PACE CONSTRUCTION SERVICES L L C v. FEDERAL INSURANCE CO

CourtDistrict Court, W.D. Louisiana
DecidedJanuary 13, 2026
Docket2:23-cv-00197
StatusUnknown

This text of PACE CONSTRUCTION SERVICES L L C v. FEDERAL INSURANCE CO (PACE CONSTRUCTION SERVICES L L C v. FEDERAL INSURANCE CO) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PACE CONSTRUCTION SERVICES L L C v. FEDERAL INSURANCE CO, (W.D. La. 2026).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION

PACE CONSTRUCTION SERVICES L L C CASE NO. 2:23-CV-00197

VERSUS JUDGE JAMES D. CAIN, JR.

FEDERAL INSURANCE CO MAGISTRATE JUDGE LEBLANC

MEMORANDUM RULING Before the court is a Motion to Dismiss [doc. 47] filed under Federal Rule of Civil Procedure 12(b)(6) by Sauer Construction LLC (“Sauer”), in response to the counterclaims asserted by plaintiff Pace Construction Services LLC (“Pace”). Pace opposes the motion. Doc. 52. I. BACKGROUND

This suit arises from a federal construction project for the renovation of barracks at Fort Polk, a United States Army installation in Vernon Parish, Louisiana. The Army (“Owner”) contracted with Sauer under Contract No. W9126G-18-C-0072 (“Prime Contract”) for Sauer to serve as design-build contractor for the project. Doc. 1, att. 5. Sauer then entered into a Subcontract Agreement No. S1C1765-1B (“Subcontract”) with plaintiff, Pace, under which Pace was to provide labor, materials, and equipment to assist Sauer in completing the Prime Contract. Doc. 1, att. 3. This work included gypsum assemblies, metal framing, and building insulation. Doc. 46, p. 11 ¶ 8. Pace was also required to obtain payment and performance bonds. Doc. 1, att. 3, pp. 7–8. These bonds were issued by defendant Federal Insurance Company (“Federal”), which acted as surety. Doc. 1, att. 2. Pace filed suit against Federal in this court in February 2023, alleging that its work on the

Project was delayed by various circumstances1 causing damages in the amount of $1,023,858.73. Doc. 1, ¶¶ 10–11. Accordingly, it sought to recover delay damages and the balance of the Subcontract from Federal under the Miller Act, 40 U.S.C. § 270(a)–(d), amended by 40 U.S.C. §§ 3131–3134. After a lengthy stay imposed by the Subcontract was lifted, Sauer intervened as defendant and asserted state law counterclaims for breach of contract and breach of

performance bond against Pace and its surety. Doc. 44. In response Pace raised a counterclaim for bad faith and/or intentional breach of contract against Sauer. Doc. 46. It alleges damages from the unpaid balance of the Subcontract as well as consequential damages including lost profits and higher costs. See id. at pp. 14, 17, ¶¶ 24, 35–36. Sauer now moves to dismiss Pace’s counterclaims, except to the extent that the counterclaim

states a breach of contract claim for the unpaid balance of the Subcontract. To this end it asserts that (1) delay damages are not available under the Subcontract and (2) Pace fails to state a claim for lost profits or other consequential damages caused by bad faith or an intentional breach of contract. Doc. 47, att. 1. Pace opposes the motion. Doc. 52.

1 In particular, Pace alleges delays resulting from (1) site conditions, including the discovery of asbestos and the presence of parapet walls not connected to the existing roof deck; (2) the COVID-19 pandemic; (3) unusually bad weather; and (4) directives to suspend work, perform work out of sequence, and/or correct defective work of a subcontractor hired to supplement Pace’s work. Doc. 1, ¶ 10; doc. 46, p. 12, ¶¶ 10–14. II. LAW & APPLICATION

A. Legal Standards Rule 12(b)(6) allows for dismissal when a plaintiff “fail[s] to state a claim upon which relief can be granted.” When reviewing such a motion, the court should focus on the complaint and its attachments. Wilson v. Birnberg, 667 F.3d 591, 595 (5th Cir. 2012). The court can also consider documents referenced in and central to a party’s claims, as well as matters of which it may take judicial notice. Collins v. Morgan Stanley Dean Witter, 224 F.3d 496, 498–99 (5th Cir. 2000); Hall v. Hodgkins, 305 Fed. App’x 224, 227 (5th Cir. 2008) (unpublished). Such motions are reviewed with the court “accepting all well-pleaded facts as true

and viewing those facts in the light most favorable to the plaintiff.” Bustos v. Martini Club, Inc., 599 F.3d 458, 461 (5th Cir. 2010). However, “the plaintiff must plead enough facts ‘to state a claim to relief that is plausible on its face.’” In re Katrina Canal Breaches Litig., 495 F.3d 191, 205 (5th Cir. 2007) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). Accordingly, the court’s task is not to evaluate the plaintiff’s likelihood of success

but instead to determine whether the claim is both legally cognizable and plausible. Lone Star Fund V (U.S.), L.P. v. Barclays Bank PLC, 594 F.3d 383, 387 (5th Cir. 2010). B. Application Sauer first asserts that the Subcontract does not allow for delay damages. The Subcontract provides:

5.3.6 CLAIMS RELATING TO DESIGN-BUILDER. Should the Subcontractor’s Work be delayed, disrupted or interfered with solely as a result of the acts or omissions of Sauer or anyone employed by Sauer on the Project, then Subcontractor shall receive an extension of time equal to the actual delay . . . as determined by Sauer. . . . An extension of time, as determined by Sauer, or the decision that no extension shall be allowed, shall be the Subcontractor’s sole remedy for the delay. In exchange, Subcontractor expressly waives the right to bring against Sauer or Sauer’s surety any claim for damage for delay, inefficiency, disruption, acceleration, interference, extra work resulting from such delay, extended overhead, wage escalation, overtime wage provisions, lost opportunity or lost profit or financial impact on Subcontractor’s other projects.

Doc. 1, att. 3, p. 11. Further, under Article 5.3.3, “Sauer shall not be liable to Subcontractor for any delay, disruption or interference . . . caused by” any number of circumstances, including weather conditions, change orders, and the act, omission, or fault of the Owner. Id. at 10. Nevertheless, Pace claims a bad faith and/or intentional breach of contract based in part on allegations that Sauer “failed to communicate crucial information regarding Change Orders relative to the Subcontract Work,” “failed to submit the proper Change Order documentation to the Owner for approval,” “failed to inform Pace that the Project schedule changed and the priorities on multiple projects at Fort Polk had been adjusted,” and communicated with the U.S. Army about “reallocat[ing] the available project resources to Project 0074 and away from the Project at issue in this litigation” while at the same time falsely claiming that any delays were attributable to Pace. Doc. 46, pp. 14–15, ¶¶ 22–23, 26–28. Additionally, Pace alleges that Sauer “intentionally made false and misleading statements regarding the quality and quantity of Pace’s work to Pace’s surety.” Id. at p. 15, ¶ 29. As a result, Pace asserts, it suffered damages. Id. at p. 17, ¶¶ 35–36. Louisiana Civil Code article 2004 nullifies any contractual clause that, “in advance, excludes or limits the liability for one party for intentional or gross fault that causes damage

to the other party.” La. Civ. Code art. 2004.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Morgan Stanley Dean Witter
224 F.3d 496 (Fifth Circuit, 2000)
Lone Star Fund v (U.S.), L.P. v. Barclays Bank PLC
594 F.3d 383 (Fifth Circuit, 2010)
Bustos v. Martini Club, Inc.
599 F.3d 458 (Fifth Circuit, 2010)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
David Wilson v. Gerald Birnberg
667 F.3d 591 (Fifth Circuit, 2012)
In Re Katrina Canal Breaches Litigation
495 F.3d 191 (Fifth Circuit, 2007)
Freeman v. Department of Highways
217 So. 2d 166 (Supreme Court of Louisiana, 1968)
Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
Roland Alonso v. Westcoast Corporation
920 F.3d 878 (Fifth Circuit, 2019)
Sanchez Oil v. Crescent Drilling
7 F.4th 301 (Fifth Circuit, 2021)
Wadick v. General Heating & Air Conditioning, LLC
145 So. 3d 586 (Louisiana Court of Appeal, 2014)
Volentine v. Raeford Farms of Louisiana, LLC
201 So. 3d 325 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
PACE CONSTRUCTION SERVICES L L C v. FEDERAL INSURANCE CO, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pace-construction-services-l-l-c-v-federal-insurance-co-lawd-2026.