Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated

District Court, E.D. Louisiana·Decided May 14, 2021·No. 2:18-cv-02885·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

FUCICH CONTRACTING, INC., et al. CIVIL ACTION

VERSUS NO. 18-2885

SHREAD-KUYRKENDALL & SECTION M (4) ASSOCIATES, INC., et al.

ORDER & REASONS Before the Court is the motion of defendant St. Bernard Parish Government (“SBPG”) to enforce the February 25, 2019 settlement agreement.1 Plaintiff Fucich Contracting, Inc. (“FCI”) opposes the motion.2 Shread-Kuyrkendall and Associates, Inc. (“SKA”) and XL Specialty Insurance Company reply in support of SBPG’s motion.3 Having considered the parties’ memoranda, the record, and the applicable law, the Court issues this Order & Reasons granting the motion and enforcing the February 25, 2019 interim settlement agreement. I. BACKGROUND This case arises out of a construction dispute over a component-compatibility problem, specifically, a rotational conflict, between the engines and gear reducers intended for use in back- up storm water drainage pumps critical to a public works improvement project known as the Lake Borgne Basin Levee District Pump Station #1 & #4 Pump Upgrade (the “Project”).4 SBPG hired FCI as the Project contractor and SKA as the Project engineer. Pursuant to the Louisiana Public Works Act, Travelers Casualty and Surety Company of America (“Travelers”) issued a

1 R. Doc. 524. 2 R. Doc. 538. 3 R. Doc. 544. 4 R. Doc. 373 at 1-4. performance and payment surety bond naming FCI as principal and SBPG as obligee.5 When the rotational conflict became apparent, SBPG informed Travelers that it intended to terminate FCI.6 FCI filed this lawsuit against SBPG and SKA, and SBPG did, in fact, terminate FCI several months later.7 SBPG filed a counterclaim and third-party demand seeking to hold FCI and SKA responsible for the rotational conflict and resulting failure to complete the Project.

In the midst of this dispute, the Project was, and still is, unfinished – meaning that the citizens of St. Bernard Parish to this day do not enjoy the protection against flooding the Project intended to afford, though another hurricane season is looming. The Project requires a total of four engines. Three engines were delivered to SBPG but the fourth remained in the possession of the engine vendor.8 On or around December 27, 2018, FCI picked up the fourth engine.9 On February 25, 2019, SBPG and FCI entered into an interim settlement agreement on the record before the magistrate judge.10 SBPG agreed “to pay [FCI] $194,219.90, which represents the balance of the engines per the scheduled values less the retainage.”11 In exchange, FCI agreed “to irrevocably release any ownership claim as to the four engines, which includes the three that

are currently on Pump Stations One and Four and also the one in his possession, which it will allow [SBPG] to pick up at [SBPG’s] expense, as well as any and all material or equipment currently on site at either Pump Station One or Four and any materials or supplies in the possession of Philadelphia Gear. All of these things, FCI agrees to release any ownership interest and claim.”12

5 R. Doc. 431 at 2. 6 Id. 7 Id. 8 R. Doc. 524-1 at 4. 9 Id.. Clayton Fucich states that “FCI picked up one engine assembly, one muffler, and one loose box of appurtenances from Puckett Power on two separate trips to Puckett Power’s facility on or about December 21, 2019 and on or about January 17, 2019.” R. Doc. 538-4 at 1. 10 R. Doc. 524-3. 11 Id. at 2. 12 Id. at 3. SBPG paid the full amount of the settlement sum to FCI.13 On March 12, 2019, SBPG picked up the engine from FCI’s premises.14 SBPG asserts that during the bid process for the second phase of the Project, on or around December 11, 2020, “it was discovered that numerous pieces of the engine were missing and that the engines would not be able to be made operational without significant expenses.”15 Steven E.

Breeding, an engineer for SKA, took a physical inventory of the engine equipment in preparation for the bid.16 He states that he “discovered that many items furnished by the Caterpillar engine vendor and included as equipment and attachments to the Caterpillar engines were missing and are not in the possession of the Parish or SKA.”17 While there are disputes as to who might have certain of the missing items, Clayton Fucich, with no apparent qualms, declares: “I do have in my possession a box of engine appurtenances accompanying the engine SBPG picked up from my facility.”18 II. PENDING MOTION In this motion, SBPG argues that FCI breached the interim settlement agreement by retaining possession of “several important pieces to the engine.”19 It contends that these items are

component parts of the engine and were not separately purchased.20 SBPG argues that FCI’s “clear breach” was “intentional” considering FCI’s “long history of attempting to sabotage the completion of this Project.”21

13 R. Doc. 524-1 at 5. 14 R. Docs. 524-1 at 5; 538-4 at 2. 15 R. Doc. 524-1 at 5-6. 16 R. Doc. 524-12 at 1-2. 17 Id. at 2. 18 R. Doc. 538-4 at 2. The packing slip listing the items in the box is attached as R. Doc. 538-1. 19 R. Doc. 524-1 at 5. 20 Id. at 6. 21 Id. In opposition, FCI argues that the settlement agreement did not include “appurtenances held in FCI’s possession, which appurtenances are distinct from the engines as frequently referenced in the contract documents.”22 FCI says it must receive additional compensation before it will deliver appurtenances that were not included in the interim settlement agreement.23 FCI argues that to hold otherwise would impermissibly extend the bounds of the compromise

agreement.24 Finally, FCI argues that it cannot be held liable for items on SBPG’s property which are outside of its control and questions the accuracy of Breeding’s attempt to identify missing items in photographs taken at FCI’s premises.25 In its reply, SKA argues that the use of the term “schedule of values” in the settlement agreement had a technical meaning which included payment for the engines and their appurtenances.26 SKA suggests that an available interim solution would be for the Court to order FCI to turn over the parts but retain its right to seek reimbursement at trial.27 Based on the sales tax exemption certificate signed by FCI and SBPG at the beginning of this Project, SKA also argues that ownership of items purchased by the contractor – which would have included the engines and their appurtenances – was transferred to the parish.28

III. LAW & ANALYSIS A. Louisiana Law on Compromise “‘Although federal courts possess the inherent power to enforce agreements entered into in settlement of litigation, the construction and enforcement of settlement agreements is governed by the principles of state law applicable to contracts generally.’” Sundown Energy, L.P. v. Haller,

22 R. Doc. 538 at 1 (emphasis in original). 23 Id. at 3. 24 Id. at 4. 25 Id. at 4-5. 26 R. Doc. 544 at 1-3. 27 Id. at 4-5. 28 Id. at 5. The contract is attached as R. Doc. 544-3. 773 F.3d 606, 611 (5th Cir. 2014) (quoting E. Energy v. Unico Oil & Gas, Inc., 861 F.2d 1379, 1380 (5th Cir 1988)). Under Louisiana law, a settlement agreement is called a compromise. La. Civ. Code art. 3071. A compromise is defined as “a contract whereby the parties, through concessions made by one or more of them, settle a dispute or an uncertainty concerning an obligation or other legal relationship.” Id. Compromises are contracts so the “‘rules of

construction applicable to contracts are therefore used.’” Celtic Marine Corp. v. James C.

Free access — add to your briefcase to read the full text and ask questions with AI

Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated, (E.D. La. 2021).

Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated (Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ortego v. STATE, DOTD
689 So. 2d 1358 (Supreme Court of Louisiana, 1997)
Trahan v. COCO COLA BOTTLING CO. UNITED
894 So. 2d 1096 (Supreme Court of Louisiana, 2005)
Sundown Energy, L.P. v. Steven Haller
773 F.3d 606 (Fifth Circuit, 2014)
Dwayne Chauvin v. Exxon Mobil Corporation
158 So. 3d 761 (Supreme Court of Louisiana, 2014)