Gersten Construction Co., a California Corporation v. The United States

346 F.2d 973, 171 Ct. Cl. 205, 1965 U.S. Ct. Cl. LEXIS 122
CourtUnited States Court of Claims
DecidedJune 11, 1965
Docket134-61
StatusPublished
Cited by2 cases

This text of 346 F.2d 973 (Gersten Construction Co., a California Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gersten Construction Co., a California Corporation v. The United States, 346 F.2d 973, 171 Ct. Cl. 205, 1965 U.S. Ct. Cl. LEXIS 122 (cc 1965).

Opinion

COLLINS, Judge.

This action is based upon a contract entered into by plaintiff, a California corporation, and the Department of the Army. The contract which provided for the construction of a Capehart housing project 1 was performed by plaintiff. In its petition, plaintiff seeks to recover the amount of $92,216, plus interest, which amount defendant required plantiff to place in escrow prior to final settlement of the contract. Each party has moved for summary judgment in its favor.

The Corps of Engineers, Department of the Army, issued on March 20, 1958, an invitation for bids regarding the construction of a 618-unit Capehart housing project at Fort Belvoir, Virginia. Plaintiff submitted a bid in the amount of $9,625,926, and, on May 14, 1958, the Corps of Engineers awarded to plaintiff a letter of acceptability. 2 In accord with *975 the requirements of the Capehart procedure, plaintiff, the “eligible builder,” accomplished the organization of four Delaware corporations which were to be the “mortgagor-builders.” 3 Also, plaintiff arranged to obtain the necessary financing from the Republic National Bank of Dallas. The bank sought insurance commitments from the Federal Housing Administration.

It was incumbent upon plaintiff to apply through the contracting officer, Col. George B. Sumner of the Corps of Engineers, to the Secretary of Labor for a determination of the current prevailing wages. As provided in the invitation for bids, the prevailing wage schedule would be used by the Federal Housing Commissioner to determine the appropriate adjustment in the contract price. In response to plaintiff’s application, the Secretary of Labor issued a wage determination which was received by the contracting officer on June 11, 1958; the' wages indicated in this determination were higher than those contained in the tentative schedule attached to the invitation for bids.

A copy of the new wage schedule was sent to the Federal Housing Administration. Also, Mr. Edward Kircher, an employee of the Corps of Engineers, telephoned the FHA and informed Mr. Ralph Cooper, the assistant chief architect of the District of Columbia Insuring Office of the FHA, that the Corps of Engineers was planning to negotiate with plaintiff an increase in the contract price. Mr. Cooper declined to take part in the negotiations; however, he expressed the opinion that the negotiated amount would be acceptable to the FHA so long as that amount was below $10,200,000, the statutory limit for the project.

Subsequently, plaintiff and the office of the contracting officer agreed that the proper increase, on account of the higher schedule of prevailing wages, would be $242,609.81. On June 17, 1958, the contracting officer wrote the FHA (i. e., Mr. Thomas C. Barringer, the director of the District of Columbia Insuring Office) that, if the agreement were acceptable to the FHA, the contract price would then be $9,808,535.81. 4 Noting that the initial closing was tentatively scheduled for June 24, 1958, the contracting officer requested that the FHA advise him promptly of the maximum insurable mortgage amounts.

No formal approval by the FHA of the negotiated adjustment was ever sent. However, on June 18, 1958, the FHA issued to the Republic National Bank and to plaintiff revised commitments for insurance, the total of which ($9,808,-535.81) included the wage adjustment negotiated by plaintiff and the contracting officer. Also, plaintiff and each of the mortgagor-builders (the Delaware corporations then owned by plaintiff) were required to execute a “trade payment breakdown,” i. e., an FHA form indicating the amount of expense attributable to the various building trades, etc. The total cost shown on the trade payment breakdowns was the amount agreed upon by plaintiff and the contracting of *976 fleer. These documents were accepted by the FHA (and by the Department of the Army) on June 24, 1958.

By June 26, 1958, the process of “initial closing” had been completed. In addition to the issuance of the insurance commitments and the approval of the trade payment breakdowns, there took place (on June 18, 1958) the execution of a tripartite housing contract by the Department of the Army, plaintiff, and each of the Delaware corporations. The total price of the four housing contracts reflected the wage adjustment agreed upon by plaintiff and the contracting officer. Plaintiff was to receive its payments from the respective mortgagor-builders (the four Delaware corporations). Simultaneous with the execution of the housing contracts, each of the mortgagor-builders entered into a building loan agreement with the Republic National Bank (the mortgagee).

The bank agreed to loan to each of the mortgagor-builders the total price of the housing project at the respective mortgage area. In turn, each Delaware corporation executed a note secured by a mortgage; the notes were endorsed for mortgage insurance by the Federal Housing Commissioner. Another aspect of the initial closing was plaintiff’s depositing in escrow the stock of the Delaware corporations; upon completion of the project, the stock would be transferred to the Department of the Army.

Subsequent to the completion of the initial closing, plaintiff began the construction of the housing project. In March 1959, approximately 8 months after plaintiff had begun construction, the Comptroller General, in a report to Congress pertaining to the Fort Belvoir housing project, reviewed the circumstances of the adjustment of the contract price. The Comptroller General recommended that the Federal Housing Commissioner reconsider the wage adjustment and then advise the Corps of Engineers of the amount which should have been included as the wage adjustment and that the Corps of Engineers adjust the contract accordingly.

On May 18, 1959, after the report of the Comptroller General, Mr. Thomas C. Barringer of the FHA wrote the contracting officer that:

Pursuant to the * * * [invitation for bids, etc.], the Commissioner (FHA) has determined that an amount of $150,392 is the sum necessary to reflect the increase attributable to the difference between the prevailing wage schedules dated March 17, 1958 and May 28, 1958. * * *

The contracting officer, in his reply of June 4, 1959, expressed the opinion that the previously accepted contract price, which contained the negotiated wage adjustment of $242,609.81, was legally binding and no longer subject to revision. The contracting officer stated that the parties had considered that the actions of the FHA in issuing revised insurance commitments and in endorsing the mortgage notes constituted approval by the FHA of the negotiated wage adjustment. On July 10, 1959, the Federal Housing Commissioner sent to the Comptroller General a letter which quoted the opinion of the contracting officer that the contract price was not subject to revision. The Commissioner then added, “If this opinion is correct, it will be impossible of course for the Corps of Enginers to take the action recommended in your report [to the Congress].”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Len Co. & Associates
174 Ct. Cl. 1278 (Court of Claims, 1966)
Murray-Sanders Constructors
173 Ct. Cl. 1184 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
346 F.2d 973, 171 Ct. Cl. 205, 1965 U.S. Ct. Cl. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gersten-construction-co-a-california-corporation-v-the-united-states-cc-1965.