Long Island Lighting Co. v. Public Sevice Commission

137 A.D.2d 205, 529 N.Y.S.2d 209, 1988 N.Y. App. Div. LEXIS 5341
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 19, 1988
StatusPublished
Cited by5 cases

This text of 137 A.D.2d 205 (Long Island Lighting Co. v. Public Sevice Commission) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Island Lighting Co. v. Public Sevice Commission, 137 A.D.2d 205, 529 N.Y.S.2d 209, 1988 N.Y. App. Div. LEXIS 5341 (N.Y. Ct. App. 1988).

Opinion

OPINION OF THE COURT

Kane, J. P.

In early 1985, respondent American REF-FUEL Company of Hempstead (hereinafter REF-FUEL) began negotiations with petitioner, Long Island Lighting Company (hereinafter LILCO), regarding LILCO’s purchase of electricity from REF-FUEL, as required by statute (see, Public Service Law § 66-c). REF-FUEL was planning to build and operate a solid waste-to-energy facility in the Town of Hempstead, Nassau County, in order to dispose of the town’s solid waste. REF-FUEL anticipated that the facility would produce between 63.5 megawatts and 79.9 megawatts of electricity and would be classified as a "qualifying facility” under the Federal Public Utility Regulatory Policies Act of 1978 (hereinafter PURPA) (see, 16 USC § 796).1

[208]*208In an effort to streamline negotiations between small alternative energy producers such as REF-FUEL and electric utilities such as LILCO, respondent Public Service Commission (hereinafter the PSC) issued Opinion and Order No. 86-8 (hereinafter Opinion 86-8) on March 27, 1986. PURPA requires a utility purchasing electricity from a qualifying facility to pay the "actual avoided cost”, that is, the cost the utility avoids paying by not generating or producing such power itself (see, 16 USC § 824a-3 [d]). In New York, Public Service Law § 66-c (1) grants the PSC the authority to set a minimum price the utility must pay but specifically prohibits the price from being lower than 6 cents per kilowatt hour (hereinafter KWH). As a result, a negotiated contract price may run greater than the actual avoided cost. However, such mandatory pricing has been upheld because such contracts afford the independent energy producers security, thus giving them an incentive to pursue alternate methods of producing electricity (see, Matter of Consolidated Edison Co. v Public Serv. Commn., 63 NY2d 424, appeal dismissed 470 US 1075; see also, American Paper Inst. v American Elec. Power, 461 US 402).

Opinion 86-8 included a "long run avoided cost” (hereinafter LRAC) projection whereby the price actually paid by the utility would be projected at the contract’s inception and last the length of the contract. It also delineated two specific contract options for nonhydroelectric facilities such as REF-FUEL. REF-FUEL’s proposed contract to LILCO basically used the second option which calculated the price based on LILCO’s actual avoided cost tariff rate with a negotiated floor and ceiling tied to LRAC estimates below and above which the price paid by LILCO could not go. However, no agreement was made and the parties turned to the PSC for nonbinding mediation. The areas of dispute concerned, inter alia, the length of the contract and its provisions for price updates. REF-FUEL sought a 20-year contract with no price updates, arguing that these provisions were necessary to guarantee it minimum payments for the life of its bonds and its contract [209]*209with the Town of Hempstead. LILCO, on the other hand, sought a 15-year contract with price updates in the sixth and eleventh years of the contract. LILCO’s proposal conformed with Opinion 86-8’s provisions.

The second option of Opinion 86-8 that REF-FUEL was relying on came to be known as the "cone pricing proposal” since both the ceiling and floor, as percentage functions of the steadily rising LRAC, diverged from the LRAC to form a "cone”. The floor guaranteed a minimum price to REF-FUEL while the ceiling provided a maximum price that would protect LILCO should the cost of producing electricity significantly increase. Although the PSC mediation staff recommended approval of REF-FUEL’s proposal, LILCO refused to accept it and REF-FUEL petitioned the PSC to compel LIL-CO’s acceptance. Upon the advice of its Power Division, the PSC initially recommended further negotiations. As a result, a new proposal known as an "asymmetrical pricing cone” was developed wherein the floor, while never going below the statutory 6 cents/KWH minimum, would descend over time lower than the ceiling would rise above the linear LRAC. Although the ceiling would ascend at a steady rate of 20% of the LRAC, the floor would remain at the 6 cent minimum for the first five years, then decline to 20% of the LRAC for years 6 through 10, fall 25% for years 11 to 15 and 40% in years 16 through 20. The proposal also included a potential 10% reduction in the price paid to REF-FUEL in the years 2001 through 2008. Based on the Power Division’s recommendations, the PSC approved the new proposed contract and ordered LILCO to sign it. Upon the denial of its motion for a rehearing, LILCO signed the contract under protest and commenced the instant CPLR article 78 proceeding. Supreme Court dismissed LILCO’s petition and LILCO has appealed.

Initially, LILCO claims that the floor of the pricing cone exceeds the statutory 6 cent/KWH minimum and that in these times of low oil prices, this provides an unfair windfall to REF-FUEL while unfairly burdening LILCO’s ratepayers.2 However, as the Court of Appeals specifically pointed out in Matter of Consolidated Edison Co. v Public Serv. Commn. (63 [210]*210NY2d 424, 438, supra), "failure to achieve consumer ratesavings is not necessarily abhorrent to the primary purpose of PURPA, which is to encourage development of cogeneration and small power facilities” (emphasis supplied). LILCO’s argument is based in part on the claim that the pricing cone violates Federal law because it departs from actual avoided costs when such costs may fall beneath the floor. Again, however, in Consolidated Edison the court noted that although the 6 cent minimum might not provide ratesavings because it could at times exceed actual avoided costs, the rate still furthered PURPA’s objective of encouraging alternate energy production and was therefore valid (supra, at 438). Similarly, in this case, although the pricing cone could result in costs higher than actual avoided costs, it did not violate Federal law.

LILCO also claims that the pricing cone violates State law since it sets a compulsory price above the statutory minimum of 6 cents/KWH. However, the clear language of Public Service Law § 66-c (1) (a) belies this argument: "the [PSC] shall require any electric corporation * * * to enter into long-term contracts to purchase * * * electricity * * * from any * * * co-generation facility under such terms and conditions as the [PSC] shall find just and economically reasonable * * * provided, however, the [PSC] shall establish a minimum sales price for such purchased electricity * * * of at least six cents per kilowatt hour for each utility” (emphasis supplied). Thus, the 6 cent/KWH price is only a minimum that the PSC must impose and in requiring a higher price, it is limited only by the phrase "just and economically reasonable”, a criterion we find to have been satisfied in the instant case. As the PSC noted, "the proposed floor price is low enough to encompass most conservative projections of avoided costs”. Therefore, we find no violation of either Federal or State law by the PSC in ordering LILCO to sign the contract.

LILCO next asserts that the PSC violated its own guidelines as set forth in Opinion 86-8 and therefore its determination accepting the contract was arbitrary and capricious. LILCO argues that Opinion 86-8 mandated a maximum contract duration of 15 years with cost evaluations in the sixth and eleventh years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Xiox Corp. v. Public Service Commission
190 A.D.2d 350 (Appellate Division of the Supreme Court of New York, 1993)
Indeck-Yerkes Energy Services, Inc. v. Public Service Commission
164 A.D.2d 618 (Appellate Division of the Supreme Court of New York, 1991)
Naftilos Painting & Sandblasting, Inc. v. Hartnett
167 A.D.2d 700 (Appellate Division of the Supreme Court of New York, 1990)
Long Lake Energy Corp. v. Public Service Commission
148 A.D.2d 84 (Appellate Division of the Supreme Court of New York, 1989)
Niagara Mohawk Power Corp. v. Public Service Commission
138 A.D.2d 63 (Appellate Division of the Supreme Court of New York, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
137 A.D.2d 205, 529 N.Y.S.2d 209, 1988 N.Y. App. Div. LEXIS 5341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-island-lighting-co-v-public-sevice-commission-nyappdiv-1988.