Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated

District Court, E.D. Louisiana·Decided May 12, 2021·No. 2:18-cv-02885·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

FUCICH CONTRACTING, INC., et al. CIVIL ACTION

VERSUS NO. 18-2885

SHREAD-KUYRKENDALL & SECTION M (4) ASSOCIATES, INC., et al.

ORDER & REASONS Before the Court are the objections of plaintiff Fucich Contracting, Inc. (“FCI”) to the magistrate judge’s ruling on a motion to compel.1 Defendants St. Bernard Parish Government (“SBPG”)2 and Shread-Kuyrkendall and Associates, Inc. and XL Specialty Insurance Company (together, “SKA”)3 oppose the motion. Having considered the parties’ memoranda, the record, and the applicable law, the Court issues this Order & Reasons sustaining the objections in one respect but otherwise overruling them. I. BACKGROUND This case arises out of a construction dispute over a component-compatibility problem, specifically, a rotational conflict, between the engines and gear reducers intended for use in back- up storm water drainage pumps critical to a public works improvement project known as the Lake Borgne Basin Levee District Pump Station #1 & #4 Pump Upgrade (the “Project”).4 SBPG hired FCI as the Project contractor and SKA as the Project engineer. Pursuant to the Louisiana Public Works Act, Travelers Casualty and Surety Company of America (“Travelers”) issued a

1 R. Doc. 498. 2 R. Doc. 518. 3 R. Doc. 520. 4 R. Doc. 373 at 1-4. performance and payment surety bond naming FCI as principal and SBPG as obligee.5 In connection with this bond, FCI, Clayton Fucich, and Kathleen Fucich (together, the “Fucich Parties”) executed a general agreement of indemnity (“GAI”) in favor of Travelers, agreeing to indemnify Travelers from loss and to deposit collateral if needed to compensate for any loss or anticipated loss.6

When the rotational conflict became apparent, SBPG informed Travelers that it intended to terminate FCI.7 FCI filed this lawsuit against SBPG and SKA, and SBPG did, in fact, terminate FCI several months later.8 SBPG filed a counterclaim and third-party demand seeking to hold FCI and SKA responsible for the rotational conflict and resulting failure to complete the Project. Travelers completed an independent investigation in which it concluded that the rotational conflict was caused by SKA.9 As a result, Travelers found that FCI did not have a duty to finish the Project.10 Since FCI, as Travelers’s principal, did not (in its opinion) have a duty to finish the Project, Travelers, as surety, refused to complete the Project.11 SBPG then added Travelers to the lawsuit.12 Given the claims against FCI, Travelers sought to have the Fucich Parties provide it

with collateral security. Pursuant to the collateral and indemnity provision in the GAI, this Court ordered the Fucich Parties to provide Travelers with $2,563,930.00 as collateral security.13 Thereafter, FCI filed a claim against Travelers for bad-faith breach of the GAI.14

5 R. Doc. 431 at 2. 6 Id. 7 Id. 8 Id. 9 Id. 10 Id. 11 Id. 12 Id. 13 R. Docs. 184; 224. 14 R. Doc. 431 at 2. SKA contends that during the September 2, 2020 corporate deposition of FCI, Clayton Fucich, as the designated representative of FCI, raised an advice-of-counsel defense to claims that FCI failed to mitigate its own damages and exacerbated SBPG’s damages.15 As a result, SKA filed a motion to compel FCI to respond to discovery related to the defense.16 SKA argues that FCI (through Fucich) asserted the advice-of-counsel defense in two ways.17

First, FCI stated it refused to attend an October 15, 2018 “technical meeting” based on the advice of its lawyer at the time, Lee Kohler.18 The purpose of the meeting was to discuss what had to be done to finish the Project from a technical standpoint. In an email to all counsel in the case, Kohler explained: “FCI considers this proposed meeting simply another attempt to have FCI perform uncompensated design work for the Parish and SKA, who can then use that work to award a completion contract to another contractor.”19 When questioned about this email at the corporate deposition, Fucich stated that he refused to attend the meeting based on “the advice of counsel on this,”20 positing: “You’re going to have to ask Lee [Kohler] what all of that stuff meant. He wrote the letter.”21 When asked, “Do you recall telling everyone, through Mr. Kohler, that you were not going to attend that meeting?,” Fucich again responded: “I was going with the advice of counsel.”22

Second, SKA argues that FCI asserted advice of counsel with respect to a pair of letters concerning settlement negotiations. In the corporate deposition of FCI, SKA referenced a letter Travelers sent to the Fucich Parties demanding collateral security.23 SKA quoted Travelers’s

15 R. Doc. 482-2 at 1-4. 16 R. Doc. 482. 17 R. Doc. 482-2 at 2-5. 18 R. Doc. 485-1 at 3-5. 19 R. Doc. 482-3 at 1. 20 R. Doc. 482-4 at 2. 21 Id. at 3. 22 Id. 23 R. Doc. 482-5. The date of the letter, either October 9, 2018, or November 12, 2018, appears to be in dispute. R. Doc. 485 at 9 n.22. assessment of “Fucich’s uncompromising refusal to participate in the formal Settlement Conference with the other parties and the Magistrate,” thereby jeopardizing FCI’s ability to mitigate its risk and that of Travelers.24 When asked if that statement was accurate, Clayton Fucich responded: “I don’t – I don’t know that that’s accurate. You know, again, I was just taking [Kohler’s] advice on this. I don’t – I don’t know what the – what the intent was.”25 SKA references

another letter, this one dated October 10, 2018, that Kohler sent to opposing counsel setting out the Fucich Parties’ settlement proposal in which they requested that “[t]he Parties … engage an independent engineer to act as an arbiter of future disputes arising out of the work.”26 When asked why he made this request, Fucich said “[m]y attorney advised that it would be a good idea.”27 On December 3, 2020, the magistrate judge granted in part SKA’s motion to compel,28 finding that in several instances during deposition, FCI’s corporate representative provided evasive or incomplete answers and “shift[ed] accountability onto his former counsel [to] hide behind the shield of advice of counsel.”29 The magistrate judge determined that FCI waived its attorney-client privilege in certain limited respects.30 The magistrate judge ordered FCI to submit to another

deposition and produce documents related to “those communications between Fucich and his former counsel, Lee Kohler, regarding his failure to attend technical meetings, failure to participate in settlement efforts, and refusal to turn over the engines for which Fucich relies on advice of

24 R. Doc. 482-4 at 4. 25 Id. 26 R. Doc. 482-7 at 3. 27 R. Doc. 482-6 at 7. 28 The magistrate judge denied SKA’s motion to compel to the extent it sought discovery regarding FCI’s fee dispute with its former counsel. 29 R. Doc. 490 at 4. 30 Id. at 7-8 & n.1 (construing Fucich’s invitation to question FCI’s former counsel “as a waiver of privilege on its own”). counsel as justification regarding his duty to mitigate damages.”31 On December 16, 2020, FCI filed timely objections to the magistrate judge’s ruling.32 II. PENDING MOTION In its objections, FCI argues that the order is overly broad and should be modified.33 Specifically, FCI maintains that (1) “[n]o evidence presented by SKA related to the Motion to

Free access — add to your briefcase to read the full text and ask questions with AI

Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated, (E.D. La. 2021).

Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated (Fucich Contracting, Inc. v. Shread-Kuyrkendall and Associates, Incorporated) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
Succession of Smith v. Kavanaugh, Pierson & Talley
513 So. 2d 1138 (Supreme Court of Louisiana, 1987)
Ressie Moore v. Ford Motor Company
755 F.3d 802 (Fifth Circuit, 2014)
McNeely v. Board of River Port Pilot Commissioners
534 So. 2d 1255 (Supreme Court of Louisiana, 1988)
Panter v. Marshall Field & Co.
80 F.R.D. 718 (N.D. Illinois, 1978)