General Dynamics Corp. v. United States

202 Ct. Cl. 347, 1973 U.S. Ct. Cl. LEXIS 75, 1973 WL 21349
CourtUnited States Court of Claims
DecidedJune 20, 1973
DocketNo. 442-70
StatusPublished
Cited by6 cases

This text of 202 Ct. Cl. 347 (General Dynamics Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics Corp. v. United States, 202 Ct. Cl. 347, 1973 U.S. Ct. Cl. LEXIS 75, 1973 WL 21349 (cc 1973).

Opinion

Per Curiam :

This case comes before the court on requests for review, under Rules 166(e) and 54(b) (3), of a recommended decision filed May 30, 1972, by Trial Commissioner Mastín G. White pursuant to Rule 166(c) wherein he denied plaintiff’s motion for summary judgment and allowed defendant’s cross motion.

Since the court is in agreement with the opinion and recommendation of the Commissioner, with a modification thereof by the court, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set •forth. Therefore, plaintiff is not entitled to recover and the petition is dismissed.

Commissioner White’s opinion, with a modification by the court, is as follows:

In this case, the court is called upon to review, under the standards prescribed in the Wunderlich Act (41 U.S.C. §§ 321,322), a decision by the Armed Services Board of Contract Appeals dated September 30,1968 (ASBCA Nos. 12814 and 12890). The Board held that an item of $882.04 was not properly chargeable by the plaintiff against a cost-reimbursement contract, No. AF 33 (600)-40599, between the plaintiff and the Department of the Air Force, and that an item of $17,355.11 was not properly chargeable against a similar contract, No. AF 04(695) -514.

The items of $882.04 :and $17,355.11 represented portions [351]*351of the total expense ($2,843,256) incurred by the plaintiff during 1964 and 1965 in fabricating and demonstrating an aircraft known as the Charger. The plaintiff’s costs in connection with the manufacture and demonstration of the Charger were initially charged on the plaintiff’s books to an overhead account that covered selling costs. From such overhead account, the plaintiff then allocated the Charger costs on a proportionate basis to approximately 160 cost-reimbursement contracts ('including Nos. AF 33(600)^40599 and AF 04(695)-514 which the plaintiff was performing for agencies at the Defense Department.

Thus, the outcome of the present case will affect claims totaling $2,843,256 under approximately 160 contracts.

The Charger was an outgrowth of the plaintiff’s interest in developing a type of light-armed reconnaissance aircraft which would be suitable for use in counter-insurgency operations. (This type of aircraft is usually referred to in the record, and will sometimes be referred to hereafter in the opinion, as “LARA/COIN.”) Since such an aircraft was thought of as being used in counter-insurgency operations under primitive conditions, it would be necessary that the aircraft be capable of operating from short, unimproved airstrips. This objective was known as the STOL (short take-off and landing) concept. The plaintiff has begun working on the concepts involved in a LARA/COIN, particularly the STOL concept, in June of 1962. The plaintiff’s research efforts in this field continued through the remainder of 1962 and 1963, and into 1964.

In August of 1962, following discussions of the subject in military and industrial circles, the Marine Corps Development Center wrote a specific operational requirement for a LARA/COIN. A year later, in August of 1963, the Advanced Research Project Agency of the Defense Department developed a LARA/COIN specification, which included performance characteristics for the aircraft desired. Then on October 28, 1963, the Department of Commerce Business Daily carried an announcement of a forthcoming competitive procurement by the Government of a LARA/COIN.

The plaintiff decided in 1963 to pursue the LARA/COIN [352]*352program more actively, as the potential business was estimated by the plaintiff to involve approximately 1,000 aircraft, representing total sales of from $200,000,000 to $300,000,000. By March of 1963, the plaintiff had developed various configurations of such a potential aircraft. As of September 1963, the plaintiff’s activities in this field were centered on bid and proposal efforts, pre-design work on the STOL concept, independent research and development, some wind tunnel work, and customer sales activities.

On December 5,1963, the Department of the Navy issued a request for proposals (“RFP”) on a LARA/COIN project. Engineering proposals were to be submitted by March 9,1964, and price proposals were to be submitted by March 23,1964. The NAYY RFP stated in part as follows:

Upon approval and funding of this program by the Secretary of Defense, anticipated in first quarter of FY 1965, it is planned to award a contract to the responsible bidder [sic] whose proposal is judged to be most advantageous to the Government. The objective of this program is the development of a versatile airplane of minimum size, complexity and price which from the outset is designed for operations by field forces in a primitive environment with a minimum of logistic support. In the evaluation of proposals significant weight will be given to performance which exceeds the requirements of the Type Specification (TS-158) in addition to design, timing and price. The ultimate performance goal for this airplane is the accomplishment of the Armed Reconnaissance Mission with takeoff and landing distances of 500 feet over a 50 foot obstacle.

TS-158, which was referred to in the Navy RFP, covered “the essential requirements for the design and construction” of the LARA/OOIN. In a paragraph entitled “GUARANTEED TABULATED PERFORMANCE,” it was stated (among other things) that the “Takeoff [and landing] distance over a 50 foot obstacle at sea level” must be “less than 800 ft.” However, the specification further stated that it was desired that the prescribed performance characteristics be bettered, if possible.

The Navy RFP stated that the initial contract to be [353]*353awarded would be on a fixed-price basis for four prototype aircraft, and would include options under which, the Government could purchase (1) up to three additional prototype aircraft and (2) a total of 500 production models over a 3-year period beginning 2 calendar years after the date of the initial contract award.

In March of 1964, the plaintiff and six other firms submitted engineering and price proposals to the Navy in response to the RFP of December 5,1963.

The plaintiff’s technical approach to the STOL concept was distinct and consisted of three basic characteristics: a fully movable horizontal tail; slipstream wind flaps that would be deflectable to a full 90 degrees in order to generate the required lift; and a landing gear with a very high sink rate, which would enable the aircraft to “fly into the ground and then stop quickly.”

Before March 1964, nothing close to these technical concepts had ever been demonstrated in an aircraft. The closest comparable aircraft was a NASA research vehicle known as the VZ-3, which had incorporated short take-off and landing techniques a few years prior to 1964. Problems had been encountered with the NASA test vehicle, and they created doubt among NASA, Navy, Air Force, and Army technical personnel as to whether the plaintiff’s concepts could achieve the proposed STOL performance and flying qualities.

The plaintiff concluded that proof of the soundness of its STOL concepts was crucial to the LARA/COIN program.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Aleynikov
737 F. Supp. 2d 173 (S.D. New York, 2010)
Coflexip & Services, Inc. v. United States
36 Cont. Cas. Fed. 75,867 (Court of Claims, 1990)
AT & T Technologies, Inc. v. United States
35 Cont. Cas. Fed. 75,731 (Court of Claims, 1989)
Leesona Corp. v. United States
599 F.2d 958 (Court of Claims, 1979)
Grumman Aerospace Corp. v. United States
587 F.2d 498 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
202 Ct. Cl. 347, 1973 U.S. Ct. Cl. LEXIS 75, 1973 WL 21349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-corp-v-united-states-cc-1973.