Tulisano v. Schonberger

810 A.2d 806, 74 Conn. App. 101, 2002 Conn. App. LEXIS 623
CourtConnecticut Appellate Court
DecidedDecember 17, 2002
DocketAC 21126
StatusPublished
Cited by8 cases

This text of 810 A.2d 806 (Tulisano v. Schonberger) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tulisano v. Schonberger, 810 A.2d 806, 74 Conn. App. 101, 2002 Conn. App. LEXIS 623 (Colo. Ct. App. 2002).

Opinion

Opinion

HENNESSY, J.

The plaintiff Robert Tulisano1 appeals from the judgment of the trial court rendered in favor of the defendant, Philip Schonberger, on his breach of contract claim.2 The plaintiff raises three claims on appeal. He contends that the court improperly found that (1) the evidence supported judgment for the defendant, (2) the plaintiff failed to provide to the defendant within a reasonable time a certain survey called for by the contract and (3) the plaintiff was not entitled to recover damages in the amount of $400,000. We affirm the judgment of the trial court.

The court found the following facts. On May 17,1996, the defendant, as president of Albermarle Equities, Inc., [103]*103contracted to purchase real property from the plaintiff and Richard Tulisano.3 The defendant deposited $40,000 with his attorney, Kevin G. Dubay, who placed it in an interest bearing account. The deposit was to be applied to the total purchase price of $400,000 at the time of the closing, July 17, 1996.

The contract contained various contingencies allowing for the termination of the contract. Specifically, the defendant could terminate the contract if he received a report from a licensed or recognized building inspector stating that the building was unsound structurally or that the mechanical, plumbing or electrical systems did not function properly. In addition, the plaintiff would be required to provide a recent survey and an estoppel certificate.4 The contract stipulated June 17,1996,5 as the deadline for the defendant to terminate the contract.

The defendant hired John Wilcox, a licensed architect, to inspect and to evaluate the property to determine its condition and viability for use as a restaurant. Wilcox submitted his written report, finding that the basement contained two to three feet of water, the building lacked power and, due to the lack of power, he was unable to test the electrical, plumbing, heating and air conditioning systems.6 He also found some interior construction work completed without the necessary permits from the town, evidence of water damage and insufficient parking spaces. The Wilcox report rec[104]*104ommended that significant consideration should be given to demolishing the existing structure.

On June 19, 1996, the defendant sent a termination letter and a copy of the Wilcox report to the plaintiff.7 On June 21, 1996, Dubay received a letter faxed from the plaintiffs attorney, objecting to the termination. On July 16, 1996, one day before the scheduled closing, Dubay wrote to the plaintiffs attorney, confirming the reasons for termination contained in the June 19, 1996 letter. The letter also addressed the absence of the required survey and estoppel certificate. The plaintiff never provided the required survey or estoppel certificate to the defendant. The plaintiff also failed to inform the defendant that he had restored the power or repaired the building systems. The plaintiff thereafter initiated an action for breach of contract on December 13, 1996.

The court found that the June 19, 1996 letter terminated the relationship of the parties and entitled the defendant to the return of the $40,000 deposit. The court concluded that time was not of the essence because the parties never agreed in the contract to make it so. The court rendered judgment in favor of the defendant and ordered Dubay to return the $40,000 deposit to the defendant. This appeal followed. Additional facts will be set forth as necessary.

I

The plaintiff first claims that the court improperly found that the evidence supported judgment for the defendant. Specifically, the plaintiff argues that the court improperly found that (1) the defendant had exercised his termination right in the time allowed by the contract, (2) the defendant was justified in terminating [105]*105the contract because Wilcox was not a recognized or licensed building inspector and (3) the reasons contained in the Wilcox report were sufficient to cancel the contract. We disagree.

Initially, we set forth the applicable standard of review. “[W]here the factual basis of the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Internal quotation marks omitted.) Barzetti v. Marucci, 66 Conn. App. 802, 807, 786 A.2d 432 (2001); see also Practice Book § 60-5. This court frequently has defined the clearly erroneous standard. “A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence in the record to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. . . . While conducting our review, we properly afford the court’s findings a great deal of deference because it is in the unique [position] to view the evidence presented in a totality of circumstances, i.e., including its observations of the demeanor and conduct of the witnesses and parties, which is not fully reflected in the cold, printed record which is available to us.” (Citation omitted; internal quotation marks omitted.) Hunter’s Ambulance Service, Inc. v. Shernow, 70 Conn. App. 96, 104, 798 A.2d 991 (2002). We now address each of the plaintiffs arguments in turn.

A

The plaintiff argues that the court improperly found that the defendant had exercised his termination rights in the time allowed by the contract. “In real estate contracts, ‘the fact that a specific time is fixed for payment or for conveyance does not make “time of the [106]*106essence” — at least, it does not make performance at the specified time of the essence.’ . . . 3A Corbin, Contracts § 716, p. 365 (1960).” (Emphasis in original.) Kakalik v. Bernardo, 184 Conn. 386, 392, 439 A.2d 1016 (1981). When the parties to a real estate contract want to fix a specific date for performance, we generally have required them to express specifically in the contract that time is of the essence; otherwise, performance within a reasonable time will satisfy the contract. See Bethlehem Christian Fellowship, Inc. v. Planning & Zoning Commission, 58 Conn. App. 441, 446, 755 A.2d 249 (2000). “Where the agreement does not specifically state that time is of the essence, it is presumed not to be unless the parties have expressed a contrary intent.” Mihalyak v. Mihalyak, 11 Conn. App. 610, 616, 529 A.2d 213 (1987).

In the present case, ample evidence existed to support the court’s finding that the parties to the contract for the purchase of the real estate did not intend to make time of the essence. Specifically, the parties did not include the phrase “time is of the essence” in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Li v. Yaggi
212 Conn. App. 722 (Connecticut Appellate Court, 2022)
Green Falls Associates, LLC v. Zoning Board of Appeals
53 A.3d 273 (Connecticut Appellate Court, 2012)
Gingras v. Avery
878 A.2d 404 (Connecticut Appellate Court, 2005)
Demattia v. Mauro
860 A.2d 262 (Connecticut Appellate Court, 2004)
Lind-Larsen v. Fleet National Bank
852 A.2d 799 (Connecticut Appellate Court, 2004)
State v. Ceballos
832 A.2d 14 (Supreme Court of Connecticut, 2003)
Bijur v. Bijur
831 A.2d 824 (Connecticut Appellate Court, 2003)
Lipshie v. George M. Taylor & Son, Inc.
828 A.2d 110 (Supreme Court of Connecticut, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
810 A.2d 806, 74 Conn. App. 101, 2002 Conn. App. LEXIS 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tulisano-v-schonberger-connappct-2002.