Colpetzer v. Wardens of Trinity Church

24 Neb. 113
CourtNebraska Supreme Court
DecidedJanuary 15, 1888
StatusPublished
Cited by5 cases

This text of 24 Neb. 113 (Colpetzer v. Wardens of Trinity Church) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colpetzer v. Wardens of Trinity Church, 24 Neb. 113 (Neb. 1888).

Opinion

Cobb, J.

This cause is brought to this court on appeal from the decree of the district court of Douglas county.

On February 24, 1883, the plaintiffs filed their petition in the court below, setting up that the wardens and vestrymen of Trinity Church, of Omaha, contracted with August Walbaum, on January 27, 1880, for the erection of the cathedral church building on the W. half of lot 2, and lots 3 and 4, in block 85 in said city, for the sum of $25,-000, due in four payments, according to the progress of the work, to be completed November 1st, following. The contractor failing to comply with his terms, entered into a supplemental contract subsequent to May 19,1881, extending the time, increasing the cost $3,400, and substituting the material for the completion of the building, and- subsequently abandoned the work, as a failing contractor, with [115]*115the full knowledge of the wardens and vestrymen, who assumed to procure material, employ labor, and complete the building at an expense nearly double that of the contract price. The contractor placed the work in charge of Benjamin Melquist, as foreman, who was continued as such by the wardens and vestrymen to the completion of the building. There was furnished by plaintiffs, who are lumber dealers in Omaha, material for the building, on the order of the foreman, prior to May 1, 1881, amounting to $380, which was paid by the wardens and vestrymen from money yet due the contractor.

A second bill of $880.29 for like material, between May 1, and September 30, 1881, was presented to and considered by the wardens and vestrymen, and payment refused as that of a bill against the contractor, and not one to be paid by the church corporation. On this bill the action is brought.

A third bill for like material, subsequent to October 1, 1881, and subsequent to the withdrawal of the contractor, was paid by the wardens and vestrymen, which closed the parties’ dealings.

On November 26, 1881, the plaintiffs proceeded to attach their lien, under section 2 of the act entitled, “An act to amend chapter 42 of the General Statutes of Nebraska, entitled ‘Mechanics’ Liens,”’ approved February 28,1881, for material furnished the Trinity Church building on lot 4 of block 85 in Omaha, amounting to the rejected bill $880.29, with notice in the proceedings to Trinity Church and to A. Walbaum & Co.

To the petition the wardens and vestrymen answered August 4, 1883, that they have no knowledge of the furnishing or use of the material as stated; they deny the allegations, and aver that whatever material was furnished was at the instance and on the credit of A. Walbaum, and not otherwise, and they are not liable.

II. They deny legal notice of the mechanic’s lien, and [116]*116the legal steps to charge them, or the church property with the material sold and delivered to A. "Walbaum.

III. They deny all knowledge that there is no dispute between the plaintiffs and Walbaum as to material furnished by plaintiffs to the contractor.

IV. They deny there is due for material furnished Walbaum any sum, but that prior to this suit the plaintiffs assigned the account to W. J. Connell, who is the owner and holder thereof, and that the plaintiffs ought not to maintain their action.

V. That by their contract with Walbaum he undertook to furnish the material for the church building, and to erect the same, and was liable to a forfeiture of compensation, at a specified date, on failure to comply with his stipulations; that he subsequently failed to comply, suspended the work, and withdrew as contractor, leaving them to assume the completion of the building at an increased cost and expense above that of the contract price; that there is nothing due the contractor, but he is largely indebted, by his failure, for the increased cost in the erection of the building; that they have, at no time, been indebted to the contractor since the delivery of said material by the plaintiffs and the filing of the account therefor.

The plaintiffs replied October 2, 1883, and denied that the material furnished and used in the church building was solely at the instance and on the credit of A. Walbaum, or that the wardens and vestrymen are in no way liable therefor.

They deny that at any time they transferred their interest in the account to W. J. Connell, or that he is the owner and holder thereof and entitled to any amount due thereon; and say they have no knowledge of, or means of knowing, the terms of contract between A. Walbaum and the wardens and vestrymen, and deny all allegations of the fifth paragraph of the answer. The defendant, Walbaum, made no answer.

[117]*117There Avas a trial to a jury, to whom the following instructions were given in charge, and special findings submitted:

“I. The plaintiffs in this action sue to foreclose what they allege to be a material man’s lien upon the church property of the defendants.
“II. The defendants answer and deny the existence of the alleged lien, and deny the furnishing of the lumber to and for the church, and fully deny the liability of defendants to pay for said material if the same Avas furnished as .alleged.
“III. Certain facts are submitted to you, and those facts alone you must pass upon.
“IV. You are to find in your verdict the amount in value of the material furnished and delivered by plaintiffs to and at the defendants’ church property at south-east corner of Capitol avenue and 18th street, in Omaha, Nebraska, under the alleged contract of the .church Avith A. "VValbaum, for use in the erection of said church building, which is in the alleged mechanic’s lien sued upon.
“V. You are also instructed to find the amount in value of the lumber and building material furnished under the contract charged in the alleged lien which actually Avent into the building contracted for.
“VI. You aré requested to find the date of the furnishing of the last item furnished, set forth in said items of the alleged lien.
“VII. You are to be guided in finding said amount or value by the contract price, if any, and if no contract price between the plaintiffs and Walbaum, then the fair market value must govern you in arriving at the said value of said alleged material.
“VIII. You are to take all the evidence and circumstances adduced in the case, and give such weight to the testimony of witnesses as you shall think right and |3roper.”

[118]*118Under which, the jury returned the following special verdict:

“We, the jury impaneled to try certain questions of fact as subniitted by the questions hereinafter set forth, do find and answer said questions as follows, to-wit:
“First. Was the lumber and building material set forth in account attached to petition furnished and delivered by plaintiffs at the premises upon which Trinity cathedral was being constructed for the purpose of being used in said cathedral? Yes.
“Second. Was said lumber and building material so furnished and delivered in pursuance of a verbal contract and arrangement with A. Walbaum? Yes.
“ Third.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coates Lumber & Coal Co. v. Klaas
168 N.W. 647 (Nebraska Supreme Court, 1918)
Drexel v. Richards
67 N.W. 169 (Nebraska Supreme Court, 1896)
Gimbert v. Heinsath
5 Ohio Cir. Dec. 176 (Cuyahoga Circuit Court, 1896)
Garlichs v. Donnelly
60 N.W. 323 (Nebraska Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
24 Neb. 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colpetzer-v-wardens-of-trinity-church-neb-1888.