Florida Wildlife Federation v. United States Army Corps of Engineers

404 F. Supp. 2d 1352, 61 ERC (BNA) 1697, 2005 U.S. Dist. LEXIS 27356, 2005 WL 3418302
District Court, S.D. Florida·Decided November 10, 2005·No. 0580339-CIV·Published·Cited by 5 cases

Opinion

ORDER

MIDDLEBROOKS, District Judge.

THIS CAUSE comes before the Court upon the parties’ memoranda on remedies. 1 The Court has reviewed the record, heard the parties’ arguments, and is otherwise fully advised in the premises.

In this action, Plaintiff environmental groups challenged the issuance of a permit by the U.S. Army Corps of Engineers (“the Corps”) to Palm Beach County (“the County”) allowing the dredging and filling of jurisdictional wetlands for the development of the Palm Beach County Biotechnology Research Park / Scripps Project. On September 30, 2005, this Court granted summary judgment in favor of Plaintiffs, and directed the parties to file memoranda on the issue of remedies. A hearing on remedies was held on November 8, 2005.

For the reasons provided below, I conclude that the appropriate remedy is to set aside the Corps’ permit, remand the matter to the Corps for further proceedings consistent with the Court’s September 30, 2005 Order, and, with certain exceptions, enjoin the County from further construction on the Mecca Farms site pending adequate environmental review. Although I decline to enjoin Scripps’ construction of three buildings on the site, I am in no way endorsing such construction, nor do I mean to suggest that developing a Research Park on Mecca Farms is environmentally sound or otherwise feasible. That determination must remain with the Corps, Scripps and officials of Palm Beach County.

I. Background

In October 2003, Palm Beach County and The Scripps Research Institute joined forces to develop plans for the Palm Beach County Biotechnology Research Park, a biotech industry cluster with Scripps as its anchor.

The State of Florida agreed to provide $310 million of economic stimulus funds over a period of seven years for the project, and the County pledged to spend up to $200 million to provide land, infrastructure and buildings for the new Scripps Florida facility.

The County and Scripps selected Mecca Farms, a 1,919-acre parcel in western *1355 Palm Beach County, as the site for the project. Scripps leased 102.03 acres on the southeastern portion of the property, and planned to construct three buildings on 44 acres of that land. The County would make the remaining property available to other biotech-related companies and support facilities, enabling the County to recover costs associated with the project. Portions would also be used to enhance surrounding ecosystems, meet water management goals, and buffer nearby residential properties.

Mecca Farms was historically part of the Hungryland Slough, and predominately wetland. Mecca is bordered to the east, west, and north by environmentally sensitive lands, including the J.W. Corbett Wildlife Management Area (“Corbett”), the Hungryland Slough, and Vavrus Ranch, which contains numerous, high value wetlands.

To prepare Mecca Farms. for agriculture, ditches were constructed in place of historic flow ways, running every 360 feet throughout the property. The agricultural ditches are permanently inundated and drain into the C-18 Canal, a tributary of the Northwest Fork of the Loxahatchee River, a National Wild and Scenic River.

The U.S. Army Corps of Engineers deemed these wetlands to be waters of the United States, and asserted jurisdiction over them under the Clean Water Act, 33 U.S.C. § 1251 et seq.

On or about May 13, 2004, the County submitted an application to the Corps for a permit to allow the dredging and filling of jurisdictional wetlands on the Mecca Farms site. In its application, the County narrowed its “proposed project” to construction on only 535 acres of the 1,919 acre site. The 535-acre portion of the site contained 21.38 acres of jurisdictional wetlands.

Before issuing the permit, federal law required the Corps to determine whether the proposed action would have a significant impact on the environment. National Environmental Policy Act, 42 U.S.C. § 4321 et seq. To make this determination, the Corps was required to take a “hard look” at the direct, indirect and cumulative effects of the proposed action on the environment, including those effects that were reasonably foreseeable. If the Corps found the proposed action would have a significant impact on the environment, it was required to prepare an Environmental Impact Statement (“EIS”) before issuing the permit.

Although the Corps was aware of the County’s plans to develop the remainder of Mecca Farms for the Research Park Project, including road extensions that the Corps believed would present troublesome environmental issues, and construction of a power substation on the adjacent Corbett conservation lands, the Corps limited its assessment of the environmental impacts to the direct effects of filling jurisdictional wetlands for the 535-acre phase of the project, only. The Corps then found that the proposed project would have no significant impact on the environment.

On February 22, 2005, the Corps issued the permit without preparing an EIS.

On February 28, 2005, Plaintiff Florida Wildlife Federation notified the Corps and the County of its intent to challenge the permit in federal court. Also on February 28, 2005, the County submitted an application to the Corps for construction of the power substation on Corbett that would serve the entire 1,919 acre planned development. .

By late May 2005, the County had dredged and/or filled all jurisdictional wetlands on the 44 acres where Scripps planned to construct its three buildings.

On April 21, 2005, Plaintiffs filed this action against the Corps, alleging that the *1356 issuance of the permit violated the National Environmental Policy Act (“NEPA”), the Clean Water Act (“CWA”), and the Rivers and Harbors Act of 1899 (“RHA”). Plaintiffs did not move for preliminary in-junctive relief.

On June 2, 2005, the parties agreed to an expedited briefing schedule and advised the Court that they believed the matter would be resolved on their cross-motions for summary judgment.

On July 29, 2005, the Court denied a joint motion by the County and Scripps to intervene in the merits phase of the case, because the only issue before the Court was whether the Corps had lawfully issued the permit. Recognizing the practical and economic interests of the County and Scripps, however, the Court granted them status as Amici Curiae during the merits phase. The Court also granted the County and Scripps status as parties during any remedial phase in the litigation.

On September 26, 2005, the Court heard argument from Plaintiffs, the Corps and the County on the parties’ cross motions for summary judgment. By that time, the County had filled most the jurisdictional wetlands throughout the 535-acre site.

Free access — add to your briefcase to read the full text and ask questions with AI

Florida Wildlife Federation v. United States Army Corps of Engineers, 404 F. Supp. 2d 1352, 61 ERC (BNA) 1697, 2005 U.S. Dist. LEXIS 27356, 2005 WL 3418302 (S.D. Fla. 2005).

404 F. Supp. 2d 1352 (Florida Wildlife Federation v. United States Army Corps of Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New York v. Shinnecock Indian Nation
560 F. Supp. 2d 186 (E.D. New York, 2008)
Sierra Club v. Strock
495 F. Supp. 2d 1188 (S.D. Florida, 2007)
Sierra Club v. Flowers
423 F. Supp. 2d 1273 (S.D. Florida, 2006)