General Construction v. Greater St. Thomas Church

CourtCourt of Appeals of Tennessee
DecidedSeptember 17, 2002
DocketW2001-01588-COA-R3-CV
StatusPublished

This text of General Construction v. Greater St. Thomas Church (General Construction v. Greater St. Thomas Church) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Construction v. Greater St. Thomas Church, (Tenn. Ct. App. 2002).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON September 17, 2002 Session

GENERAL CONSTRUCTION CONTRACTORS ASSOCIATION, INC., v. GREATER ST. THOMAS BAPTIST CHURCH

Direct Appeal from the Chancery Court for Shelby County No. 105579-2 Floyd Peete, Jr., Chancellor

No. W2001-01588-COA-R3-CV - Filed December 10, 2002

This appeal arises from a dispute over the construction of a church. Both parties alleged that the other breached the construction contract. The trial court found the Church to be in breach, awarded damages to the Contractor, and this appeal ensued. We affirm in part and reverse in part.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed in part; Reversed in part; and Remanded

DAVID R. FARMER , J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S., and ALAN E. HIGHERS, J., joined.

James H. Kee, Memphis, Tennessee, for the appellant, Greater St. Thomas Baptist Church.

Regina C. Morrison and James W. Hodges, Jr., for the appellee, General Construction Contractors Association, Inc.

OPINION

In May, 1994 General Construction Contractors Association, Inc., d/b/a General Construction Contractor Associates, Inc. (GCCA) entered into a contract with Greater Saint Thomas Baptist Church (Church) to construct a church facility in Memphis, Tennessee. Construction began on this facility in August of the same year. Problems during the construction increased the cost of the job, and a dispute arose between GCCA and the Church over who was responsible for paying these increases. The dispute resulted in a verbal agreement by the Church to pay part of the increased costs. To avoid future problems, it was decided that all remaining correspondence between GCCA and the Church should pass through a surety company. This company would receive GCCA's invoices and pay them. Also during this meeting, Church approved the payment of the first "draw" to the surety company1.

In mid-October, GCCA ceased work on the site stating that additions or corrections to the plans and specifications would be needed before construction could continue. Shortly thereafter, GCCA submitted a second “draw” application to the surety company, including some items included from the first “draw” request, but not yet paid. The Church did take steps to check the second “draw” request, though it never paid any money on it. In November, an attorney for the Church requested, pursuant to its contract rights, copies of documents related to GCCA’s construction work. GCCA responded with a letter stating it was owed several thousand dollars by the Church through its failure to pay its “draw” requests and that “[GCCA would] not continue to do all of the work and not be compensated." GCCA then referred all future correspondence from the Church to its legal counsel. In December, Church notified GCCA it was terminating the contract for “nonperformance.” In April, 1995, GCCA filed a complaint seeking to attach its lien against the property. 2 GCCA subsequently filed suit seeking not only the lien amount, but also lost profits and additional damages. The Church filed a counterclaim against GCCA alleging breach of contract and seeking damages. The trial court, sitting without a jury, found that the Church, and not GCCA, had breached the contract between the parties in an Order dated October 21, 1996. As such, the Church was denied relief and GCCA was granted damages,3 the determination of which was reserved pending submission of post trial briefs as to damages. The chancellor issued a Final Judgment on December 2, 1998, awarding GCCA actual damages in the amount of $35,868.54, lost profits of $76,200.00, recording fees of $220.00 and “pre-judgment interest in the statutory amount to begin October 10, 1994 to the date of entry of this Court’s final judgment.”

On December 30, 1998 the Church filed a Motion to Alter or Amend/New Trial. GCCA responded to this motion with its own Motion to Strike, stating that an ‘attorney of record’ had not filed the motion within the required period. Upon receiving a copy of GCCA’s motion, the Church's trial lawyer signed the motion. Nevertheless, the trial court granted the ‘Motion to Strike.’ On appeal to this Court (Church I), the Church argued that an undisputed ‘attorney of record’ had signed the motion as permitted under the Tennessee Rules of Civil Procedure. In an

1 A “draw” is a partial payment for work comp leted in a construction contract. In this case, a “draw” request would be subm itted to the Church. T he Church's represe ntative would check and appro ve all or part of the "d raw" req uest and those approved funds would be paid to GCCA.

2 GC CA’s Notice of Lien was registered and recorded in the Shelby County Registrar’s Office on December 22, 1994 . Notice of the lien was contemporaneously received by the Church.

3 It should be noted that GST was granted a judgment against the Surety in the amount of $112,06 8.35, who could not be loc ated a nd wa s never served. This amount differs from the amount awarded GCCA by a mere nineteen cents, and presu mab ly was meant to reflect the actual judgment against GST. If the Surety were to be sub sequently located, and this judgment were allowed to stand , the result would be a w indfall for GST . Accordingly, GST’s judgment against the Surety is modified to reflect the amo unt of the final judgment on this appe al.

-2- order dated October 9, 2000 this Court agreed that the trial court’s granting of the ‘Motion to Strike’ was in error and remanded the case for consideration of the Church’s ‘Motion to Alter or Amend/New Trial.’ The Church, as Appellant in Church I, had presented several additional issues for decision by this Court, which we declined to address as they did not bear upon our decision. In remanding the case, this Court noted that the trial court had never considered the Church’s motion on its merits and specifically stated that either party would have the option to perfect a timely appeal following such a ruling by the trial court. In other words, the only issue before this Court in Church I was the propriety of the order granting GCCA’s Motion to Strike. The other issues raised by Appellant were, therefore, not addressed.

On February 8, 2001, subsequent to this Court’s decision, but prior to the trial court’s ruling on the Motion to Alter or Amend/New Trial, the Church submitted a First Amendment to Motion to Alter/New Trial, adding thirteen additional assignments of error to the four alleged in the original motion. The trial court denied the Church’s Motion to Amend/New Trial by an order dated June 15, 2001. In the order the chancellor specifically stated that the order was based upon, inter alia, “Defendant’s First Amendment to Motion to Alter Judgment/For New Trial . . . .” This appeal followed.

Appellant presented twelve (12) issues on appeal, discussion of the following six (6) are necessary for our determination of this matter:

(1) The Chancellor erred in concluding that the Church breached the contract and in concluding that GCCA did not breach the contract.

(2) The Chancellor erred in the construction and/or application of the construction contract by failing to conclude same was an absolute contract containing the contractor’s express warranty that the plans and specifications were sufficient to complete the work and obligated the contractor to perform any misdescribed or omitted work without additional cost to the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. Brooks
992 S.W.2d 403 (Tennessee Supreme Court, 1999)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Scholz v. S.B. International, Inc.
40 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
Marshall v. Jackson & Jones Oils, Inc.
20 S.W.3d 678 (Court of Appeals of Tennessee, 1999)
Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc.
521 S.W.2d 578 (Tennessee Supreme Court, 1975)
Security Federal Savings & Loan Ass'n of Nashville v. Riviera, Ltd.
856 S.W.2d 709 (Court of Appeals of Tennessee, 1993)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Anderson-Gregory Co. v. Lea
370 S.W.2d 934 (Court of Appeals of Tennessee, 1963)
Morristown Lincoln-Mercury, Inc. v. Lotspeich Publishing Co.
298 S.W.2d 788 (Court of Appeals of Tennessee, 1956)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Nelson v. Wal-Mart Stores, Inc.
8 S.W.3d 625 (Tennessee Supreme Court, 1999)
Hamblen County v. City of Morristown
656 S.W.2d 331 (Tennessee Supreme Court, 1983)
Hanover Insurance Company v. Haney
425 S.W.2d 590 (Tennessee Supreme Court, 1968)
Smithart v. John Hancock Mut. Life Ins.
71 S.W.2d 1059 (Tennessee Supreme Court, 1934)
Webb v. Aetna Life Insurance Co.
496 S.W.2d 511 (Court of Appeals of Tennessee, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
General Construction v. Greater St. Thomas Church, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-construction-v-greater-st-thomas-church-tennctapp-2002.