Cole Manufacturing Co. v. Falls

16 S.W. 1045, 90 Tenn. 466
CourtTennessee Supreme Court
DecidedJune 11, 1891
StatusPublished
Cited by60 cases

This text of 16 S.W. 1045 (Cole Manufacturing Co. v. Falls) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cole Manufacturing Co. v. Falls, 16 S.W. 1045, 90 Tenn. 466 (Tenn. 1891).

Opinion

Calwdell, J.

This is a material-maids bill, brought to enforce an alleged lien for materials furnished by complainant to Bempe, and by him used in the construction of a building for Falls. The action is founded on Chapter 103, Acts of [469]*4691889, and can he maintained, if at all, alone under that statute. The constitutionality of the Act is called in question hy demurrer. The demurrer was overruled, and appeal taken by special leave of the Chancellor.

■ The Act, as a whole and in each of its sections, is impeached, as in conflict with the organic law, and, therefore, null and void. This makes a consideration of all its provisions necessary. Eor convenience the different sections will he considered seriatim first, and after that the Act will he considered as a whole.

It is well to observe in the outset that all in-tendments arc in favor of the constitutionality .of an Act of the Legislature, passed with the forms and ceremonies requisite to give it the force of law; and that, where one construction will make a statute void on account of conflict with the Constitution, and another would render it valid, the latter will he adopted hy the Courts, even though the former, at first view, he otherwise the more natural interpretation of the language used.

Every reasonable doubt must be solved in favor of the legislative action. Sutherland on Statutory Construction, Sec. 332; Cooley’s Const. Lim. (5th Ed.), p. 218; 3 Am. & Eng. Ency. of Law, 673,. 674; Morrell v. Fickle, 3 Lea, 81; Garvin v. State, 13 Lea, 162.

The first section is as follows: “That Section 2 of the Act of the Legislature of 1881, Chapter 67, above referred to in this caption, shall be amended [470]*470so as to read as follows, viz.: ‘Every journeyman, or other person, employed by sucli mechanic, founder, or machinist to work on the buildings, fixtures, machinery, or improvements, or to furnish materia] for the same, shall have this lien for his work or material; Provided, That within thirty days after the building is completed, or the contract of such laborer, mechanic, or workman shall expire, or he be discharged, he or they shall notify, in writing, the owner of the property on which the building or improvement 'is being made, or his agent or attorney, if he reside out of the county, that said lien is claimed, and said lien shall continue for the space of ninety days from the date of said notice in favor of such subcontractor, mechanic, or laborer, and the same shall have precedence over all other liens for such time; Provided, A. statement of the amount due for such work, labor, or materials shall bo filed with the County Register, who- shall note the same for registration, and put it on record in the trust book in his office," for which he shall have fifty cents, and also twenty-five cents for registering the affidavit to the same, which shall be paid by the party filing the same, but said fee shall be receipted for on the statement of account, and shall be charged as part of the cost, and this registration shall be notice to all persons of the existence of such lien.’ ”

This section gives all subcontractors and material-men (“every journeyman or other person”) employed [471]*471by the original contractor (“such mechanic, founder’, or machinist”) to work or furnish material, a lien for their work or material, on the two conditions mentioned respectively in the two provisos. The original contractor is the person who has undertaken the work of construction, erection, etc., “by special contract with the owner or his agent,” as prescribed by § 1981 of the Code of 1858.

By §1986 of that Code the same lien was given to the same classes of persons, on condition that notice, in writing, of an intention to claim,, it be communicated to the owner of the property at the time of beginning to work or furnish materials. That section was- amended by. the Act of 1881, Chapter 67, Section 2, so as to give the lien if such written notice be served on the owner during the progress of the work, or after its completion, if before the contractor has been paid — the amount of such lieu not to exceed the amount due, or to become due, to the original contractor.

Section 1986 of the Code, as thus amended by the Act of 1881, is the statute amended and superseded by the first section of the Act of 1889, which has just been quoted in full.

Thus it is seen that the same idea of protection and compensation to the subcontractor and material-man has found expression, in one form or another, in successive Acts since 1845, when the said section (1986) was first enacted. . It cannot, therefore, be said that the scheme is either novel or without recurring legislative indorsement in this State.

[472]*472The lien given by the Act of 1845 has been enforced by this Court in many cases without the expression of even a doubt as to the constitutionality of the enactment; and there is as little room for doubt with respect to the validity of the amendatory Act of 1881.

The corresponding provision of the Act of 1889 is assailed, upon the assumption (1) that it undertakes to appropriate the property of the owner for the benefit of a person with whom he has made ^ no contract; (2) that this result may be accomplished, though the owner have no notice of the claim until after he has paid the original contractor in full; and (3) that the aggregate of the claims of subcontractors and material-men may exceed the amount agreed to 'be paid the original contractor, in which case the owner will be compelled to pay more than the contract price for the advantages received.

The provision is not fairly subject to all of these animadversions, and such o'f them as are well made do not render it obnoxious to the Constitution.

It is true that a lien is provided for persons with whom the owner is supposed to have no direct contractual relations, but that fact alone does not invalidate the Act; for the owner must be held to a knowledge of the existing law on the subject, and to the presumption that he employed the original contractor and gave out his work with reference to that law. The right of lien to [473]*473subcontractors and material-men is, by operation of law, incorporated into and made a part of the owner’s contract as much as if expressly included and written therein. lie contracts about a subject in whieli the law declares certain advantages to all persons concerned, whether by direct contract with him or by the employment of his contractor. The law declares that a lien shall exist in favor of the subcontractor and material-man in certaiu contingencies; hence, the owner who makes the contemplated contract cannot justly complain of the legal result, especially when he receives the benefit of the labor and material of those for whom the lien is provided, and who often have no other means of compensation. The enforcement of this- law does not necessarily result in loss to the owner, nor take from him something for nothing.

The second criticism, involving the proposition that the owner may be compelled to pay the subcontractor and material-man after he has already paid the original contractor, is true literally; but it is not true in the sense that it ascribes to the statute a purpose of enforcing double payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Bobo
727 S.W.2d 945 (Tennessee Supreme Court, 1987)
Silverman v. Gossett
553 S.W.2d 581 (Tennessee Supreme Court, 1977)
Blankenship v. Old Republic Insurance Co.
539 S.W.2d 23 (Tennessee Supreme Court, 1976)
Metropolitan Government of Nashville & Davidson County v. Reynolds
512 S.W.2d 6 (Tennessee Supreme Court, 1974)
State ex rel. Russell v. LaManna
498 S.W.2d 891 (Tennessee Supreme Court, 1973)
State ex rel. Cole v. City of Hendersonville
445 S.W.2d 652 (Tennessee Supreme Court, 1969)
Metropolitan Government of Nashville v. Hillsboro Land Co.
436 S.W.2d 850 (Tennessee Supreme Court, 1968)
Ellenburg v. State
384 S.W.2d 29 (Tennessee Supreme Court, 1964)
Thomas v. Noe
301 S.W.2d 391 (Court of Appeals of Tennessee, 1956)
Great Atlantic & Pacific Tea Co. v. McCanless
157 S.W.2d 843 (Tennessee Supreme Court, 1942)
Tennessee Electric Power Co. v. Mayor of Fayetteville
114 S.W.2d 811 (Tennessee Supreme Court, 1938)
Richmond Screw Anchor Co. v. E. W. Minter Co.
300 S.W. 574 (Tennessee Supreme Court, 1927)
Steele v. Louisville & Nashville R. R. Co.
285 S.W. 582 (Tennessee Supreme Court, 1926)
Foster & Creighton Co. v. Graham
285 S.W. 570 (Tennessee Supreme Court, 1926)
Kee v. Parks
283 S.W. 751 (Tennessee Supreme Court, 1926)
Bank of Commerce & Trust Co. v. Senter
149 Tenn. 569 (Tennessee Supreme Court, 1923)
Richardson v. Lanius
150 Tenn. 133 (Tennessee Supreme Court, 1923)
Kingsport Brick Corp. v. Bostwick
145 Tenn. 19 (Tennessee Supreme Court, 1921)
Wilson v. State
143 Tenn. 55 (Tennessee Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
16 S.W. 1045, 90 Tenn. 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-manufacturing-co-v-falls-tenn-1891.