Flagg Energy Development Corp. v. General Motors Corp.

709 A.2d 1075, 244 Conn. 126, 35 U.C.C. Rep. Serv. 2d (West) 138, 1998 Conn. LEXIS 59
CourtSupreme Court of Connecticut
DecidedMarch 17, 1998
DocketSC 15611
StatusPublished
Cited by69 cases

This text of 709 A.2d 1075 (Flagg Energy Development Corp. v. General Motors Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flagg Energy Development Corp. v. General Motors Corp., 709 A.2d 1075, 244 Conn. 126, 35 U.C.C. Rep. Serv. 2d (West) 138, 1998 Conn. LEXIS 59 (Colo. 1998).

Opinion

[129]*129 Opinion

PETERS, J.

General Statutes § 42a-2-725,1 the statute of limitations contained in article 2 of the Uniform Commercial Code, establishes a four year time frame within which a buyer may bring a damages action for the sale of allegedly defective goods. Section 42a-2-725 (2) further specifies that a cause of action for breach of warranty accrues upon tender of delivery of the contract goods. The principal issue in this case is the applicability of § 42a-2-725 to a contract for the sale of goods in which the seller agrees not only to deliver the goods but also to perform testing of the goods at the buyer’s work site.

The plaintiffs, Flagg Energy Development Corporation (Flagg), CCF-1, Inc. (CCF-1), and Process Construction Services, Inc. (Process),2 brought an action claiming that the defendant, General Motors Corporation, Allison Gas Turbine Division,3 had delivered defective gas turbine engines for a construction project. [130]*130Because of losses allegedly suffered by the plaintiffs due to the failure of the engines to operate efficiently and economically, the plaintiffs claimed a right to recover compensatory and punitive damages, fees and costs. The defendant’s answer raised, as a special defense, the claim that the warranty counts of the plaintiffs’ complaint, filed October 26,1992, were time barred by the provisions of § 42a-2-725.

Although the major focus of the plaintiffs’ complaint was on the defendant’s alleged breaches of the express and implied warranties contained in their 1987 purchase agreement, the complaint also included a count for breach of contract and two counts charging Allison with misrepresentation and breach of the Connecticut Unfair Trade Practices Act (CUTPA). General Statutes § 42-110 (b).4 The trial court, Dorsey, J., granted the defendant’s motion to strike the latter two counts of the complaint.

The defendant filed a motion for summary judgment on the warranty counts, which the trial court, Gaffney, J., granted in part. The court concluded that Flagg and Process were not proper parties to this action and that CCF-l’s breach of warranty claims were time barred except for the allegation of breach of a promise for repair or replacement of defective material and equipment.

In motions to open and vacate the summary judgment, and to reargue, CCF-1 raised no question either about the accuracy of the facts described in the trial court’s memorandum of decision or about the suitability [131]*131of the case for summary disposition.5 Focusing only on the court’s ruling on the statute of limitations, CCF-1 claimed, for the first time, that a 1990 settlement agreement between the parties contained new promises that, as a matter of law, constituted a novation and thereby renewed the accrual of the statute of limitations. The court concluded that the text of the settlement agreement did not support the plaintiffs’ claim and, on that basis, denied CCF-l’s motion on its merits.6

CCF-1 then presented to a jury its damages claim pursuant to the repair or replacement clause in the purchase agreement. At the end of CCF-l’s presentation, the trial court, Gaffney, J., directed a verdict in favor of the defendant on the ground of evidentiary insufficiency.

After the trial court’s final judgment against them, the plaintiffs appealed to the Appellate Court.7 We transferred their appeal to this court pursuant to Practice Book § 40248 and General Statutes § 51-199 (c).9

In their appeal, the plaintiffs challenge the adverse pretrial and trial rulings of Judge Dorsey and Judge Gaffney. They have raised four issues. First, they argue that the breach of warranty claims contained in their [132]*132October, 1992 complaint were timely filed, within the four year § 42a-2-725 limitations period, because the purchasing agreement required the defendant to perform on-site testing that was not completed until November, 1988. Second, they contend that the 1990 settlement agreement was a novation that restarted the running of the limitations clock, either because it imposed new warranty obligations on the defendant, or because it supported the plaintiffs’ independent claim for breach of contract. Third, they maintain that the repair or replacement clause contained in the 1987 purchase agreement affords them an additional remedy for breach of warranty that extends the period of limitations. Fourth, they claim a right to recover damages for misrepresentation and breach of CUTPA.10 We are persuaded by none of these claims.11

I

THE 1987 PURCHASE AGREEMENT

We begin with an examination of the plaintiffs’ claim that, under the terms of their purchase agreement, their breach of warranty claims were filed properly within the four year limitation period contained in § 42a-2-725. The plaintiffs do not dispute that § 42a-2-725 (2) provides for the accrual of a cause of action for breach of warranty, “regardless of the aggrieved party’s lack of knowledge of the breach . . . when tender of delivery is made . . . .” They argue, however, that tender of delivery does not occur upon the physical delivery of the goods if, as in their case, a purchase agreement contains terms that postpone the tender of delivery. We disagree.

[133]*133The record discloses the following facts. As the trial court observed, although the parties draw differing legal conclusions from the history of their contractual relationship, the underlying relevant facts and documents are not at issue.12 On November 12, 1987, Sulzer Tur-bosystems, Inc. (Sulzer), and Process entered into a purchase agreement (1987 purchase agreement) for two gas turbine generator assemblies, including two engines manufactured by the defendant. Process needed the engines to power the generators required to fulfil its obligation to construct and operate a cogeneration power plant in Hartford. CCF-1 was the owner of the property on which the power plant was to be built. Soon after delivery of the engines, the plaintiffs voiced repeated complaints about their performance, and, on October 26, 1992, filed the present complaint.

The terms of the 1987 purchase agreement contained express and implied warranties as well as a clause requiring Sulzer, for a period of one year from the date of acceptance of the engines, to replace or to remedy defective materials or equipment.13 The agreement also obligated Sulzer to provide staff, at the plaintiffs’ construction site, to perform “check-out, start-up, [and] preliminary acceptance testing] . . . ,”14 Finally, the agreement provided that CCF-1 would pay for the goods “30 days after satisfactory completion of the Preliminary Acceptance Test, but not more than 60 days from date of delivery or 90 days from alternative due to [Sulzer] supply.”

[134]*134Sulzer physically delivered the engines to the construction site on May 27 and June 23,1988. Their installation was completed by July 26, 1988. The tests described in the purchase agreement, however, had not been performed by that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisa Earl v. NVR Inc
990 F.3d 310 (Third Circuit, 2021)
Tomey Realty Co. v. Bozzuto's, Inc.
147 A.3d 166 (Connecticut Appellate Court, 2016)
State v. Peeler
Supreme Court of Connecticut, 2016
Lawrence v. O & G Industries, Inc.
Supreme Court of Connecticut, 2015
Geremia v. Geremia
Connecticut Appellate Court, 2015
Fleming v. Government Employees Insurance
86 F. Supp. 3d 102 (D. Connecticut, 2015)
Davis v. Connecticut Community Bank, N.A.
937 F. Supp. 2d 217 (D. Connecticut, 2013)
Alarmax Distributors, Inc. v. New Canaan Alarm Co.
61 A.3d 1142 (Connecticut Appellate Court, 2013)
Levinson v. Westport National Bank
900 F. Supp. 2d 143 (D. Connecticut, 2012)
Association Resources, Inc. v. Wall
2 A.3d 873 (Supreme Court of Connecticut, 2010)
Haynes v. City of Middletown
997 A.2d 636 (Connecticut Appellate Court, 2010)
Cardinal Health 301, Inc. v. Tyco Electronics Corp.
169 Cal. App. 4th 116 (California Court of Appeal, 2008)
Somers v. Chan
955 A.2d 667 (Connecticut Appellate Court, 2008)
Trans-Spec Truck Service, Inc. v. Caterpillar Inc.
524 F.3d 315 (First Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
709 A.2d 1075, 244 Conn. 126, 35 U.C.C. Rep. Serv. 2d (West) 138, 1998 Conn. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flagg-energy-development-corp-v-general-motors-corp-conn-1998.