John Ritchie & Sons v. City of Wichita

163 P. 176, 99 Kan. 663
CourtSupreme Court of Kansas
DecidedFebruary 10, 1917
DocketNo. 20,273
StatusPublished
Cited by18 cases

This text of 163 P. 176 (John Ritchie & Sons v. City of Wichita) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Ritchie & Sons v. City of Wichita, 163 P. 176, 99 Kan. 663 (kan 1917).

Opinion

The opinion -of the court was delivered by

Dawson, J.;

On February 27, 1911, the city of Wichita awarded a contract to the plaintiffs for the paving of a street with vitrified brick. The contract provided that the plaintiffs should furnish the materials and do certain grading and excavation work. The improvement was to be under the supervision of the city engineer, and payments for eighty-five per cent of the work done were to be made every thirty days upon the engineer’s estimates. Work was to begin within thirty days and completed by July 1 of that year. Another contract between the same parties, let at the same time for some paving on another part of the same street, was to the same general effect, but was to be completed by June 1. Neither contract contained any stipulation as to penalties or liquidated damages for delay in the completion of the work, but in the first-mentioned contract it was provided :

“That if said second parties are delayed upon said improvement upon ' the request of said first party, by injunction suits or any unforseen contingencies, beyond the control of said second parties, then and in that case the time for the completion of said improvement shall be extended the same length of time as such delay.”

The same day that these contracts were awarded to the plaintiffs the city commissioners were served with a summons in a suib filed two days earlier, in which certain taxpayers affected by the proposed paving improvement prayed for an injunction restraining the city and its officials from levying and collecting special taxes on the abutting property to pay for the paving in question, on the ground that the petition under which the city had assumed to act and to let the contracts was not signed by the resident owners of one-half the fronting and abutting property. No temporary restraining order was issued, and that lawsuit proceeded leisurely to final judgment and the permanent injunction prayed for was granted on June 21, 1911. The plaintiffs were not parties to [665]*665the taxpayers’ suit, but sometime between March 13 and April 1 they learned that it was pending.

! On March 13 the plaintiffs furnished a surety bond as required by the contracts awarded them and on the same date the city commissioners executed the contracts. The surety bond cost the plaintiffs $146.76.

Notwithstanding the pendency of the taxpayers’ suit for an injunction, challenging the regularity and sufficiency of the proceedings leading up to the letting of the paving contracts, the city commissioner in charge of the department of public improvements, after consulting with the city attorney, directed the plaintiffs to proceed with the paving. To that end they made contracts for cement, sand, brick, etc., and had them brought to Wichita from distant points, and hauled to the place where the work was to be done. They did much excavation down to the grade established by the city engineer. They put in a considerable part of the concrete base. One of the monthly estimates was made by the city engineer as to the work done — $1600; and eighty-five per cent 'of that amount, $1360, was ordered paid by the city commissioners. It was not paid, however. When the judgment in the taxpayers’ suit was rendered on June 21 the city commissioner in charge of the paving construction ordered the plaintiffs to stop all work. They obeyed. Afterwards, on new proceedings, another contract for another kind of paving, called Westrumite, was let to another contractor, on different specifications, which required the filling in of part of plaintiff’s excavations, and some of the concrete laid by plaintiffs was laid partly below and partly above the grade specified for the Westrumite paving, and had to be torn out. Under the second letting the street has been paved.

The plaintiffs filed this action to recover on their contracts, for loss of profits, on quantum meruit, and for damages. The city answered denying its liability, alleging that the proceedings leading up to the letting of the contracts were void, that the contracts were void, and reciting the history of the" taxpayers’ suit. The plaintiffs replied, pleading estoppel by the action of the city commissioners in determining that the original petition to pave the street was sufficiently signed by resi[666]*666dent taxpayers affected thereby, by their resolution to pave,, their advertising for bids, etc., and—

“That the said city of Wichita, by and through its commissioner of' streets and public improvements and by and through its city attorney-advised the said plaintiffs herein after the action No. 28745, Sarah E. Smith et al. v. The City of Wichita et al., was commenced, that said:' action would not amount to anything, that no injunction was prayed' for, and that the beginning of the said action did not, in any wise, prevent the city or the plaintiffs from going ahead and completing the work according to contract and said commissioner of streets and said' city attorney directed the said plaintiffs to go ahead with the contract. That thereafter the city engineer and other officers of the city set the stakes for the grading and supervised and oversaw the work- of the-plaintiffs. That by reason of such facts the said city should be estopped' from setting up the said action of Sarah E. Smith et al. v. The City of Wichita et al., No. 28745, as a ground for defeating the plaintiff’s claim sued on in this action.”

Reserving proper objections as to competency, etc., the-litigants stipulated as to all the facts, and the trial court gave-judgment for plaintiffs for the sum paid by them for the-surety-bond, $146.76, but nothing more.

Plaintiffs’ appeal, contending that when the city commissioners make a finding that a petition is legally sufficient upon which to base their official action in proceeding to call forbids for paving, the contractor was entitled to rely on that finding and make a contract with the city and proceed with his', undertaking. It was decided in Sleeper v. Bullen & Dustin, et al., 6 Kan. 300, 307, that where the city had made such a finding as to the sufficiency of a petition of taxpayers to grade-a street, and had let a contract thereunder, and the work had' been completed, the city was estopped to deny the validity of the contract or its liability to the contractors for the paving. In H. & S. Rid. Co. v. Comm’rs of Kingman Co., 48 Kan. 70,. 28 Pac. 1078, the same principle was upheld in mandamus to require the issuing of railroad aid bonds after the railroad was constructed. There the defendants were estopped to deny the-sufficiency of the taxpayers’ petition after having made an administrative finding that it was sufficient and calling the-bond election pursuant thereto. This principle is well established in bond litigation when the rights of innocent holders have attached. (Finnup v. School District, 94 Kan. 695, 699, 146 Pac. 349, 148 Pac. 245, and citations.)

[667]*667But some legitimate field must be left for the operation of section 265 of the civil code and other statutes to the same effect:

“An injunction may be granted to enjoin the illegal levy of any tax, charge, or.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stauffer v. City of Topeka
436 P.2d 980 (Supreme Court of Kansas, 1968)
Harris v. City of Topeka
327 P.2d 1088 (Supreme Court of Kansas, 1958)
J. D. Adams Co. v. Dor Township
113 P.2d 138 (Supreme Court of Kansas, 1941)
City of Kanopolis v. Mountain
76 P.2d 803 (Supreme Court of Kansas, 1938)
Board of Education v. Powers
51 P.2d 421 (Supreme Court of Kansas, 1935)
Hutchin v. State Highway Commission
18 P.2d 124 (Supreme Court of Kansas, 1933)
Schenk v. City of Kansas
5 P.2d 842 (Supreme Court of Kansas, 1931)
Columbian Title & Trust Co. v. City of Tribune
298 P. 798 (Supreme Court of Kansas, 1931)
Getty v. City of Syracuse
281 P. 883 (Supreme Court of Kansas, 1929)
Du Bois v. City of Galena
276 P. 802 (Supreme Court of Kansas, 1929)
Mountjoy v. Cheyenne County High School District
240 P. 464 (Supreme Court of Colorado, 1925)
Eberhardt Construction Co. v. Board of County Commissioners
186 P. 492 (Supreme Court of Kansas, 1920)
City of Topeka v. Ritchie
184 P. 728 (Supreme Court of Kansas, 1919)
Frederick v. City of Bonner Springs
178 P. 435 (Supreme Court of Kansas, 1919)
Campbell v. Wichita Union Terminal Railway Co.
168 P. 833 (Supreme Court of Kansas, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
163 P. 176, 99 Kan. 663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-ritchie-sons-v-city-of-wichita-kan-1917.