Frederick v. City of Bonner Springs

178 P. 435, 104 Kan. 257, 1919 Kan. LEXIS 238
CourtSupreme Court of Kansas
DecidedFebruary 8, 1919
DocketNo. 21,929
StatusPublished
Cited by2 cases

This text of 178 P. 435 (Frederick v. City of Bonner Springs) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frederick v. City of Bonner Springs, 178 P. 435, 104 Kan. 257, 1919 Kan. LEXIS 238 (kan 1919).

Opinion

The opinion of the court was delivered by

Mason, J.:

W. H. Frederick entered into a paving contract with the city of Bonner Springs, by the terms of which he was to receive 37 cents .per cubic yard o’f excavation and $1.02 per square yard of paving. Claiming to have performed his contract, he brought an action for the contract price, $1,104.72, of which $87.50 was for g-rading. The city contested the claim on the ground that the work had not been approved by the city engineer, as required by the contract, and was so defectively performed as to be of no value. The plaintiff recovered judgment for $769.96, and the defendant appeals.

1. The fact that the engineer refused to approve the work is not fatal to the plaintiff’s recovery, if such refusal was arbitrary or unreasonable. (6 R. C. L. 960.) Under the instructions, the verdict necessarily implied a finding that this was the case, but the defendant insists that there was no evidence to justify it. The witnesses differed in their judgment as to the quality of the pavement. Although some of them testified that it was'very defective, others said in effect that the contract was substantially complied with. The plaintiff gave a version of the dealings between himself and the city officials which may be thus summarized :

The contract was made on November 23, 1916. It required work to be begun within ten days, to be prosecuted uninterruptedly, to be completed within 90 days, and to be done at the time and in the manner directed by the engineer. The grading was completed and the paving begun in December. About the middle of the forenoon of January 9 the engineer [259]*259ordered work to stop until further notice “owing to the uncertain weather conditions and the unsatisfactory condition of the subgrade.” The plaintiff continued work for about three hours, using the cement on hand, and then quit. The weather was then cloudy, but not freezing. On January 27, ■he asked the engineer by telephone for leave to begin work again the next day. The engineer said it was all right with him if it was with the mayor. He then-called the mayor and asked him to talk with the engineer. Later' the mayor told him he had done so and that it was all right with him. The mayor and engineer asked the plaintiff to sign a waiver with reference to the work he had done after being notified to quit —an agreement that if he was allowed to proceed this should not be construed by him as an acceptance of that work. He agreed to this; he wanted to sign the waiver,'and omitted to do so only because no opportunity was given him. He told the mayor he was going ahead, and asked if he could get an inspector. The mayor answered that he would do the best he could for him. The plaintiff resumed work and completed it on January 30, no inspector being furnished. On March 17 the plaintiff asked the engineer to come and look at the street. He did so and said that the work done without an inspector looked far better than the other, and that he would recommend an allowance of 70 per cent on the whole. They then went to the mayor and the engineer said to him: “Mr. Frederdick and I have come to the conclusion, or I have come to the conclusion, that I will recommend to the council that we pay him 70 per cent of that street and hold back 30 per cent, and if the job don’t hold up we will take the 30 per cent to complete the work, and I will recommend that you call the council together and pay him 70 per cent.” The mayor answered: “Anything that the city engineer says is all right with me. I am satisfied, I want to be honest about it.” On May 2, the mayor and council, acting in pursuance of later advice of the engineer, refused to pay anything whatever, and ordered the plaintiff to tear up and remove all the paving and repave the street. He asked to be told what portion of the paving was bad and offered to replace it, but no modification of the-demand for the removal of all of it was made.

The engineer in a written report to the mayor and council made statements to this effect: The plaintiff did not quit [260]*260work when ordered to do so, but continued until stopped by freezing weathér. When he asked leave to begin again the engineer told him he would consent provided the weather stayed warm, 'and provided further, that he would sign the “waiver” already referred to. The plaintiff agreed to do this, but began work without having done so, and without an inspector. After the completion of the pavement the engineer “figured to give an estimate of 60 per cent,” and when this was stated to the mayor, and the plaintiff insisted that he understood the estimate was to be 60 p'er cent of the work not inspected, he (the engineer) finally suggested that it might stand that much, which would amount to 70 per cent on the entire contract. After this conversation, the engineer decided to stick to his original recommendation that “a six-months test be required on all of this work not city inspected.” Holding the city not to be liable for any paving except that part put in under city inspection, the engineer submitted an estimate dated March 21, reporting that the plaintiff had completed 230 cubic yards of grading at 37 cents, and 225 square yards of paving at $1.02, making a total of $314.60.

The jury made a special finding to the effect that the plaintiff was ready, willing and able to perform his part of the contract, but that the city and the engineer acted unreasonably in demanding that he put in the whole street over again.

We regard this evidence as warranting the finding by the jury of the existence of the following circumstances, which are open to interpretation as tending to show bad faith on the part of the city authorities: The plaintiff was given permission to resume work only on condition that he should sign the agreement called a waiver — the necessity for which is not apparent. He was willing to sign it but was given no fair opportunity to do so. His not signing it was made an excuse for refusing to furnish him an inspector as the work progressed. The engineer upon his inspection (made more than six weeks after the work had been done) believed and told the mayor that the plaintiff was entitled to 70 per cent of the contract price, and that the 30 per cent retained would be sufficient security for the correction of any defects that developed later. Within a few days he made a formal report recommending the payment of $314.60. Later the mayor and council refused to make any [261]*261payment and ordered all the pavement removed. The plaintiff offered to replace any portion that should be pointed out to him as defective, but no particular part was so designated.

We do not suggest that the evidence compels these findings or that a conclusion of bad faith necessarily follows from them; but when conflicts in the testimony are resolved.in favor of the plaintiff, and the permissible inferences most favorable, to him are drawn from them, we are unable to say that a decision against the good faith of the engineer and the officials must be set aside as without support.

2. The defendant asserts that the amount of the. verdict (a little’ less than 70 per cent of the contract price) shows that the recovery was based upon quantum meruit, instead of upon the express contract, and contends that a municipality cannot be held liable on that basis. The rule that one who obtains an advantage from a part' performance by' a contractor who refuses to perform in full is sometimes liable to the extent of the value of the benefit conferred, may not apply to the same extent to municipalities as to individuals. (See, however, Ritchie v. City of Wichita, 99 Kan. 663, 163 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stauffer v. City of Topeka
436 P.2d 980 (Supreme Court of Kansas, 1968)
City of Denver v. Midwest Plumbing & Heating Co.
125 P.2d 960 (Supreme Court of Colorado, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
178 P. 435, 104 Kan. 257, 1919 Kan. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frederick-v-city-of-bonner-springs-kan-1919.