Fulton Cogeneration Associates v. Niagara Mohawk Power Corp.

84 F.3d 91, 1996 U.S. App. LEXIS 11351, 1996 WL 266541
CourtCourt of Appeals for the Second Circuit
DecidedMay 15, 1996
Docket700, Docket 95-7540
StatusPublished
Cited by56 cases

This text of 84 F.3d 91 (Fulton Cogeneration Associates v. Niagara Mohawk Power Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fulton Cogeneration Associates v. Niagara Mohawk Power Corp., 84 F.3d 91, 1996 U.S. App. LEXIS 11351, 1996 WL 266541 (2d Cir. 1996).

Opinion

OAKES, Senior Circuit Judge:

Niagara Mohawk Power Corporation (“Niagara”) appeals from a summary judgment entered by the United States District Court for the Northern District of New York, Frederick J. Scullin, Jr., Judge, in favor of Fulton Cogeneration Associates (“Fulton”) on its claim against Niagara for breach of contract. The district court held that Niagara was obligated under the contract to purchase all electricity generated by an electric generating facility operated by Fulton in the Town of Fulton, New York, so long as such quantities were not unreasonably disproportionate to the stated estimates within the contract, and that, as a matter of law, Fulton never produced an amount of electricity that exceeded commercially reasonable expectations. Niagara argues on appeal that the district court should have dismissed or stayed the action until the New York Public Service Commission (“PSC”) ruled on the matter, that the district court erred in granting Fulton summary judgment because several genuine issues of material fact exist, and that the district court erred in not granting summary judgment to Niagara because Niagara acted properly under the Agreement and PSC rules. We find that this case presents material issues that must be determined by a trier of fact, and we therefore reverse and vacate in part the summary judgment in favor of Fulton and remand. In all other respects, we affirm the district court.

BACKGROUND

In 1978, Congress passed the Public Utility Regulatory Policies Act (“PURPA”), 16 U.S.C. § 824, et seq., in an effort to reduce United States dependence on foreign oil by encouraging the development of alternative energy sources. To further this goal, PURPA requires electric utilities to purchase all electricity produced by independent power producers operating so-called Qualifying Facilities (“QF”). See 16 U.S.C. § 824a-3(b); 18 C.F.R. § 292.304. State agencies such as the PSC are empowered to regulate the facilities and approve the contracts covered by PURPA. See 16 U.S.C. § 824a-3; N.Y.Pub. Serv.Law § 66-c(l) (McKinney Sup.1995).

In December 1987, Turner Power Group, Inc., Fulton’s predecessor-in-interest and an independent power producer operating a QF (the “Plant”), entered into a power purchasing agreement (the “Agreement”) with Niagara pursuant to the provisions of PURPA. The first ‘WHEREAS” clause of the Agreement describes the size of Fulton’s Plant:

SELLER will own and operate an electric generating plant ... with a capacity of approximately 47.0 megawatts, and with expected annual production of approximately 392,000 Megawatt-hours (individually and together referred to as “ELECTRICITY”)

Under the terms of the Agreement, Fulton agreed to deliver and Niagara agreed to accept all of the “electricity” produced by the Plant, net of any amounts used by Fulton itself. 1 The Agreement further provides that Niagara must pay for the electricity “on the basis of energy, or kwh, delivered” to Niagara at the rate established in Niagara’s tariff, *95 which- is 6<f/Kwh. The PSC approved the contract in April 1988.

The Plant is designed to deliver electricity to Niagara and steam to a Nestle Chocolate & Confections Company factory located nearby. The Plant’s gas turbine generator set burns natural gas or #2 distillate oil to produce electricity. Exhaust heat from the turbine is captured and used to generate steam, some of which can be injected back into the turbine to boost capacity levels, and therefore ultimate energy production, after Fulton has sent the required amount of steam to the Nestle factory.

The distinction between capacity and energy is crucial to an understanding of the dispute between these two parties. As explained in affidavits submitted by both parties, the term “capacity” refers to the amount of electric power that an electric generator can produce, and is measured in kilowatts (Kw) or megawatts (Mw). The term “energy” is the usage of capacity over a period of time and is measured in kño-watthours (Kwh) or megawatthours (Mwh). Thus, the two concepts are linked and dependent upon one another. As the contract states, the terms are referred to individually and collectively as “ELECTRICITY.”

Upon completion of the Plant in July 1991, Fulton began delivering electricity to Niagara. From July 1991 through April 1992, Niagara bought all delivered electricity from Fulton at the rate of 6<t/Kwh.

On March 13,1992, Niagara informed Fulton that the Plant was producing above a 47 megawatt capacity. 2 Because Niagara believed it was not required to pay for production above that level, it stated that it would use a formula called “Demonstrated Maximum Net Capability,” or “DMNC,” to measure the seasonal capacity of the Plant and prorate payments to Fulton. Under this formula, if the capacity climbed over the 47 megawatts provided in the contract, Niagara would calculate a seasonal capacity rate based upon the four peak hour capacity output in the summer and winter — in other words, the highest average consecutive four-hour output — and would pay the 6<t/Kwh rate only for that proportion of electricity attributable to a 47 megawatt capacity. Any excess would be paid at a market rate, which was lower than the 6<c/Kwh contract rate. The DMNC formula was mentioned nowhere within the Agreement between Niagara and Fulton, but Niagara chose it because it had been utilized by the PSC in connection with other PURPA contracts.

Niagara thus measured the seasonal capacity of the Plant in terms of the DMNC formula at 50 megawatts. Niagara thereafter paid for 47/50ths of the energy at the 6<t/Kwh rate and the rest at a market rate. Niagara used this DMNC formula from May 1992 through October 1992. After October 1992, it began paying the 6<c/Kwh rate again. The use of the formula resulted in Niagara paying Fulton $279,691.19 less in 1992 than it would have been obligated tó do at the contract rate. 3

Fulton commenced this breach of contract action based upon diversity of citizenship on October 30, 1992, seeking both equitable and monetary relief.- After denying Niagara’s motion to dismiss the complaint due to the doctrines of abstention and primary jurisdiction, the district court ordered that discovery proceed. After the close of discovery, both parties moved for summary judgment. In an order dated October 11, 1994, the district court denied both parties’ motions. 4 The *96 case was scheduled for a final pre-trial conference and a bench trial to commence on March 27,1995. On the morning of the first day of trial, the district court decided to reconsider the summary judgment motions sua sponte, based in large part upon a recently decided case of the Appellate Division, Third Department,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thani A.T. Al Thani v. Hanke
S.D. New York, 2025
O'Hara v. Cohen-Sanchez
E.D. New York, 2025
Palmer v. Amazon
51 F.4th 491 (Second Circuit, 2022)
Jiminez v. Credit One Bank, N.A.
377 F. Supp. 3d 324 (S.D. Illinois, 2019)
Reed v. 1-800-Flowers.com, Inc.
327 F. Supp. 3d 539 (E.D. New York, 2018)
In Re Bfw Liquidation, LLC
459 B.R. 757 (N.D. Alabama, 2011)
Schanfield v. Sojitz Corp. of America
663 F. Supp. 2d 305 (S.D. New York, 2009)
Town of Riverhead v. CSC Acquisition—NY, Inc.
618 F. Supp. 2d 256 (E.D. New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
84 F.3d 91, 1996 U.S. App. LEXIS 11351, 1996 WL 266541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fulton-cogeneration-associates-v-niagara-mohawk-power-corp-ca2-1996.