Georgia Power Company v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 26, 2018
Docket17-1492
StatusPublished

This text of Georgia Power Company v. United States (Georgia Power Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Georgia Power Company v. United States, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 17-1492 C

(E-Filed: March 26, 2018)

) GEORGIA POWER COMPANY, ) ) Plaintiff, ) Motion to Dismiss; RCFC 12(b)(6); ) Collateral Estoppel; Covenant of Good v. ) Faith and Fair Dealing. ) THE UNITED STATES, ) ) Defendant. ) )

Alan T. Rogers, Birmingham, AL, for plaintiff.

Borislav Kushnir, Washington, DC, with whom were Chad A. Readler, Principal Deputy Assistant Attorney General, Robert E. Kirschman, Jr., Director, Allison Kidd-Miller, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant.

OPINION

CAMPBELL-SMITH, Judge.

Before the court is defendant’s motion to dismiss two claims in plaintiff’s complaint—the first relating to the recovery of certain fees levied by the Nuclear Regulatory Commission (NRC), and the second to plaintiff’s claim for breach of the covenant of good faith and fair dealing. See ECF No. 7. According to defendant, plaintiff litigated the issue of NRC fees in the previous iteration of this case, and thus, its claims are barred by the doctrine of collateral estoppel. See id. at 1-2. In addition, defendant argues that the court should dismiss plaintiff’s claim that defendant breached the covenant of good faith and fair dealing as duplicative of its claim for breach of contract, on which defendant concedes “liability already is established.” Id. at 2. Defendant’s motion to dismiss is fully briefed and ripe for a decision by the court. See ECF Nos. 13 (response brief); 18 (reply brief). For the following reasons, defendant’s motion is GRANTED. I. Background

This is the fourth round of litigation brought by plaintiff against the United States in an effort to recover damages related to the continuing breach of a contract for the removal of spent nuclear fuel (SNF) from plaintiff’s facilities. See ECF No. 1.1 Plaintiff initially filed suit in 1998, and the court ultimately granted summary judgment in its favor on the issue of liability. See S. Nuclear Operating Co., et al. v. United States, Case No. 98-614, ECF Nos. 1 (complaint); 234 (order of April 7, 2004). The court determined damages in the trial that followed. See S. Nuclear Operating Co., et al. v. United States, 77 Fed. Cl. 396 (2007). Although the United States Court of Appeals for the Federal Circuit reversed a portion of the damages award on appeal, it affirmed that “liability in these SNF cases has been established.” S. Nuclear Operating Co., et al. v. United States, 637 F.3d 1297, 1299 (Fed. Cir. 2011). Following remand, the parties settled the remaining issues relating to damages accrued through December 31, 2004. See S. Nuclear, Case No. 98-614, ECF Nos. 422 (stipulation on damages); 424 (judgment).

Because this situation involves a continuing breach on the government’s part, namely the government’s continuing failure to remove the SNF from plaintiff’s facilities, plaintiff filed a second case in this court in an effort to recover damages accrued from January 1, 2005, through December 31, 2010. See Alabama Power Co., et al. v. United States, Case No. 08-237, ECF No. 1. Plaintiff’s damages claim consisted of alleged entitlement to: (1) costs incurred for certain plant construction, maintenance and operation; (2) costs incurred for certain activities related to the handling of SNF; and, (3) a portion of the generic fees collected by the NRC. See generally Alabama Power Co., et al. v. United States, 119 Fed. Cl. 615 (2014). The court held that plaintiff was entitled to a significant recovery, but that award did not include the recovery of NRC fees. See id. at 641. Specifically, the court held that plaintiff failed to prove the causal relationship between defendant’s breach of contract and the subsequent increase in NRC fees. See id. at 640. Absent proof of causation, plaintiff was not entitled to recover the fee differential. See id. Importantly, for the purpose at hand, the court concluded this section of its opinion by noting:

1 The history of these agreements is long and complex, and the court has discussed the details at length in previous opinions. See Alabama Power Co., et al. v. United States, 119 Fed. Cl. 615 (2014); S. Nuclear Operating Co. v. United States, 77 Fed. Cl. 396 (2007), aff’d in part, vacated in part, 637 F.3d 1297 (Fed. Cir. 2011). Because the specifics of the contracts at issue in the litigation more broadly are not directly relevant to the question immediately before the court, the court will not repeat them here. 2 To be clear, the court does not hold that plaintiffs cannot, as a matter of law, establish causation. But in this case, considering the Federal Circuit’s binding precedent, plaintiffs have failed to present sufficient evidence to support a finding that the government’s breach was a substantial causal factor in the NRC’s decision to increase fees.

Id. at 641.

In plaintiff’s third case, which is still pending before the court, it seeks to recover damages incurred since January 1, 2011. See Georgia Power Co. v. United States, Case No. 14-167, ECF No. 1 at 2. As part of those damages, plaintiff again sought to recover a portion of the generic NRC fees. Id. at 7 (alleging that plaintiff “has also incurred increased and/or additional regulatory fees, including but not limited to the dry storage portion of the Spent Fuel Storage/Reactor Decommissioning Fee imposed by the Nuclear Regulatory Commission, as a result of the Government’s partial breach of the Standard Contract”). Defendant filed a motion for partial summary judgment on the discrete issue of NRC fees, and the court granted the requested relief, determining that plaintiff’s claim for NRC fees was barred by the doctrine of collateral estoppel. Following an extended analysis, the court concluded that “[c]onsidering the findings of the court in the previous round of litigation, and the allegations presented to the court in the instant matter, the court finds that plaintiffs are collaterally estopped from alleging entitlement to recovery of NRC fees.” Alabama Power Co., et. al v. United States, 132 Fed. Cl. 412, 418 (2017).

Now, in its fourth case before this court, plaintiff yet again seeks to recover NRC fees. The allegation is nearly identical to its counterpart in plaintiff’s third case (Georgia Power, Case No. 14-167), stating that plaintiff “has also incurred increased and/or additional regulatory fees and other types of fees, including but not limited to the dry storage portion of the Spent Fuel Storage/Reactor Decommissioning Fee imposed by the Nuclear Regulatory Commission, as a result of the Government’s partial breach of the Standard Contracts.” ECF No. 1 at 7.

Plaintiff’s complaint in this matter alleges both a claim for partial breach of contract, and a claim for breach of the implied covenant of good faith and fair dealing. As noted above, the Federal Circuit has previously affirmed that “liability in these SNF cases has been established,” on a partial breach of contract theory. S. Nuclear Operating Co., 637 F.3d at 1299. As such, according to defendant, plaintiff’s claim for breach of the implied covenant of good faith and fair dealing should be dismissed as unnecessary and duplicative. See ECF No. 7 at 2.

3 II. Legal Standards

A complaint should be dismissed under Rule 12(b)(6) of the Rules of the Court of Federal Claims (RCFC) “when the facts asserted by the claimant do not entitle him to a legal remedy.” Lindsay v. United States, 295 F.3d 1252, 1257 (Fed. Cir. 2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commissioner v. Sunnen
333 U.S. 591 (Supreme Court, 1948)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Southern Nuclear Operating Co. v. United States
637 F.3d 1297 (Federal Circuit, 2011)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Laguna Hermosa Corp. v. United States
671 F.3d 1284 (Federal Circuit, 2012)
In Re Jerre M. Freeman
30 F.3d 1459 (Federal Circuit, 1994)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
Bristol Bay Area Health Corporation v. United States
110 Fed. Cl. 251 (Federal Claims, 2013)
Dotcom Associates I, LLC v. United States
112 Fed. Cl. 594 (Federal Claims, 2013)
Cfs International Capital Corporation v. United States
118 Fed. Cl. 694 (Federal Claims, 2014)
Alabama Power Company v. United States
119 Fed. Cl. 615 (Federal Claims, 2014)
Entergy Nuclear Indian Point 2, LLC v. United States
121 Fed. Cl. 667 (Federal Claims, 2015)
Biery v. United States
818 F.3d 704 (Federal Circuit, 2016)
Georgia Power Company v. United States
132 Fed. Cl. 412 (Federal Claims, 2017)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Young v. United States
94 Fed. Cl. 671 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Georgia Power Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/georgia-power-company-v-united-states-uscfc-2018.