Gemini Tech Services, LLC v. United States

United States Court of Federal Claims·Decided September 18, 2025·No. 25-1337·Unpublished

Opinion

In the United States Court of Federal Claims No. 25-1337C (Filed Under Seal: September 8, 2025) (Reissued for Publication: September 18, 2025) 1

************************************ * GEMINI TECH SERVICES, LLC, * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant, * * And * * ACQUISITION LOGISTICS LLC, * * Defendant-Intervenor. * * ************************************

OPINION AND ORDER

This bid protest involves a challenge to the decision by the United States Army (“the Army”) to override an automatic stay pursuant to the Competition in Contracting Act (CICA), 31 U.S.C. § 3553(d)(3)(C)(i). See ECF No. 2 at 1. Presently before the Court is Plaintiff’s, Gemini Tech Services, LLC’s (“Plaintiff’s”) Motion for a Preliminary Injunction which Plaintiff filed on August 11, 2025. See ECF No. 31. The Government and Defendant Intervenor filed their respective Responses to the Motion on August 20, 2025, see ECF No. 37-38, and Plaintiff filed a reply in support of the Motion on August 22, 2025, see ECF No. 39. The Motion is now fully briefed and ripe for decision. On August 28, 2025, the Court heard oral argument. The Court has considered all of the parties’ arguments and addresses the issues that are pertinent to the Court’s ruling in this opinion. For the reasons given below, the Court hereby DENIES Plaintiff’s Motion.

1 The Court issued this opinion under seal on September 8, 2025, and the Court gave the parties ten days to propose the redaction of competition-sensitive, proprietary, confidential, or otherwise protected information. The parties filed a document with proposed redactions. ECF No. 50. Thus, the Court issues the redacted opinion unsealed. I. Background

On July 18, 2025, the Army awarded a task order to Acquisition Logistics LLC (“ALL”) to construct, operate, and maintain a new 5,000-capacity short-term detention facility at Fort Bliss, Texas, on Montana Avenue (“Montana Ave”) for single adults awaiting immigration proceedings or removal from the United States. See Tab 58. Once the Army completes the construction of the Montana Ave detention facility, the Army plans to transfer detainees from an existing detention facility called the Enhanced Hardened Facility (“EHF”), which the Army states has an insufficient capacity, and transfer the detainees to the new Montana Ave facility. ECF No. 37 at 17. The base period for the award is three months long, and in that period the contractor will construct the facility, achieve initial operating capacity for 1,000 detainees, and continue to expand at a rate of 250 detainees per week. Tab 37, AR 01309.

A. Plaintiff’s GAO Protest

On July 28, 2025, Plaintiff filed its protest before the Government Accountability Office (“GAO”) challenging the Agency’s decision to award the contract to ALL. AR 00005-7. Plaintiff raised three allegations in its GAO protest. See AR 00005-7. First, Plaintiff alleged that ALL failed to comply with two material solicitation requirements: proposing a final site design and failing to propose critical utilities. AR 00005. Second, Plaintiff argued that the Army failed to evaluate the quality of offerors’ past performance. AR 00006. Finally, Plaintiff contended that the Army’s responsibility determination was unreasonable. AR 00006-7.

B. The Army’s Override Decision

In this case, a stay of contract performance in this procurement was triggered pursuant to 31 U.S.C. § 3553(d)(3)(A) when Plaintiff filed its currently-pending protest before the GAO on July 28, 2025. See ECF No. 2 at 2. At that point, CICA required the contracting officer to “immediately direct the contractor to cease performance under the contract[.]” 31 U.S.C. § 3553(d)(3)(A)(ii). But instead of doing that, the Army determined it would override the stay and gave an “oral” direction on July 28, 2025, to continue performance under ALL’s task order.

Under CICA and the AFARS, the Army could override the stay only after executing a written determination and notifying GAO, but the Army proceeded with performance without doing either of those things. 31 U.S.C. § 3553(d)(3)(C); AFARS 5133.104(c)(2). The Army eventually notified GAO of its decision three days later on July 31, executed a determination and findings (“D&F”) on August 1, and filed that D&F with GAO the following week on August 4, 2025. Although the Army corrected its error, the Court notes that by proceeding with the contract performance without first notifying GAO and executing a written determination, the Army violated the statute by failing to comply with the CICA stay which was in place.

Plaintiff correctly points out that if the stay override is not removed, the contract here will be completed before the GAO reaches its decision on November 5, 2025. Lilly Decl. ¶ 3. To this point, the Court highlights that though the GAO has a statutory requirement to resolve protests within 100 days, 31 U.S.C. § 3554(a)(1), the Court wonders why the GAO did not expedite its decision-making. See 4 C.F.R. §21.10(a) (“Upon a request filed by a party or on its

2 own initiative, GAO may decide a protest using an express option”). In the case of contracts with a short time frame, the competitive system is open to manipulation.

C. The Army’s Determination and Findings Memorandum

The 10-page D&F, dated August 1, 2025, documents the Army’s rationale. Tab 19. It describes the nature, origin, and urgency of the requirement, as well as the procedures used to solicit the requirement. AR 00324-328. The D&F went on to document the GAO protest filed by Plaintiff, noting “[a]fter consultation with legal, it is the Army’s position that the protestor’s protest lacks merit, and that the Army has strong substantive defenses which it will assert and upon which it will prevail.” AR 00327. The substance of the D&F determination is discussed in further detail below.

II. Jurisdiction and Standard of Review

A. Jurisdiction

The Court of Federal Claims possesses jurisdiction to entertain bid protests pursuant to the Tucker Act, 28 U.S.C. §1491(b)(1). 28 U.S.C. § 1491(b)(4) requires that the Court “review the Army’s decision pursuant to the standards set forth in section 706 of title 5” of the Administrative Procedure Act (APA). See Impresa Construzioni Geom. Domenico Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001). Thus, in a bid protest, applying the APA standard of review, the Court must determine whether the agency’s actions were “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); 28 U.S.C. § 1491(b)(4); Banknote Corp. of Am. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Gemini Tech Services, LLC v. United States, (uscfc 2025).

Gemini Tech Services, LLC v. United States (Gemini Tech Services, LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pai Corp. v. United States
614 F.3d 1347 (Federal Circuit, 2010)
Axiom Resource Management, Inc. v. United States
564 F.3d 1374 (Federal Circuit, 2009)
Somerset Pharmaceuticals, Inc. v. Dudas
500 F.3d 1344 (Federal Circuit, 2007)
Honeywell, Inc. v. The United States v. Haz-Tad, Inc.
870 F.2d 644 (Federal Circuit, 1989)
E.W. Bliss Company v. United States
77 F.3d 445 (Federal Circuit, 1996)
Ramcor Services Group, Inc. v. United States
185 F.3d 1286 (Federal Circuit, 1999)
Advanced Data Concepts, Incorporated v. United States
216 F.3d 1054 (Federal Circuit, 2000)
Beechcraft Defense Company, Llc v. United States
111 Fed. Cl. 24 (Federal Claims, 2013)
Dyncorp International LLC v. United States
113 Fed. Cl. 298 (Federal Claims, 2013)
At & T Corp. v. United States
133 Fed. Cl. 550 (Federal Claims, 2017)
Dell Federal Systems, L.P. v. United States
906 F.3d 982 (Federal Circuit, 2018)
Chapman Law Firm Co. v. United States
62 Fed. Cl. 464 (Federal Claims, 2004)
Automation Technologies, Inc. v. United States
72 Fed. Cl. 723 (Federal Claims, 2006)
Reilly's Wholesale Produce v. United States
73 Fed. Cl. 705 (Federal Claims, 2006)