have brought the proposed subdivision into compliance with town regulations. A question remained, however, as to whether the developers could access their twenty-three acres, which were zoned as residential, via the newly purchased property, which was in [589]*589an industrial zone. That issue was never resolved because the developers never filed a second subdivision application.

On March 12, 2003, when the developers purchased the abutting property, they realized that it was not possible for a closing to take place by March 15 in accordance with the terms of the bond for deed and its addendum. The landowners refused to agree to postpone the closing date. The landowners also refused to agree to a closing date prior to March 15, because several material terms of the contract had not been, and could not be, met at that time. On March 17, 2003, the landowners withdrew their permission for the developers to seek zoning approval for the property and returned the developers’ deposit.

After reviewing the terms of the real estate contract and hearing testimony about the intent of the parties, the court made two findings of fact. On the basis of the evidence of record, including the testimony of the parties, it found that the parties had intended not to go forward with the sale of the property unless the developers obtained subdivision approval. It also found that “it [was] problematic that [subdivision approval] could have been obtained within a reasonable time after March 15, 2003.” Accordingly, the court held that the developers were not entitled to specific performance because the landowners’ termination of the contract to convey the property was not a breach of contract.

In their appeal, the developers argue that the trial court improperly (1) decided that the contract was unenforceable without timely subdivision approval, (2) failed to consider the role that the landowners played in the developers’ inability to obtain subdivision approval and (3) found that it was problematic that the developers would succeed in obtaining subdivision approval within a reasonable time. We are not persuaded.

[590]*590I

The developers’ principal claim on appeal is that the trial court misinterpreted the terms of their real estate contract. They concede that subdivision of the landowners’ property was their intended goal. They claim, nonetheless, that the court improperly found that the landowners’ obligation to convey their property was conditioned on the developers’ first obtaining subdivision approval from the commission. We do not agree.

We begin by setting forth the appropriate standard of review. The parties appear to have assumed that their disparate interpretations of the terms of their real estate contract raise questions of law.2 Inferentially, they consider the terms of the bond for deed and the addendum, singly or jointly, to be unambiguous. Although the fact that they disagree about the meaning of their contract does not demonstrate its ambiguity; see Gould v. Mellick & Sexton, 263 Conn. 140, 151, 819 A.2d 216 (2003); “[w]hen . . . contract provision^] are internally inconsistent, a question of fact is involved.” Bank Boston Connecticut v. Avon Meadow Associates, 40 Conn. App. 536, 540, 671 A.2d 1310 (1996). “Whether the performance of a certain act by a party to a contract is a condition precedent to the duty of the other party to act depends on the intent of the parties as expressed in the contract and read in light of the circumstances surrounding the execution of the instrument.” (Internal quotation marks omitted.) Christophersen v. Blount, 216 Conn. 509, 512, 582 A.2d 460 (1990); Lach v. Cahill, 138 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Air Brake Systems, Inc. v. Tuy Rheinland of North America, Inc.
699 F. Supp. 2d 462 (D. Connecticut, 2010)
Wesley v. Schaller Subaru, Inc.
893 A.2d 389 (Supreme Court of Connecticut, 2006)
Smith v. Coldwell Banker Commercial N.E.R.A., LLC
880 A.2d 1012 (Connecticut Appellate Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
878 A.2d 404, 90 Conn. App. 585, 2005 Conn. App. LEXIS 334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gingras-v-avery-connappct-2005.