Gimbert v. Heinsath

5 Ohio Cir. Dec. 176
Cuyahoga Circuit Court·Decided March 15, 1896·Published

Opinion

Caldwell, J. *

The plaintiffs in error filed a petition in the court of common pleas setting up in substance that the defendant, Jennie Madden, entered into a written contract with the defendant, H..A. Heinsath, sometime prior to the 21st day of June, 1895, whereby the said Heinsath agreed to furnish all materials and labor necessary for the complete construction of a two-story frame house for her upon a parcel of land (fully described) in Cleveland, Ohio; said Jennie Madden agreed to pay therefor the sum of $2,397.50 as the work progressed. The entire sum to be paid within sixty days from the date of the completion of said house. That said Heinsath fully performed said contract upon his part, and fully completed the house on July 1,1895. That between June 1, 1895, and June 21,1895, the plaintiff furnished certain material and performed certain labor necessary for putting a slate roof upon the same, as required by said contract, under a verbal contract with said Heinsath for the agreed sum of $131.00, said sum being the reasonable value of the work and material required to be performed and furnished in doing said work. Plaintiff says he completed said work on the 21st day of June, 1895, and the same was fully accepted by said Heinsath and by said Jennie Madden; the said sum of $131.00 is due and unpaid, and the defendants refuse to pay the same. On the 11th day of July, . 1895, the plaintiff duly filed with the recorder of Cuyahoga county, Ohio, under the statutes providing for obtaining a mechanic’s lien, an affidavit containing an itemized account of the amount and value of said material and labor, with all credits and offsets indorsed [177]*177thereon, with a copy of the contract under which said work was done and said material furnished, and a description of the premises. The petition avers the record of the lie'n,'£nd claims a lien, and asks for a foreclosure of the same. The ans#fc*-®f Jennie Madden admits the contract under which the house was built for., her, and avers that said contract, among other things, provided thah thé'.sáid Heinsath should and he did thereby waive any and all right*f>plaeitig a lien upon said premises for labor performed or material furnished for said building, and provided that no lien or liens should be >plaqed'thereon for labor performed or materials furnished therefor by hiítóélJMsir others under him, and contests the right of the plaintiff to any lien on said premises. It is conceded that the contract between said Jenúíe l\£ádden and the plaintiff was after, and some time after April 13th, 1891. The plaintiff demurred to the said answer on the ground it did not .state a defense. The demurrer was overruled and judgment was rendered in'favor of Jennie Madden. It is claimed by defendant in error that the overruling of the demurrer was right, because the answer states a good defense; and if it does not, it was good as to the petition, because it states no cause of action good in law. There are two questions in the case:

1. The constitutionality of ,the amendment of the Mechanics lien law as found in 91 O. H, 135. '

2. Can the owner and contractor by contract deprive the material-man of a lien on the premises for which he has furnished material under a contract with the contractors?-’ Section 3184 in the act, 910, h., 135, is:

“ A person who performs labor, or furnishes machinery or material for constructing, altering or repairing a boat, vessel or other watercraft,' or for erecting, altering, repairing" of removing a house, mill, manufactory, or any furnace or furnace material therein, or other building, appurtenance, fixture, bridge qr -other structure, or for the digging,, drilling, plumbing, boring, operating, completing or repairing of any gas well, oil well or any other well, or peforms labor of any kind whatsoever, in altering, repairing or constructing any. oil-derrick, oil-tank, oil or gas pipe line, or furnishes tile for the drainage of any lot or land by virtue of a contract with, or at the instance of the owner thereof or his agent, trustee, contractor or subcontractor, shall have a lien to secure the payment of the same upon such boat, vessel or other watercraft, or upon such house, mill, manufactory or other building or appurtenance, fixture, bridge or other structure, or upon such gas-well, oil-well or any other well, or upon such oil-derrick, oil-tank, oü or gas pipe line and upon the material and machinery so furnished', and upon the interest, leasehold or otherwise, of the owner in the lot or land on which the same may stand, or to which it may be removed.” ' '.

And section 3185a is:

“In all cases where labor, material or machinery referred to in sections 3184 and 3185, shall be furnished by any person other than the original contractor, with such -‘owner or his agent or trustee, the lien shall not exceed the actual value of the labor, material or machinery so furnished, and the aggregate” amount of liens for which the property may be held shall not, in the absence of fraud or collusion between the owner and original contractor, exceed the amount of the price agreed upon between the owner and original contractor for the performing of such labor and the furnishing of such material and machinery. Provided, if it shall be made to appear that the owner and contractor, for the purpose of defrauding said subcontractors, material-men or laborers, fixed an [178]*178unreasonably low price in the original contract for any work or material for which a lien is given under section thirty-one hundred and eighty-four, the court shall ascertain the difference between such fraudulent contract price and a fair and reasonable price therefor, and such subcontractors, material-men and laborers shall have a lien to the amount of such fair and reasonable price so ascertained.”

It is claimed that in so far as this act undertakes to give to any one who has furnished material to the contractors under a contract with him, a lien upon the premises is unconstitutional, because if the owner pays the contractor in full the contract price before the building is erected or during its erection or any part of the contract price, still laborers who have worked upon the building and material-men who have furnished materials for the same may charge the property with liens to the extent of the contract price, ojr even more if the contractor undertook the work for less than its true value. It is claimed that the material-man under the statute can subject the owner’s property to a lien for materials not called for under, the contract between the owner and his contractor if the same are ordered for the building, and used in the same by the contractor. That these provisions of the statute deprive the owner of the right to own, possess, enjoy and contract in regard to his property as guaranteed to him by the highest law of the state. The law of the land where a contract is made, enters into the contract and forms a part of the same, and the scope and effect of the contract is determined by the law; and where, as in this case, a contract is entered into after the passage of a law on the subject matter of the contract, that law enters into the contract and becomes obligatory upon the parties thereto. This rule has been repeatedly recognized by the supreme court of Ohio. In Smith v. Parsons, 1 O., 236, the court say: “ The legislature has a right, by law, to regulate contracts, to determine their effect, and point out the mode of their discharge. These laws are applied to all subsequent engagements, and fix the rights of the parties at the very instant the contract is closed.

Free access — add to your briefcase to read the full text and ask questions with AI

Gimbert v. Heinsath, 5 Ohio Cir. Dec. 176 (Ohio Super. Ct. 1896).

5 Ohio Cir. Dec. 176 (Gimbert v. Heinsath) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bowen v. Phinney
39 N.E. 283 (Massachusetts Supreme Judicial Court, 1895)
Kellogg v. Howes
22 P. 509 (California Supreme Court, 1889)
Merrigan v. English
9 Mont. 113 (Montana Supreme Court, 1889)
Foster v. Dohle
17 Neb. 631 (Nebraska Supreme Court, 1885)
Colpetzer v. Wardens of Trinity Church
24 Neb. 113 (Nebraska Supreme Court, 1888)
James Hunter & Co. v. Truckee Lodge
14 Nev. 24 (Nevada Supreme Court, 1879)
S. V. R. R. Co. v. Miller
80 Va. 821 (Supreme Court of Virginia, 1885)
Coffin v. Hanner, Jennings & Co.
1 Or. 236 (Oregon Supreme Court, 1857)
Colter v. Frese
45 Ind. 96 (Indiana Supreme Court, 1873)
McLaughlin v. Reinhart
54 Md. 71 (Court of Appeals of Maryland, 1880)
Hartman v. Berry
56 Mo. 487 (Supreme Court of Missouri, 1874)
Henry & Coatsworth Co. v. Evans
97 Mo. 47 (Supreme Court of Missouri, 1888)
Mallory v. La Crosse Abattoir Co.
49 N.W. 1071 (Wisconsin Supreme Court, 1891)
Cole Manufacturing Co. v. Falls
16 S.W. 1045 (Tennessee Supreme Court, 1891)