City of Newcastle v. Dingle

114 N.E. 221, 185 Ind. 626, 1916 Ind. LEXIS 78
CourtIndiana Supreme Court
DecidedNovember 28, 1916
DocketNo. 22,527
StatusPublished
Cited by6 cases

This text of 114 N.E. 221 (City of Newcastle v. Dingle) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Newcastle v. Dingle, 114 N.E. 221, 185 Ind. 626, 1916 Ind. LEXIS 78 (Ind. 1916).

Opinion

Cox, J.

— This appeal is from a judgment in an action in the court below for damages claimed by appellees against the city of Newcastle. The complaint alleges, in substance, that the appellees in the year 1907 contracted with appellant to build a portion of Race street in appellant city by grading and paving the same with brick, and by constructing cement sidewalks on either side thereof. That the appellees. proceeded to construct the street according to the contract but that before the completion of the same or during its construction, they were delayed by the failure of the city to remove certain telegraph, telephone or other poles that were in the street, and that, by reason of the delay caused by such failure on the part of appellant, appellees were compelled to delay the work until the summer of 1908, at which time they completed the work on the street, which was accepted by the city

[628]*628officials. That appellant issued bonds to the appellees for the amount of the contract price. That in the fall and winter of 1907 they were ordered by appellant to proceed with the construction of the cement sidewalks along the street at a time when the weather was too cold for the proper construction of cement walks, and that in compliance with- the order received from the town board, appellees proceeded to construct a portion of the sidewalk along the street and that the same froze, and by reason of such freezing appellees were compelled to take up a portion of the walk and reconstruct the same. That appellees were compelled to borrow money for the purpose of carrying on the construction of the street, and had gathered together a large number of men and tools and implements necessary for the construction of the street and sidewalks, for which they invested a large amount of money, and that by reason of the delay caused by the failure of the town promptly and properly to remove the poles within the street, they were compelled to be without the use of these tools and implements and to pay interest on the money so borrowed. That the town board during the construction of the street condemned a portion of the sidewalk that had been constructed and required the appellees to remove the same, which they did at the order of the town board, and that at the further order of the town board they reconstructed -the removed sidewalk. That the walk so condemned by the town board was walk that had been caused to crack by reason of the fact that the town board in constructing ditches and removing poles had failed to properly restore the dirt so removed, causing the ground beneath the sidewalk to give way and leaving the walk without proper support. For all of which [629]*629appellees claim to have been damaged in the snm of $2,000.

To this complaint appellant filed a demurrer-which was overruled. Appellant then filed an answer in three paragraphs, the first being a general denial, the third a plea of payment and the second an answer which was in substance as follows: That the work and improvement of Race street in the town of Newcastle, Indiana, set out and described -in the complaint and the contract filed with the complaint and all proceedings had in relation to. such improvement were had and entered into under and by virtue of §265 of an act of the general assembly entitled “An act concerning municipal corporations,” approved March 6, 1905, and all acts amendatory and supplementary thereto, and the entire cost of the improvement was assessed as special benefits to the abutting and adjacent property owners, and the town of Newcastle assumed and agreed to pay no part of the cost of the improvement. That the appellees did not give any bond to the approval of the board- of trustees of the town to secure the performance of the contract set out in the complaint as provided by law, until July 7, 1908, and all acts, omissions and transactions set out and complained of by appellees had been consummated and had transpired prior to that date and the alleged causes of action sued on had all accrued prior to that date.

To this answer appellees replied in two paragraphs, the first a general denial, and the second, in substance, as follows: That in the month of July, 1907, the town of Newcastle, by proper, resolution, determined to improve the street 'in the town, known as East Race street, by grading and paving the same with brick, and cement curb and sidewalk. That under and pursuant to the [630]*630resolution the town prepared and caused to be prepared full and complete plans and specifications for the work by its civil engineer and adopted the same, and by proper notice as required by law, advertised for bids for the construction of the work. That appellees submitted at the time required in the notice thereof, their bid in writing, proposing to< construct the street, curb and sidewalk, in all respects according to the specifications and' plans therefor. That thereafter the town of Newcastle duly accepted the bid made by appellees and directed the engineer to enter into a written contract with bond with the appellees for the construction of the . work. That the engineer was delayed, for some cause unknown to appellees, in the preparation of the contract and bond, but that the board of trustees ordered the appellees to proceed with the work, which they did under the order and directions of the board, and pursuant to the terms of their bid and proposal and the written acceptance thereof by the town. That after the same had been partly completed, the-engineer of the town prepared the contract set out in the complaint with the proper bond for the execution of the same and that they, were both dated back to the date of the acceptance of the bid and signed by appellees and appellant. That the contract and bond were intended to evidence the contract for the improvement of the street, and after the execution of the same the appellees proceeded with the completion of the contract, at an expense of over $6,000. That the town stood by and witnessed the progress of the work both before and after the execution of the contract and requested and demanded the appellees to proceed with the work, and after the completion of the same they accepted the improvements and assessed the costs thereof, according to the terms of the [631]*631agreement, upon the abutting property owners, all of whom acquiesced in the same. The appellees aver that by the execution of the agreement set forth in the complaint, and by standing by and allowing the work to proceed without objection, and by accepting the work and assessing the costs therefor, the appellant ratified and confirmed all acts and liabilities under the contract and waived all questions of its legality by reason of the failure to reduce it to writing at the time entered into; and that the contract set forth in the complaint is of the same binding force as if it had been entered into, signed and executed at the time the oral agreement was entered into.

Appellant demurred to this reply, which demurrer was overruled. Following this ruling there was a trial by jury on the issues formed by general denial. The jury returned a verdict for appellees for the sum of $250 upon which the court rendered judgment for the appellees. Appellants filed a motion for a new trial setting up as causes therefor that: (1) the verdict of the jury was not sustained by the evidence; (2) the verdict of the jury was contrary to law; (3) the court committed certain errors in the trial of the said cause in giving instructions and in admitting evidence. This motion was overruled by the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1st Source Bank v. Village of Stevensville
947 F. Supp. 2d 934 (N.D. Indiana, 2013)
St. Joseph Loan & Trust Co. v. Studebaker Corp.
66 F.2d 151 (Seventh Circuit, 1933)
Boyer v. City of Yakima
273 P. 188 (Washington Supreme Court, 1928)
Blain v. City of Delphi
145 N.E. 764 (Indiana Supreme Court, 1924)
Buck v. Indiana Construction Co.
138 N.E. 356 (Indiana Court of Appeals, 1923)
City of Laporte v. Ahlborn
133 N.E. 874 (Indiana Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
114 N.E. 221, 185 Ind. 626, 1916 Ind. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-newcastle-v-dingle-ind-1916.