Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor. Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor

711 F.2d 219, 228 U.S. App. D.C. 433, 1983 U.S. App. LEXIS 26779
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 14, 1983
Docket82-1708
StatusPublished

This text of 711 F.2d 219 (Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor. Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor. Florida Power & Light Co. v. Federal Energy Regulatory Commission, Resources Recovery (Dade County), Inc., Intervenor, 711 F.2d 219, 228 U.S. App. D.C. 433, 1983 U.S. App. LEXIS 26779 (D.C. Cir. 1983).

Opinion

711 F.2d 219

228 U.S.App.D.C. 433

FLORIDA POWER & LIGHT CO., Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Resources Recovery (Dade County), Inc., Intervenor.
FLORIDA POWER & LIGHT CO., Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Resources Recovery (Dade County), Inc., Intervenor.

Nos. 82-1708, 82-1709.

United States Court of Appeals,
District of Columbia Circuit.

Argued April 19, 1983.
Decided June 14, 1983.

[228 U.S.App.D.C. 434] Petition for Review of Orders of the Federal Energy Regulatory commission.

J.A. Bouknight, Jr., Washington, D.C., with whom Jill E. Grant, Washington, D.C., was on the brief, for petitioner.

Robert F. Shapiro, Atty., F.E.R.C., Washington, D.C., for respondent.

Barbara J. Weller, Deputy Sol., F.E.R.C., Joanne Leveque and Michael Kessler, Attys., F.E.R.C., Washington, D.C., were on the brief, for respondent.

David J. Bardin, Lewis E. Leibowitz and Donald B. Mitchell, Jr., Washington, D.C., were on the brief, for intervenor.

Before EDWARDS, Circuit Judge, MacKINNON, Senior Circuit Judge, and FAIRCHILD,* Senior Circuit Judge, United States Court of Appeals for the Seventh Circuit.

Opinion for the Court filed by Senior Circuit Judge FAIRCHILD.

[228 U.S.App.D.C. 435] FAIRCHILD, Senior Circuit Judge:

Petitioner, Florida Power & Light Company ("FPL"), seeks review of orders by the Federal Energy Regulatory Commission ("the Commission") dismissing FPL's challenges to the self-qualification by Resources Recovery (Dade County), Inc. ("RRD") of a small power production facility and to its filing of initial energy rates for the facility under provisions of the Public Utility Regulatory Policies Act (PURPA). FPL contends that RRD's claims to qualifying status and resulting rate payments by FPL under PURPA conflict with "preexisting contractual arrangements which obligate RRD to surrender possession of the [facility] upon completion of construction and which entitle FPL to acquire the energy produced ... on terms specified by contract." Brief for Petitioner at 1-2. RRD's contractual obligations are currently the subject of state court proceedings. The Commission declined to consider FPL's challenges pending resolution of those proceedings. We affirm.

I.

Resource Recovery (Dade County) Construction Corporation ("RRDC") and Dade County, Florida entered into contracts which called on RRDC to construct facilities capable of producing steam from processed solid waste and generating electricity from the steam.1 On completion of construction, title to the waste processing facility and the electrical generating facility were to pass to the County. By contract between the County and FPL, title to the electrical generating facility was to be transfered to FPL. RRD was to operate the processing facility and sell steam to FPL at specified prices.

But contractual disputes arose between the County and RRDC during construction. The substance of these disputes was eventually referred to arbitration.2 Pending resolution RRDC continued to construct the facilities. On completion RRDC refused to transfer title and RRD assumed their operation.

On March 13, 1981 RRD filed a Notice of Qualification for a small power production facility. RRD's notice stated that it was the owner and operator of a resource recovery facility which met all the criteria necessary to satisfy the Commission's self-certification regulation for small power production facilities. See 18 C.F.R. § 292.207(a). This notice filing entitled RRD to specific benefits under PURPA. See 16 U.S.C. § 824a-3. Most importantly, it required electric utilities--in this case FPL--to purchase energy from the qualifying small power production facility at favorable rates. 16 U.S.C. §§ 824a-3(a)(2), 3(b). Following RRD's filing of a Notice of Qualification, it filed with the Commission a schedule of electric energy rates based on FPL's full avoided costs.3

[228 U.S.App.D.C. 436] FPL filed petitions with the Commission protesting RRD's notice and proposed rates. FPL argued that RRD's qualifying notice was inconsistent with its contractual obligations to relinquish ownership of the electric generating facility and to provide steam at agreed upon rates. FPL also asserted that the uncertainty of RRD's obligations required it to obtain a formal determination of its qualifying status pursuant to 18 C.F.R. § 292.207(b) rather than merely claim that status through the self-certification process under § 292.207(a). Finally, FPL argued that even if RRD is entitled to qualifying status, its proposed rates conflict with this court's decision in American Elec., Etc. v. Federal Energy Reg., 675 F.2d 1226 (D.C.Cir.1982), rev'd, --- U.S. ----, 103 S.Ct. 1921, 76 L.Ed.2d 22 (1983), and FPL's pending state court challenge to the valuation of FPL's full avoided costs. See note 3 supra.

In a series of orders, the Commission rejected each of these arguments. As to FPL's contention that RRD's qualification notice was inconsistent with its contractual obligations, the Commission declined "to sift through the competing claims of the parties to determine, under state contract law, who is the rightful owner or operator of the facility." Appendix at 4. The Commission ruled that these commercial issues "should be resolved in the state forum of competent jurisdiction." Id. On rehearing, the Commission stated:

[T]he issue of who owns the facility is currently being decided in a state forum of competent jurisdiction. Under the circumstances of this case, we are not inclined to interfere with the state court's consideration of state contract principles. FPL has the opportunity to seek revocation of RRD's qualifying status if the commercial dispute is resolved in its favor. In the interim, we perceive no irreparable harm accruing to FPL.

Id. at 9. The Commission also declined to upset RRD's § 292.207(a) self-certification on the basis of a "substantive commercial dispute," observing that FPL would have an opportunity to seek revocation of RRD's qualifying status when "the commercial dispute is resolved." Id. at 5.

As to RRD's rate filing, the Commission found the rates just and reasonable, and made them effective subject to possible refund in the event of a final adverse ruling in American Electric or state court proceedings.4 The Commission declined, on rehearing, to require a surety bond from RRD, indicating that such a requirement would be inappropriate where based principally upon a state-law contract dispute, and would, in any event, be contrary to traditional practice.

II.

By petition for review, FPL raises two principal objections to the Commission's refusal to disturb RRD's claim to self-qualifying status pursuant to § 292.207(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
711 F.2d 219, 228 U.S. App. D.C. 433, 1983 U.S. App. LEXIS 26779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-light-co-v-federal-energy-regulatory-commission-cadc-1983.