Freeman v. Department of Highways

217 So. 2d 166, 253 La. 105, 1968 La. LEXIS 2485
CourtSupreme Court of Louisiana
DecidedNovember 12, 1968
Docket48729
StatusPublished
Cited by17 cases

This text of 217 So. 2d 166 (Freeman v. Department of Highways) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeman v. Department of Highways, 217 So. 2d 166, 253 La. 105, 1968 La. LEXIS 2485 (La. 1968).

Opinions

SUMMERS, Justice.

Certiorari was granted to review a judgment of the First Circuit rejecting, in part, the claim for damages for breach of contract asserted by the plaintiff E. M. Freeman against the Department of Highways. See 197 So.2d 188 and 250 La. 928, 199 So.2d 925.

Plaintiff’s 'suit arose out of two contracts entered into with the Department of Highways, wherein he agreed to perform engineering service on two segments of the national system of interstate highways in Louisiana.

The first contract, Number 13, dated June 25, 1957, represented that the Department had completed a topographic sui’vey; and, by the terms of the contract, the Department engaged plaintiff to perform engineering services in connection with the preparation of preliminary and contract plans, specifications and estimates of costs, including supplemental topographic surveys, for the Greenwood-Shreveport section of the interstate system. The service to be performed by the engineers was to be divided into two successive phases covering: (I) All investigations, studies and surveys necessary or required for, and the preparation of, preliminary plans; and (II) the making of right of way survey and map, the preparation of construction contract plans and specifications, and the checking of contractors’ shop drawings.

[109]*109The Department agreed to furnish to the engineers for use in the preparation of the required plans and designs certain services and data, consisting of: (1) Information showing locations of route, and location and schematics of interchanges, bridges and grade separations, (2) topographic survey, (3) traffic assignments for determining design of the project, (4) information in the Department’s files as to boring data, surveys, plan and studies within the area and assistance in securing similar data from others, and (5) prints of standard plans of bridges, culverts and incidental drainage structures.

Phase I of Contract Number 13, including completion of the subsurface investigation and delivery of the preliminary plans and estimates, was required by the contract to be completed within six months after receipt of notice to proceed. Phase II was to be completed within four months.

The other contract, Number 37 dated May 19, 1958, covers the Texas State Line-Greenwood Section of the interstate system. It differs from Contract No. 13 in effective dates and the segments of the highway affected. The contracts are otherwise essentially the same.

One provision of the contracts which is of special concern to us relates to delays and extensions, for it is this provision which the Department relies upon to defeat the claims of plaintiff in this suit. It is an exculpatory clause which reads as follows:

“Delays and Extensions:
“The Engineers will be given credit and extension of time for delays beyond their control or for those caused by tardy approvals of work in progress by various official agencies, but no additional compensation shall be allowed for such delays.”

While conceding that delays occurred which were not attributable to the plaintiff engineers, the Department maintains that the quoted clause relieved it of responsibility for the delays notwithstanding the fact that the Department may have caused them. The plaintiff, on the other hand, contends that the clause does not exculpate the Department, for it applies only to delays attributable to “various official agencies”, meaning agencies other than the Department; and since the Department is not relieved of responsibility for delays which it caused, it must compensate plaintiff for the damage which plaintiff incurred by reason of the delays.

The trial court gave judgment for the contractor, being of the opinion that the Department had unduly and unnecessarily delayed plaintiff’s compliance with the contracts. The Department’s contention that the quoted exculpatory “Delays and Extensions” clause of the contracts relieved it of liability for damages for delays was disallowed. The trial judge reasoned that the clause did not refer to delays of the Department, but, instead, referred to delays by [111]*111agencies other than the Department itself. In its decision, the court cited and relied upon Sandel & Lastrapes v. City of Shreveport, 129 So.2d 620 (La.App.1961) decided by the Second Circuit Court of Appeal.

In the Sandel & Lastrapes Case, the City of Shreveport was sued by the contractor under a construction contract for damages caused by the City’s failure to timely furnish concrete pipe to be used in the construction project as provided for in the contract. The City resisted liability for damages caused by delays for which it was admittedly responsible, urging in support of its position an exculpatory clause of the contract, which it contended relieved it from liability for “any delays”. The Second Circuit held that “It is contrary to public policy to allow a contractee to stipulate exemption from negligent acts which cause injury.” Accordingly, the City was held to respond for the damage incurred by the contractor due to the City’s delay in providing the concrete pipe

In the instant matter, the First Circuit Court of Appeal stated that it did not agree with the Sandel & Lastrapes Case, but in the final analysis it distinguished the Sandel Case from the case at bar. The apparent conflict created by the statement of the First Circuit prompted us, at the urging of the plaintiff, to grant certiorari.

Now that the record is before us and we have had an opportunity to study the contracts in detail and have considered them in the light of the facts disclosed by the voluminous record, we are aware that this case involves the application of facts to a contractual provision distinguishable from the facts and the contract in the Sandel and Lastrapes Case. We find it unnecessary, therefore, to reconcile the alleged conflict between these cases and address ourselves, instead, to the merits of the case at hand.

The Delays and Extensions Clause

The first issue presented is whether the Department is contractually responsible for actions or nonactions which may have hindered plaintiff in his work and caused damages. This involves an interpretation of the “Delays and Extensions” clause ; for if the Department is not contractually responsible for delays caused by it, we need not inquire into whether the delays were or were not caused by the Department.

We find, however, that the "Delays and Extensions” clause does not exonerate the Department. The clause refers to official, agencies other than the Department — third parties whose approval or actions might be involved in the contract. For example, because this project was in large measure-financed by Federal funds, the Bureau of Public Roads may, conceivably, have delayed approval of plans and designs submitted, by plaintiff. A delay by the Bureau would have been caused by one of the “official. [113]*113agencies” referred to in the contract and would have been beyond the control of the Department. Plaintiff would, under the language of the clause, be entitled to credit and extensions of time, but no additional compensation would be due by the Department for actions of third parties. Thus the clause seeks to exculpate the engineers and the Department for delays “beyond their control” or for delays “caused by tardy approvals of work in progress by various official agencies”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
Massey v. Decca Drilling Co., Inc.
647 So. 2d 1196 (Louisiana Court of Appeal, 1994)
Utley-James v. State, Div. of Admin.
593 So. 2d 1261 (Louisiana Court of Appeal, 1991)
Pal Construction Corp. v. Leonard B. Hebert, Jr. & Co.
544 So. 2d 17 (Louisiana Court of Appeal, 1989)
In Re Incident Aboard
758 F.2d 1063 (Fifth Circuit, 1985)
Lindsey v. H. A. Lott, Inc., Contractors & Engineers
371 So. 2d 301 (Louisiana Court of Appeal, 1979)
FMC Corp. v. Continental Grain Co.
355 So. 2d 953 (Louisiana Court of Appeal, 1977)
Lucas v. Ins. Co. of North America
342 So. 2d 591 (Supreme Court of Louisiana, 1977)
Alan Abis, Inc. v. Burns Electronic Security Serv., Inc.
283 So. 2d 822 (Louisiana Court of Appeal, 1973)
Brenham v. Southern Pacific Company
328 F. Supp. 119 (W.D. Louisiana, 1971)
Plantation Pipe Line Co. v. Kaiser Alum. & Chem. Corp.
222 So. 2d 905 (Louisiana Court of Appeal, 1969)
Freeman v. Department of Highways
217 So. 2d 166 (Supreme Court of Louisiana, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
217 So. 2d 166, 253 La. 105, 1968 La. LEXIS 2485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeman-v-department-of-highways-la-1968.