Florida East Coast Railway Co. v. Eno

128 So. 622, 99 Fla. 887, 70 A.L.R. 506, 1930 Fla. LEXIS 1587
CourtSupreme Court of Florida
DecidedApril 23, 1930
StatusPublished
Cited by38 cases

This text of 128 So. 622 (Florida East Coast Railway Co. v. Eno) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida East Coast Railway Co. v. Eno, 128 So. 622, 99 Fla. 887, 70 A.L.R. 506, 1930 Fla. LEXIS 1587 (Fla. 1930).

Opinion

*890 Per Curiam.

Upon consideration of this canse on rehearing, it is ordered that the dissenting opinion filed by Mr. Justice Strum upon the original consideration of this cause on June 28, 1928, reported in 117 So. R. 713, be and the same is hereby ádopted .as the opinion of the Court upon the matters discussed in that opinion. The former order remanding this cause to the lower court with directions to dismiss the bill is hereby vacated.

A suit in interpleader consists of two major phases. It , should first be determined whether the bill will lie. See Lowry v. Downing, on second appeal, 80 Fla. 745, 87 So. R. 65. That phase of the matter may be determined by any of the several methods appropriate to chancery practice for testing the sufficiency of a bill, if the objectionable matter appears on the face of the bill. If any facts exist which are not shown by the bill of interpleader, but which constitute a valid reason why thei bill should not lie, they are matters of defense and may be set up by answer, which of course must be supported by proof. If it is found that the bill will not lie, it is useless to go further, and the bill will be dismissed. If it is found that the bill will lie, then the court so decrees, and upon bringing into court the property in dispute the complainant is discharged from further liability, with his costs. The second phase of the matter is then taken up. If the case is ripe for decision between the defendants, as well as between them and the complainant, the court may forthwith settle the conflicting claims of the parties and make a final decree as to all parties at one hearing. If, however, the cause is not then ready for decision as between the conflicting claimants, the court orders that such claimant's, who originally are defendants, interplead and litigate the matter in dispute between themselves. Appropriate issues are then made and proof taken, if necessary, between the claimants, and the *891 contest proceeds between them to determine who is entitled to the subject mattér. The latter phase of the matter becomes, in effect, a new and independent proceeding between the claimants alone as adversaries. Wainwright v. Connecticut Ins. Co., 73 Fla. 130, 74 So. R. 8; Lowry v. Downing, supra; Sammis v. L’Engle, 19 Fla. 800; Grass v. Memphis (Ala.), 11 So. R. 480; Puterbaugh Pl. & Pr. (6th Ed.) 359; Story’s Eq. Pl. (10th Ed.), Sec. 297A.

In its answer, which is directed to the first phase of this controversy, the defendant bank raises certain issues of fact, proof of which would have a material bearing upon the complainant’s right to compel an interpleader. Of course, proof does not lie in mere assertion. The presence of such averment's of fact in the bank’s answer affords no justification for holding that the bill must fail merely because the assertion is made. Such action is premature at that point in the controversy. The complainant is enütled first to test the soundness of the answer in an appropriate manner, and then if issues of fact remain, such issues, and their effect upon the questions of whether the bill will lie, can be decided only after proof. If the proof shows conduct or interest on the part of the railway inconsistent with the requisite status of a complainant in inter-pleader, it will be fatal to the bill.

It appears from the bill of complaint herein that all parties defendant to this cause claim under James L. EnO. See 117 So. R. 710, 713. The lien claimants are laborers, materialmen and sub-contractors under Eno, who was the principal contractor with t'he c.omplainant railway in the performance of four separate construction contracts, under each of which a separate and distinct balance is due by the railway, making four separate and distinct funds. The bank is Eno’s assignee of all moneys due and to become due from the railway to Eno under all the contracts. The *892 claims of the assignee bank and of all the lien claimants are adverse to each other, the bank asserting its claim to be superior to all others.

Interpleader will lie when the adverse claims of the defendants are derived through a common source. See the cases hereinafter cited; also Fogg v. Goode, 78 Fla. 138, 82 So. R. 614; Puterbaugh Pl. & Pr. (6th Ed.) 346, 15 R. C. L. 224, 33 C. J. 433.

There is a group of lien claimants as to each of the four funds. All of them claim through Eno. The bank claims' all of the funds by assignment from Eno. In respect to each of the funds considered separately, Eno is the common debtor of the bank and the group of lien claimants whose claims apply to that particular fund. Eno and the claimants of each of the several funds, including the bank, are in privity of contract' as to the particular fund to which their claim applies. In the absence of disqualifying interest or conduct on its part which would preclude inter-pleader, the railway, by making each of the five funds the subject of a separate suit, could maintain interpleader between the bank and the lien claimant's as to each of the several funds due under the four construction contracts, because as to each of said funds, considered separately, the adverse claims of the bank and the lien claimants are derived through a common source with respect to that particular fund, namely, Eno; the common debtor, with whom all claims are in privity of contract. If each of the four funds were made the subject of a separate suit for inter-pleader between the claimants of that particular fund, the same situation in principle would be presented as in Lowry v. Downing, on first appeal, 73 Fla. 535, 74 So. R. 525, the bank, as Eno’s assignee, occupying Eno’s exact position in the matter. As a claimant of the fund, the bank is in privity of contract with Eno, the common debtor of, all the *893 claimants, and the common source of all claims against each fund.

The railway having joined the four several and unrelated funds in one bill, and the lien claimants having no common interest in all the funds, but only in the particular fund to which their respective lien claims apply, the bill for that reason may be multifarious and might have been subject to a timely objection upon that ground interposed by a party in a position to raise the point. But the question of multifariousness is not before us on this appeal, and the question is not a jurisdictional one. See 117 So. R. 713.

There is no dispute here as to the amount of money the complainant offers to bring into court. In that respect this case differs essentially from Lowry v. Downing, on second appeal, 80 Fla. 754, 87 So. R. 65, wherein it was held that a bill of interpleader would not lie because it was there established, upon proof, that' the complainant had first unjustifiably adjusted his own claims against the fund by making certain disputed deductions therefrom, and then sought to compel the defendants to interplead as to the remainder. See also Fogg v. Goode, 78 Fla. 138, 82 So. R. 614.

The mere fact that the bank claims as Eno’s assignee does not of itself affect complainant’s right to an interpleader. East India Co. v. Edwards, 18 Ves. R. 377; Puterbaugh Pl. & Pr. (6th Ed.) 349. Eno had the right to assign to the bank all moneys due or t'o become due him under his construction contracts with the railway. Clarkson v. Lauderbeck, 36 Fla. 660, 19 So. R. 887; Tampa etc., R. Co. v. Harrison, 55 Fla. 810, 46 So. R. 592.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaw v. State Farm Fire & Casualty Co.
37 So. 3d 329 (District Court of Appeal of Florida, 2010)
Avco Corp. v. Peterson Engineering Co., No. Cv535232 (Nov. 16, 1994)
1994 Conn. Super. Ct. 11511 (Connecticut Superior Court, 1994)
Radio South Dade, Inc. v. Marrero
572 So. 2d 3 (District Court of Appeal of Florida, 1990)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
540 So. 2d 113 (Supreme Court of Florida, 1989)
Editorial Cernuda, Inc. v. Editorial America, S.A.
522 So. 2d 1030 (District Court of Appeal of Florida, 1988)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
524 So. 2d 439 (District Court of Appeal of Florida, 1988)
Angora Enterprises, Inc. v. Cole
439 So. 2d 832 (Supreme Court of Florida, 1983)
Shreve Land Co., Inc. v. J & D FINANCIAL CORP.
421 So. 2d 722 (District Court of Appeal of Florida, 1982)
Cole v. Angora Enterprises, Inc.
403 So. 2d 1010 (District Court of Appeal of Florida, 1981)
Alderman Int. Sys v. First Nat.-Heller Factors
376 So. 2d 22 (District Court of Appeal of Florida, 1979)
Morton v. Morton
307 So. 2d 835 (District Court of Appeal of Florida, 1975)
Dickerson, Inc. v. Federal Deposit Insurance Corp.
255 So. 2d 521 (Supreme Court of Florida, 1971)
City of Miami Beach v. Sterin
214 So. 2d 360 (District Court of Appeal of Florida, 1968)
Prestress Erectors, Inc. v. James Talcott, Inc.
213 So. 2d 296 (District Court of Appeal of Florida, 1968)
City National Bank of Coral Gables v. H. & B. Construction Corp.
183 So. 2d 704 (District Court of Appeal of Florida, 1966)
Fred S. Conrad Construction Co. v. Exchange Bank of St. Augustine
178 So. 2d 216 (District Court of Appeal of Florida, 1965)
FRED S. CONARD CONSTRUCTION CO. v. Exchange Bank of St. Augustine
178 So. 2d 217 (District Court of Appeal of Florida, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 622, 99 Fla. 887, 70 A.L.R. 506, 1930 Fla. LEXIS 1587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-east-coast-railway-co-v-eno-fla-1930.