This text of 178 So. 2d 217 (FRED S. CONARD CONSTRUCTION CO. v. Exchange Bank of St. Augustine) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FRED S. CONARD CONSTRUCTION CO. v. Exchange Bank of St. Augustine, 178 So. 2d 217 (Fla. Ct. App. 1965).

Opinion

178 So.2d 217 (1965)

FRED S. CONARD CONSTRUCTION COMPANY, a corporation of Florida, Appellant,
v.
The EXCHANGE BANK OF ST. AUGUSTINE, a state banking corporation, the Fidelity and Casualty Company of New York, a corporation of New York, Clement A. Solana, and Victor E. Raymos, as Trustee in Bankruptcy in the matter of Clement Alfonso Solana and Jacqueline Juanita Solana, his wife, Bankrupts, Appellees.

No. G-194.

District Court of Appeal of Florida. First District.

August 19, 1965.
Rehearing Denied September 30, 1965.

*218 W.O. Birchfield, of Milam, Ramsay & Martin, Jacksonville, for appellant.

Upchurch & Upchurch, St. Augustine, for appellee.

STURGIS, Judge.

Fred S. Conrad Construction Company, defendant below, appeals from a summary final judgment in favor of the plaintiff, The Exchange Bank of St. Augustine (appellee).

The appellee bank brought an action at law against appellant and others to recover an alleged indebtedness arising under the following circumstances:

The appellant, a contractor, agreed to construct for Wise Potato Chip Company a manufacturing plant in St. Augustine, Florida, and later subcontracted to Clement A. Solana certain masonry work on the plant. The subcontract provided in pertinent part:

"The Sub-Contractor agrees to provide the work required to complete and will complete the following described items of work in connection with the erection of Wise Potato Chip Company Manufacturing Plant, St. Augustine, Florida, and will furnish * * * all necessary labor to complete installation of all masonry products."
* * * * * *
"* * * the payment of the consideration is executory and conditioned upon completion of this contract and completion of the work as above specified."
* * * * * *
"* * * the unpaid balance of the price at all times [shall] be sufficient in the judgment of the * * * Contractor, to complete the work and to pay any unpaid liens or claims for which said Contractor is responsible hereunder."
* * * * * *
"No progress payment made under this contract shall be conclusive evidence of the performance of this contract either wholly or in part, and no payment shall be construed to be acceptance of defective work or improper materials."

Solana then assigned to the appellee bank "all monies due or to become due on that certain contract between * * * [Solana] and * * * [appellant] * * * dated April 15, 1963," a true copy of which *219 was attached to and by reference made a part of the assignment. Appellant then accepted said assignment and agreed to pay to appellee "all sums due or to become due Clement A Solana, under its contract * * * dated April 15, 1963." There was no modification of said subcontract or the contract of assignment.

It was customary at the end of each week for Solana and a representative of appellant to calculate the work done by Solana during that week and record their computations on a form entitled "Masonry Work Order" which indicated the amount payable to Solana under a caption entitled "This Draw," and it was Solana's custom to take this document to the bank and borrow almost the exact amount shown under said item, giving his promissory note therefor. It was customary for the bank to then attach a copy of the "Masonry Work Order" to duplicate copies of a covering form letter and mail same to appellant with a request that it return a copy of the form letter after noting thereon the date received, by whom approved, and the date payment might be expected. It is pertinent at this juncture to note that prior to such mailing the bank in each instance had already consummated its loan to Solana.

Acting pursuant to the bank's letters, appellant remitted to the bank the amounts indicated as "This Draw" on the first five "Masonry Work Orders" transmitted, but refused to remit funds pursuant to such letters of the bank relating to the next eight "Masonry Work Orders" in point of time, totaling $4,720.00. This amount was admittedly due by Solana to the bank for money borrowed on the strength of said assignment and evidenced by his several 7% promissory notes in favor of the bank.

The appellant, in answer to appellee's second amended complaint, admitted it had refused to pay the said amount alleged to be due, and asserted that it was withholding said amount in accordance with the terms and conditions of its subcontract with Solana; and appellant also alleged, in substance, that Solana had breached his contract with appellant and that under the terms thereof appellant was entitled to retain such amount as would be sufficient to complete the work subcontracted to Solana in accordance with the terms and conditions of the contract.

It was established at the hearing upon appellee's motion for summary judgment that Solana defaulted in his contract with appellant, who got another masonry contractor in to finish the job, and that the resulting cost to appellant exceeded the amount retained by it under the subcontract with Solana.

Appellant's motion for leave to file a counterclaim against the appellee was denied.

By this appeal we are called on to decide: First. Whether the trial court erred in holding appellant liable to the appellee bank pursuant to Solana's assignment of "monies due or to become due" to Solana under his subcontract with appellant, to which the assignment was subject, and where it appears that in the absence of such assignment Solana would unquestionably be liable to appellant for damages suffered by virtue of Solana's admitted default under the contract and that appellant would have been entitled to withhold the subject payments to Solana and to apply the same on account of the damages sustained by Solana's default.

It is fundamental that the assignee of a contract or non-negotiable chose in action occupies the same position as its assignor and is subject to the same equities, conditions and defenses that could have been asserted against the assignor. Florida East Coast Ry. Co. v. Eno, 99 Fla. 887, 128 So. 622, 626, 70 A.L.R. 506 (1930); Birmingham Trust & Savings Co. v. Jackson County Mill Co., 41 Fla. 498, 27 So. 43, 45 (1899); 3 Fla.Jur., Assignments, Sec. 25. These principles were applied in Geo. G. Tapper Company, Inc. v. Bank of Fort Walton, 117 So.2d 8 (Fla.App. 1959), *220 holding that the contractor's liability to the assignee bank was limited to the balance of the approved estimates of amounts payable to the subcontractor, less all amounts for which the subcontractor was liable to the contractor under the terms of the contract; and referring to a letter of the contractor to the bank recognizing the assignment, upon which the bank relied to fix liability, we observed that the only efficient method by which the bank could ascertain what funds would be available to the subcontractor and in turn applicable to the discharge of the promissory notes held by the bank was by having reference to the subcontract proper, and in that connection said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Standard Jury Instructions—Contract & Business Cases
116 So. 3d 284 (Supreme Court of Florida, 2013)
Kelly v. Lodwick
82 So. 3d 855 (District Court of Appeal of Florida, 2011)
Shaw v. State Farm Fire & Casualty Co.
37 So. 3d 329 (District Court of Appeal of Florida, 2010)
NCP Lake Power, Inc. v. Florida Power Corp.
781 So. 2d 531 (District Court of Appeal of Florida, 2001)
Escandar v. Southern Mgmt. & Inv. Corp.
534 So. 2d 1203 (District Court of Appeal of Florida, 1988)
Danna v. Bay Steel Corporation
445 So. 2d 704 (District Court of Appeal of Florida, 1984)
Nat. Merchandise Co., Inc. v. United Serv. Auto. Ass'n
400 So. 2d 526 (District Court of Appeal of Florida, 1981)
Linder Industrial Machinery Co. v. Le-Bert International, Inc.
359 So. 2d 550 (District Court of Appeal of Florida, 1978)
Morton v. Morton
307 So. 2d 835 (District Court of Appeal of Florida, 1975)
Dickerson, Inc. v. Federal Deposit Insurance Corp.
255 So. 2d 521 (Supreme Court of Florida, 1971)
Dickerson, Inc. v. Federal Deposit Insurance Corp.
244 So. 2d 748 (District Court of Appeal of Florida, 1971)
Douberley v. Angelini
240 So. 2d 98 (District Court of Appeal of Florida, 1970)
Gorham Construction Co. v. Superior Fertilizer & Chemical Co.
218 So. 2d 516 (District Court of Appeal of Florida, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
178 So. 2d 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fred-s-conard-construction-co-v-exchange-bank-of-st-augustine-fladistctapp-1965.