Indeck-Yerkes Energy Services, Inc. v. Public Service Commission

164 A.D.2d 618, 121 P.U.R.4th 431, 564 N.Y.S.2d 841, 1991 N.Y. App. Div. LEXIS 577
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 24, 1991
StatusPublished
Cited by10 cases

This text of 164 A.D.2d 618 (Indeck-Yerkes Energy Services, Inc. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indeck-Yerkes Energy Services, Inc. v. Public Service Commission, 164 A.D.2d 618, 121 P.U.R.4th 431, 564 N.Y.S.2d 841, 1991 N.Y. App. Div. LEXIS 577 (N.Y. Ct. App. 1991).

Opinion

OPINION OF THE COURT

Levine, J.

Petitioner owns and operates a cogeneration facility (hereinafter the facility) in the Town of Tonawanda, Erie County, that is qualified under the Federal Public Utility Regulatory Policies Act (16 USC § 824a-3) (hereinafter PURPA) and Public Service Law § 66-c for the mandatory purchase of its electric energy production by public utilities. PURPA provides that such purchases shall be paid for at rates that are, inter alia, "just and reasonable to the electric consumers of the electric utility” (16 USC § 824a-3 [b] [1]), but may not exceed the purchasing utility’s avoided cost, i.e., the cost the utility avoids paying by not producing the energy itself (see, 16 USC § 824a-3 [d]; Matter of Consolidated Edison Co. v Public Serv. Commn., 63 NY2d 424, 431, appeal dismissed 470 US 1075). Under Public Service Law § 66-c, respondent Public Service Commission (hereinafter the PSC) is directed to fix the terms and conditions of such purchases it finds are "just and economically reasonable to the [utility’s] ratepayers, non-discriminatory * * * and further the public policy” of encouraging the development of alternate energy production facilities, etc., with the added requirement of a minimum purchase price of 6 cents per kilowatt hour (Public Service Law § 66-c [1]). Thus, the PSC performs the regulatory role under the statutory framework of approving the terms and conditions of energy purchase agreements between public utilities and qualifying alternate energy production facilities, cogeneration facilities and small hydro-facilities (see, Matter of Long Lake Energy [620]*620Corp. v Public Serv. Commn., 148 AD2d 84, 88, lv denied 75 NY2d 701), and none of the parties to these appeals dispute this.

In February 1987, petitioner entered into a 30-year contract with respondent Niagara Mohawk Power Corporation (hereinafter NiMo) for the purchase of electric production from petitioner’s facility. The agreement recited that petitioner was to operate a plant with an "initial capacity of approximately 49 megawatts, and with expected annual production of approximately 400,000 megawatt-hours initially, (individually and together referred to as 'electricity’)”. The agreement obligated NiMo to purchase "all of the electricity” produced at petitioner’s facility.

The contract between NiMo and petitioner contained a "cone-like” pricing structure that included a floor and a ceiling, as has been particularly described in Matter of Long Is. Light. Co. v Public Serv. Commn. (137 AD2d 205, 209, lv denied 73 NY2d 703). The pricing structure in the agreement was "front-loaded” for the first 15 years of its term, i.e., the payments were likely to exceed estimated avoided costs. In that sense, during the first half of the life of the contract, NiMo’s ratepayers would be subsidizing the construction and operation of petitioner’s facility, since NiMo’s cost of buying energy from petitioner was passed on in its rates to customers, and that cost exceeded what NiMo’s expenses would have been in otherwise producing the same energy (see, Matter of Long Lake Energy Corp. v Public Serv. Commn., supra, at 90; Matter of Long Is. Light. Co. v Public Serv. Commn., supra, at 209).

The agreement was submitted to the PSC staff, which issued a report qualifiedly recommending approval. The PSC approved the agreement at its meeting of June 10, 1987. In April 1988, petitioner informed NiMo that "due to improvement in cycle efficiency and overall system availability”, the anticipated output of its facility would be 53.38 megawatts (hereinafter MW) rather than 49 MW and that it considered NiMo bound to purchase the increased amount pursuant to the pricing terms of the agreement. When NiMo disagreed, petitioner applied to the PSC for a declaratory ruling as to whether NiMo was required to accept the additional output priced according to the pricing structure of the agreement.

The PSC issued its declaratory ruling effective September 14, 1988 in which it determined that (1) representations of the [621]*621size of the facility were "a significant factor in evaluating the reasonableness” of the contract submitted to it for approval, (2) the increase of 4.38 MW, some 9% of the original total estimated output, was a material deviation from the estimate in the approved agreement, (3) the use of the word "approximately” in conjunction with the capacity of 49 MW only referred to "an inescapable imprecision with respect to the expected output of a planned facility”, and not to an increase which is attributable, as here, to changes in the facility’s operations "to improve cycle efficiency and availability”, and (4) petitioner failed to expressly reserve the increased capacity in the agreement. Therefore, the PSC ruled that its approval of the terms of the agreement did not cover the increased capacity, and the sale of the additional output to NiMo required renegotiation and pricing in conformity with the PSC’s more recently adopted "Interim Policy”, which was less favorable to facility developers (see, Matter of Long Lake Energy Corp. v Public Serv. Commn., supra). Petitioner’s application for a rehearing was denied, with the PSC reiterating that the specified capacity of approximately 49 MW was a "material consideration” in the PSC’s approval of the agreement and of its "unusual pricing provisions”.

Petitioner then brought the instant CPLR article 78 proceeding for judicial review of the PSC’s declaratory ruling. Supreme Court annulled. The court interpreted the contract as essentially requiring NiMo to accept and pay for the entire output of petitioner’s facility. It also found, based notably upon other terms of the agreement and portions of the PSC’s staff report, that NiMo and the PSC were aware of the possibility that petitioner’s facility would be expanded well beyond the estimated initial capacity of 49 MW. Therefore, the court held that the PSC acted arbitrarily in refusing to include the increase within NiMo’s obligations under the agreement. The PSC and NiMo appeal from Supreme Court’s annulment of the declaratory ruling.

We reverse. The issue in this proceeding is not one of pure interpretation of the language of the agreement between petitioner and NiMo by application of common-law principles of contract. Rather, it is whether there was a rational basis to the PSC’s determination of the scope of its prior approval of the parties’ agreement, particularly the price structure contained therein, as not covering other than insignificant deviations from the contract’s stated initial output of approximately 49 MW (see, Matter of New York State Cable Tel. Assn. [622]*622v New York State Pub. Serv. Commn., 125 AD2d 3, 6). Moreover, we disagree with Supreme Court as to the significance of any understanding by NiMo and the PSC that petitioner’s facility might expand its output substantially beyond the initial capacity set forth in the agreement. As the PSC recognized in its declaratory ruling, petitioner, the operator of a qualified facility under PURPA and Public Service Law § 66-c, could expect that NiMo would be required to purchase the output of any expanded capacity at the facility. However, this is not determinative of whether the purchase of any additional output should be governed by the pricing structure set forth in the agreement.

In our view, the reasonableness of the PSC’s determination is amply demonstrated by the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Navillus Tile, Inc. v. Port Auth. of N.Y. & N.J.
2026 NY Slip Op 31013(U) (New York Supreme Court, New York County, 2026)
Luyster Creek, LLC v. New York State Public Service Commission
82 A.D.3d 1401 (Appellate Division of the Supreme Court of New York, 2011)
Wheelabrator Lisbon, Inc. v. Department of Public Utility Control
931 A.2d 159 (Supreme Court of Connecticut, 2007)
Florida Power Corp. v. Garcia
780 So. 2d 34 (Supreme Court of Florida, 2001)
United Water New York, Inc. v. Public Service Commission
252 A.D.2d 810 (Appellate Division of the Supreme Court of New York, 1998)
Philadelphia Corp. v. Niagara Mohawk Power Corp.
207 A.D.2d 176 (Appellate Division of the Supreme Court of New York, 1995)
Kessel v. Public Service Commission
193 A.D.2d 339 (Appellate Division of the Supreme Court of New York, 1993)
Xiox Corp. v. Public Service Commission
190 A.D.2d 350 (Appellate Division of the Supreme Court of New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
164 A.D.2d 618, 121 P.U.R.4th 431, 564 N.Y.S.2d 841, 1991 N.Y. App. Div. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indeck-yerkes-energy-services-inc-v-public-service-commission-nyappdiv-1991.