City of Dunkirk v. Wallace

49 N.E. 463, 19 Ind. App. 298, 1898 Ind. App. LEXIS 35
CourtIndiana Court of Appeals
DecidedFebruary 18, 1898
DocketNo. 1,944
StatusPublished
Cited by6 cases

This text of 49 N.E. 463 (City of Dunkirk v. Wallace) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Dunkirk v. Wallace, 49 N.E. 463, 19 Ind. App. 298, 1898 Ind. App. LEXIS 35 (Ind. Ct. App. 1898).

Opinion

Wiley, J.

— The material facts charged in the complaint are that on October 7, 1891, John Reese and John Hayes, under the firm name of Hayes & Reese, entered into a written contract with the appellant to improve a certain street in said city; that before said work was commenced Reese sublet his interest in said improvement contract to Edward Stack and John Buckley; that afterwards, and before the work was begun, Hayes, Stack, and Buckley, sublet the work to appellee; that thereupon the appellee and Hayes, Stack, and Buck-ley entered into a written contract whereby appellee agreed to fulfill the terms and conditions of the contract between appellant and Hayes and Reese; that in compliance with the terms of said contract between appellant and Hayes & Reese, appellee commenced the work of said improvement, and prosecuted said work for many weeks, with the knowledge and consent of appellant; that appellee had almost completed the grading of said street according to the terms of the contract, when appellant, without the knowledge or consent of appellee, entered into a contract with one A. A. Knapp Company for the construction of a sewer in and along said street and the part thereof which appellee was then improving; that appellant thereupon demanded that appellee should cease, his said work of improvement in order that said sewer niight first be constructed in said street; that appellee refused to give up the possession of said street; that thereupon said Hayes, Buckley, and Stack came to appellee, and requested and demanded that he suspend work on said street; that appellee still refused to abandon his said work, when he was in[300]*300formed by the street committee of said city that the town trustees had ordered him to suspend such work, and said committee and said Hayes then and there informed him that if he did not cease operations and give up possession of said street they would compel him to do so by injunction; that appellee believed appellant had the right to compel him to suspend said work and, having been further directed by said Hayes, Buckley, and Stack to so suspend, he did, in obedience to said demands and requests, suspend said work, and permitted the sewer contractor to take possession of said street; that at that time he had almost completed the grading; that he had spent in the prosecution of said work in time and labor, $1,050.00; that the work so done by him was of great permanent value, both to appellant and to persons owning property abutting on said street; that he suspended said work in September, 1892, and near the end of the season suitable for such work; that before another season arrived • in which it was possible for appellee to resume and complete said improvement, appellant entered into a written contract for the improvement and macadamizing of said street with one-; that said contract was still in force and covered the same portion of said street as the contract sublet to appellee; that appellant thereupon gave possession of said street to said---, for the purpose of making said improvement, all of which was done without the knowledge or consent of appellee; that said sewer was constructed in said street, and that the work of constructing the same, and the trench made therefor was so negligently and improperly refilled, practically destroyed and ruined a large part of the grading completed by appellee; that appellant has been requested to restore said street to the condition in which appellee left it; that it has refused to allow appellee [301]*301any compensation for refilling said trench and for restoring said street to the condition in which appellee left it. That appellant refuses to recognize appellee as in any way connected with said contract for the improvement of said street; that appellee has not received any pay or compensation for his expenditure of labor and money for the improvement of said street, and that he was in no way responsible for the construction of said sewer, or the condition of the street caused thereby. The prayer of the complaint is as follows: “Wherefore plaintiff says that defendants have prevented plaintiff from completing his said contract for a long and unreasonable time, to his damage in the sum of $1,200.00 for which he prays judgment, etc.” Hayes, Buckley, and Stack were made defendants, but during the trial the appellant dismissed as to them. A copy of the contract between Hayes, Buckley, and Stack and appellant was made a part of the complaint, but it adds no force or effect to the complaint, because it is not the foundation of the action, and we cannot consider it for any purpose.

The appellant demurred to the complaint for want of sufficient facts, which the court overruled, and appellant excepted. The cause was put at issue, tried by the court, resulting in a finding and judgment for appellee in the sum of $760.00. The errors assigned are: (1) That the court erred in overruling the demurrer to the complaint, and (2) that the court erred in overruling appellant’s motion for a new triál.

The record, as it comes to us, presents but one question, and that is the sufficiency of the complaint. The motion for a new trial is based on questions which arose in the progress of the trial in regard to the rejection and admission of evidence, that the dam-' ages are excessive, that the decision of the court is not sustained by sufficient evidence, and that the de[302]*302cisión is contrary to law. None of the questions thus raised are available, for the reason that the evidence is not in the record.

The motion for a new trial was overruled June 15, 1895, and ninety days given in which to prepare and file a bill of exceptions. The record shows that on September 13, 1895, the bill of exceptions was presented to and signed by the judge, and the clerk certifies that the longhand manuscript of the evidence, as transcribed by the shorthand reporter, was filed in the clerk’s office September 17, 1895, being four days after it was incorporated in the bill of exceptions. Under the uniform authorities in this State, the longhand manuscript of the evidence must be filed in the clerk’s office before it is incorporated in the bill of exceptions. Upon this proposition the citation of authorities is unnecesary.

The theory of the complaint is that appellant wrongfully caused appellee to suspend work on the' street he was improving under the contract sublet to him by Hayes, Buckley, and Stack, and afterwards let the contract for the same improvement to another, without his knowledge or consent, after he had done work and expended money under the contract. To state it differently, appellee’s theory is that appellant is liable to him for the work done and money expended under his contract on the ground that appellant caused him to suspend his work, gave the possession of the street to another for the construction of a sewer therein, and then violated its contract with him by letting the contract to another, and refusing to put him in possession of the street to complete the work, and in refusing to restore the street to the condition in which he left it. The original contract between Hayes and Reese and appellant, is not brought into the record, and we have no means of knowing [303]*303what its terms and conditions were, other than as stated in the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blain v. City of Delphi
145 N.E. 764 (Indiana Supreme Court, 1924)
City of Laporte v. Ahlborn
133 N.E. 874 (Indiana Supreme Court, 1922)
Frederick v. City of Bonner Springs
178 P. 435 (Supreme Court of Kansas, 1919)
City of Newcastle v. Dingle
114 N.E. 221 (Indiana Supreme Court, 1916)
Broad v. City of Moscow
99 P. 101 (Idaho Supreme Court, 1908)
Grau v. Grau
77 N.E. 816 (Indiana Court of Appeals, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
49 N.E. 463, 19 Ind. App. 298, 1898 Ind. App. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dunkirk-v-wallace-indctapp-1898.