G.D. Searle & Co. v. Metric Constructors, Inc.

572 F. Supp. 836, 1983 U.S. Dist. LEXIS 12623
CourtDistrict Court, N.D. Georgia
DecidedOctober 18, 1983
DocketCiv. A. C83-1824
StatusPublished
Cited by3 cases

This text of 572 F. Supp. 836 (G.D. Searle & Co. v. Metric Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.D. Searle & Co. v. Metric Constructors, Inc., 572 F. Supp. 836, 1983 U.S. Dist. LEXIS 12623 (N.D. Ga. 1983).

Opinion

ORDER

ROBERT H. HALL, District Judge.

This case is presently before this court on defendant’s motion to stay proceedings pending arbitration. In response to this motion plaintiff has requested this court to enjoin arbitration until this court has ruled on defendant’s motion. Jurisdiction exists pursuant to 28 U.S.C. § 1332. For the reasons stated hereinafter defendant’s motion is GRANTED; plaintiff’s motion is DENIED.

FACTS

In 1981 G.D. Searle & Co. (Searle), a Delaware Corp. entered into a contract with Metric Constructors, Inc. (Metric), a North Carolina corporation, under which Metric was to construct a bulk chemical manufacturing facility for Searle in Augusta, Georgia. The Construction Agreement was executed by Searle on October 12, 1981 and by Metric on October 22, 1981. Under this Agreement Searle was obligated to pay Metric a fixed “Contractor’s Fee” in the amount of $350,000, “Fixed Overhead Costs” of $1,105,910 and “Contractor Reimbursable Costs.” The sum of the “Fixed Overhead Costs” and the “Contractor Reimbursable Costs” was not to exceed $18,904,-000, this sum being known as the “Guaranteed Maximum Cost.” The Construction Agreement also contained an arbitration *838 provision at paragraph 13. This provision, essential to the issues before this court, provides as follows:

Any claim or controversy arising between the parties hereto in connection with this Agreement or with an alleged breach thereof which cannot be settled by mutual agreement of the parties shall be resolved by arbitration held in a location within Richmond County, in the state of Georgia in accordance with the Construction Industry rules of the American Arbitration Association. Contractor shall continue performance of the Work during the pendency of any arbitration proceedings hereunder, unless otherwise directed by Searle in writing.

By October, 1982 Searle had paid Metric a sum equal to the “Guaranteed Maximum Cost.” Construction had not been completed at this point and Metric threatened to terminate the agreement and discontinue construction unless Searle agreed to increase the contract price. By letter agreement dated October 28, 1982 (the “October Agreement”) the parties modified the original agreement. In the October Agreement Searle agreed to pay Metric an additional amount, in excess of the Guaranteed Maximum Cost, as a convenience to allow construction to continue. Searle reserved the right to recover this additional amount. In addition Metric agreed that Searle could hold back 15% of the said additional amounts. Finally, the October Agreement contained the following paragraph:

3. The parties will diligently process the change orders in the manner provided in the [Construction] Agreement and, upon completion of the Work, will submit to arbitration as provided in paragraph 13 of the [Construction] Agreement, any remaining dispute as to whether sums paid hereunder or the Holdback were properly payable to Metric under the [Construction] Agreement ... (emphasis added).

In May, 1983, four months after the scheduled completion date, the working relationship between the two parties was terminated.

On August 12,1983 Metric filed a petition for arbitration with the American Arbitration Association (AAA) demanding Atlanta as the hearing site and seeking the following:

[A]n adjustment to the Guaranteed Maximum Price of its contract with Respondent, for additional and changed work, delays, interferences, disruptions and suspensions of its work, and increased and extended overhead costs associated therewith. Entitlement to such adjustment arises out of changes in the plans and specifications made by the Respondent or its agents, as well as delays and suspensions of the work by Respondent, and acceleration of the pace of work ordered by Respondent.

Metric demanded in relief:

An equitable adjustment of the contract Guaranteed Maximum Price of approximately $9.7 million, and payment of the balance of the unreimbursed cost and fees allowable under the contract.

Subsequent to Metric’s petition, Searle filed an action in Fulton County Superior Court alleging breach of contract and requesting a declaratory judgment on certain issues, primarily the question of whether, and to what extent, an arbitration agreement exists. (G.D. Searle & Co. v. Metric Constructors, Inc., Civil Action File No. D-2494). Defendant removed this action to Federal Court on August 29, 1983 due to diversity jurisdiction and an amount in controversy exceeding $10,000. Defendant subsequently filed a counterclaim and two motions, one for an order compelling arbitration and one for a stay of the proceedings pending arbitration. These two motions were brought pursuant to the Federal Arbitration Act, 9 U.S.C. §§ 3 and 4. Pursuant to 9 U.S.C. § 4 Searle demanded a jury trial.

On September 15, 1983 defendant withdrew its motion to compel arbitration and informed the court that the AAA was proceeding with the administration of the arbitration and that since Searle was not seeking to enjoin the arbitration there was no need to compel Searle to submit. Metric *839 specifically stated that it was not withdrawing the motion to stay the litigation pending arbitration. 1 Because the case is now proceeding to arbitration Searle has brought a motion requesting this court to enjoin arbitration until such time as this court rules on defendant’s motion to stay proceedings.

Further facts will be disclosed as necessary for the discussion of these motions.

DISCUSSION

1. Defendant’s Motion to Stay Pending Arbitration

The key statutory provisions relevant to defendant’s motion are §§ 2 and 3 of the United States Arbitration Act of 1925 (9 U.S.C. §§ 2 and 3). Section 2 provides that a written provision for arbitration “in any maritime transaction or a contract evidencing a transaction involving commerce ... shall be valid, irrevocable and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.” Section 3 requires a federal court in which suit has been brought “upon any issue referable to arbitration under an agreement in writing for such arbitration” to stay the court action pending arbitration once the court is satisfied both that the issue is arbitrable under the agreement and that the applicant for stay is not in default in proceeding with such arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied-Bruce Terminix v. Dobson
628 So. 2d 354 (Supreme Court of Alabama, 1993)
Intercontinental Packaging Co. v. China National Cereals, Oils & Foodstuffs Import & Export Corp.
159 A.D.2d 190 (Appellate Division of the Supreme Court of New York, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
572 F. Supp. 836, 1983 U.S. Dist. LEXIS 12623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gd-searle-co-v-metric-constructors-inc-gand-1983.