GII Industries, Inc. v. New York State Department of Transportation (In re GII Industries, Inc.)

464 B.R. 557
CourtUnited States Bankruptcy Court, E.D. New York
DecidedSeptember 30, 2011
DocketBankruptcy Nos. 04-27013-CEC, 04-27015-CEC, 06-42964-CEC, 06-42966-CEC, 06-43325-CEC; Adversary No. 07-1464-CEC
StatusPublished
Cited by3 cases

This text of 464 B.R. 557 (GII Industries, Inc. v. New York State Department of Transportation (In re GII Industries, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GII Industries, Inc. v. New York State Department of Transportation (In re GII Industries, Inc.), 464 B.R. 557 (N.Y. 2011).

Opinion

DECISION

CARLA CRAIG, Chief Judge.

This matter comes before the Court on the complaint of GII Industries, Inc. f/k/a Grace Industries, Inc. (“Grace”), seeking payment from the New York State Department of Transportation (“DOT” or “State”) for amounts allegedly due on account of services Grace rendered to the DOT under a contract to reconstruct a portion of the West Side Highway in New York City. A bench trial was conducted to determine the appropriate cost methodology to calculate Grace’s damage claim against the DOT, and to determine whether Grace was entitled to prejudgment interest on that claim. For the reasons set forth below, Grace is instructed to calculate its damages using the total cost method, and is granted prejudgment interest on its damage claim from May 8, 2003.

JURISDICTION

This Court has jurisdiction over this matter pursuant to 28 U.S.C. § 1334(b), and the Eastern District of New York standing order of reference dated August 28, 1996. Pursuant to the Joint Pre-Trial Order (“JPTO”), the parties have stipulated that this matter is a core proceeding under 28 U.S.C. § 157(b). (JPTO at ¶ 73.) See 28 U.S.C. § 157(c)(2). This decision constitutes the Court’s findings of fact and conclusions of law to the extent required by Federal Rule of Bankruptcy Procedure 7052.

BACKGROUND

The following facts are undisputed.

On March 26, 1998, the State of New York, acting by and through the DOT, [561]*561began soliciting bids for a contract (the “Contract”) to reconstruct Route 9A, the West Side Highway, from West 25th Street to West 40th Street in Manhattan (the “Project”). (JPTO at ¶¶1, 4.) The DOT awarded Grace the Contract on May 12,1998. (JPTO at ¶1.)

The Contract contained over three hundred and seventy one items of work to be completed in five sequential stages. (JPTO at ¶¶ 7, 8.)

The Contract divided the Project into an “A” portion and a “B” portion. The “A” portion outlined the tasks Grace was to complete, and detailed the amount Grace would be paid for each item of work. The “B” portion of the Contract concerned the timing of the Project, and set a completion date. The Contract provided that Grace would be entitled to receive a bonus, or be required to pay a penalty, depending on whether the Project was completed before or after the Contract’s completion date. (JPTO at ¶¶ 2, 3.)

Grace was awarded the Contract on the basis of a bid consisting of an “A” portion of $43,744,312 and a “B” portion of 660 days with a $15,000 bonus or penalty for each day finished before or after the completion date. (JPTO at ¶ 5.)

On November 10, 1998, during Grace’s work on the first stage of the Project, Grace struck a 68-inch by 43-inch elliptical pipe. The elliptical pipe, which extended across the highway, did not appear on the drawings or site information provided by the DOT. (JPTO at ¶ 15.)

The following day, Grace sent a letter notifying the DOT of the discovery of the elliptical pipe. In that letter, Grace informed the DOT that the pipe might affect the Project’s schedule and requested that “T & M records be kept to reimburse” Grace for any “additional costs, losses, and expenses arising from and attributable to this changed condition.” (JPTO at ¶ 16; Ex. 5.)

On November 24, 1998, Grace sent a letter informing the DOT that the elliptical pipe was having a major impact on the Project’s scheduling and was preventing Grace from progressing to Stage 2 of the Project. Grace requested “guidance on how to proceed so that the DOT and Grace Industries will be able to assess the impact on the “b” portion of this contract and maintain construction continuity.” (JPTO at ¶ 17; Ex. 6.)

On December 4,1998, the DOT responded to Grace’s letter dated November 24, 1998, instructing Grace to proceed to a modified stage 2. The DOT explained that because the impact to the “B” portion of the Contract could not be assessed at that time, “[t]he progress of the work and the approved CPM schedule will be monitored closely for any delays and/or impacts to the “B” portion of the contract.”1 (JPTO at ¶ 18; Ex. 7.)

Oh September 2, 1999, the State approved Order On Contract (“OOC”) No. 2.2 [562]*56200C2 addressed the engineering and design issues associated with installing a diversion for the elliptical pipe. (Ex. 9).

As a result of the elliptical pipe, the Project’s original five stage plan was modified. On January 31, 2000, Grace and the DOT met to discuss the restaging and the impact the restaging would have on the Project’s CPM schedule. (JPTO at ¶ 25.)

The parties met again on April 25, 2000 to discuss a possible adjustment to Grace’s compensation under the Contract, and a possible extension of time for Grace to complete the Project. (JPTO at ¶ 26.)

On June 28, 2000, the DOT issued OOC7, which extended the “B” portion of the Contract by 579 calendar days because of the restaging of the Project. (JPTO at ¶ 27; Ex. 13.)

On July 13, 2000, the DOT issued OOC8 to compensate Grace for its increased overhead costs beginning as of March 31, 2000 due to the Project’s restaging. Pursuant to OOC8, the State established a force account of $3,000,000.3 (JPTO at ¶ ¶ 28, 29; Ex. 12.) OOC8 also provided that Grace gave proper notice of its delay claim. (JPTO at ¶ 30.)

Between April, 2000, and November, 2000, the parties negotiated the actual labor costs incurred by Grace as a result of the restaging. (SUF at ¶ 64.)4 However, the DOT rejected the CPM-based adjustment to the Contract that Grace proposed. (SUF at ¶ 67.)

Over the next seventeen months, Grace and representatives from the DOT attempted to reach a negotiated agreement regarding Grace’s claim by comparing the resource loading from Grace’s CPM schedule to Grace’s costs attributable to the Project’s restaging. (JPTO at ¶ 32; SUF at ¶ 68.)

On July 13, 2001, Grace completed its work on the project. (JPTO at ¶ 34.) Grace earned the maximum allowable bonus under the amended “B” portion of the Contract, having completed the Project 110 days before the Contract’s modified completion date. On July 17, 2001, the State paid Grace its bonus of $1,650,000. (JPTO at ¶ 35.)

During March, 2002, Grace completed its punch list for the Project. Since that time, the West Side Highway has been fully operational. (JPTO at ¶¶ 36, 37.)

On May 6, 2002, Grace and the DOT met in Albany to discuss what cost methodology should be used to calculate Grace’s claim for additional compensation. (JPTO at ¶ 38.)

The parties met again on July 10, 2002 to continue discussions regarding methodologies of calculating Grace’s claim for additional compensation. (SUF at ¶ 72.) From July 10, 2002 until February 5, 2003, Grace and the DOT continued to negotiate [563]*563the calculation of Grace’s claim for additional compensation. (JPTO at ¶ 39.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
464 B.R. 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gii-industries-inc-v-new-york-state-department-of-transportation-in-re-nyeb-2011.