Gamble v. Woodlea Construction Co.

228 A.2d 243, 246 Md. 260
CourtCourt of Appeals of Maryland
DecidedMay 4, 1967
Docket[No. 222, September Term, 1966.]
StatusPublished
Cited by8 cases

This text of 228 A.2d 243 (Gamble v. Woodlea Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gamble v. Woodlea Construction Co., 228 A.2d 243, 246 Md. 260 (Md. 1967).

Opinion

Barnes, J.,

delivered the opinion of the Court.

The appellee, Woodlea Construction Co., Inc. (builder) filed a mechanic’s lien for $12,411.93 in the Circuit Court for Baltimore County on September 24, 1965, against the dwelling house of the appellants, Charles Lawrence Gamble and wife (owners). The trial court (Raine, J.) after taking testimony entered a decree on January 13, 1966 sustaining the lien in the amount of $3,008.10. The appeal is from this decree.

The owners and builder executed a written contract for the construction of the one-story ranch house on January 9, 1964. The contract price was $30,000. Certain work, specified as “extras” increased the contract price by $565.00. The house was to be completed in 180 days.

During the course of construction many differences arose between the builder and the owners regarding the performance of the building contract, which contained a provision for the arbitration of such differences. This provision was availed of twice, but the parties did not carry out the last arbitration agreement of March 31, 1965, and work came to a standstill. Finally by an “Agreement and Compromise,” dated May 25, 1965, it was agreed that the builder would immediately resume work, begin grading within five days and deliver the completed project, subject to the written approval of the arbitrators, with releases of mechanics’ liens, at the end of twenty-one days, that is, by June 15, 1965. It was also agreed that the completion date should be extended in the event of delays caused by weather ■conditions.

Andrew Bozylinski, the president and sole owner of the builder, Woodlea Construction Co., Inc., testified that wet weather prevented the completion of the exterior work and that it would have taken three or four additional days to finish the outside work. He testified that, except for the outside work, the interior construction of the house was completed except for the sanding and finishing of the floors. Exterior work which had to await the completion of the final grading, such as the *263 rear porch, exterior walls, driveways, etc., were not completed. Cross-examination disclosed that certain other relatively small interior items were not completed. Mr. Bozylinski testified, without contradiction, that when he arrived on the job on the morning of June 16, 1965, he was met by the owners who had slept overnight in the house. They ordered him off the job and refused permission to do further work. Being threatened with calling the police, he left the job. Thereafter the owners refused to malee any further payments under the building contract, moved into the house and completed the remaining work themselves. The owner had previously paid the builder $20,-140.00.

The carpenter subcontractor on the job testified in regard to the interference by the owners with the progress of the work. He stated:

“Well, we tried to avoid him [Mr. Gamble] as much as possible, because he was continually—he would follow us around the house. They stayed with us constantly. If he wasn’t [was] working and he wasn’t there, his wife was there and just overlooking everything we did.
“* * * [H]e would talk to my help quite a bit. Naturally, that slowed them down, couldn’t get the work done.”

He complained to the builder about this but the builder told him to do whatever the owners wished done within reason and if there was any extra expense, the builder would take care of it.

The plumbing and heating subcontractor testified, without contradiction, that Mr. Gamble requested him not to deliver a bathtub to the house, but to keep it at his home or shop for a while. When Mr. Gamble was asked the reason for this request, he stated that he wanted to tie up the job for a while and that he intended “to break” the builder and that “when he got done with him he wouldn’t even have his own home.”

In preparing the bill of particulars to the mechanic’s lien, counsel for the builder inadvertently included as part of the particulars, a driveway and tiled foyer which were not installed *264 by the builder. No dollar amounts, however, were assigned to these particular items. There was no mention in the bill of particulars of the grading, seeding, tree removal, pruning or porches which had not been completed.

After taking testimony, the trial court found that the work had been substantially completed, and after computing various allowances and deductions, found a balance due of $5,554.00. Unknown to the builder, two subcontractors had filed mechanic’s liens in a total amount of $2,545.90. This amount was deducted from the balance of $5,554.00 leaving a net amount of $3,008.10 for which the decree was entered.

The owners contended in the lower court and urged before us that (1) the trial court was clearly erroneous in finding that the building contract had been substantially performed, (2) the performance by the builder demonstrated that he did not attempt in good faith to perform the building contract, and (3) the entire amount of the mechanic’s lien should be disallowed, in any event, because it had been grossly and deliberately exaggerated.

(1) and (2)

It will be convenient to consider the owners’ contentions (1) and (2) together as they are in part related.

Our predecessors have set forth the applicable law in Hammaker v. Schleigh, 157 Md. 652, 668-69, 147 Atl. 790 (1929). Judge Parke, for the Court, stated:

“In a building contract where the plaintiff, in good faith, performs all that the contract requires, although not at the time or in the manner required, but substantially as agreed, except in respect to those things which he is prevented from performing through the breach or default of the owner, the plaintiff is entitled, when the owner has received the fruits of plaintiffs work, material and labor, to recover, since full performance has failed in those things which are not of the essence of the contract, and since otherwise there would be a forfeiture of the plaintiff’s beneficial work, labor and material to the unjust enrichment of the owner.”
*265 “ * * * The mode of ascertaining the real benefit derived by the owner from the substantial performance of the contract, where there has been no willful breach going to the essence of the contract, but comparatively slight omissions and defects in performance, which can be readily ascertained, measured, and compensated in damages, is ordinarily to estimate the whole work at the price fixed by the contract, and to deduct from the amount whatever sum would be required to complete the part of the work left unfinished through the default of the contractor.” (Emphasis supplied).

We followed Hammaker in Evergreen Amusement Corp. v. Milstead, 206 Md. 610, 621, 112 A. 2d 901 (1955) where Judge (now Chief Judge) Hammond, for the Court, stated:

“The question of whether there has been substantial compliance and whether a deviation from the contract requirements is wilful or justified is ordinarily a question for the trier of the facts.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CSR Contractors, Inc. v. Kendall Construction, Ltd.
726 P.2d 1018 (Court of Appeals of Washington, 1986)
In Re Northup-Johnson, Inc.
15 B.R. 767 (D. Maryland, 1981)
Singer v. Steven Kokes, Inc.
384 A.2d 463 (Court of Special Appeals of Maryland, 1978)
Della Ratta, Inc. v. American Better Community Developers, Inc.
380 A.2d 627 (Court of Special Appeals of Maryland, 1977)
Merritt Building & Supply Co. v. Shaulis
249 A.2d 177 (Court of Appeals of Maryland, 1969)
First National Realty Corporation v. Warren-Ehret Company, Inc.
233 A.2d 811 (Court of Appeals of Maryland, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
228 A.2d 243, 246 Md. 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gamble-v-woodlea-construction-co-md-1967.