Duquesne Light Co. v. Westinghouse Electric Corp.

66 F.3d 604
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 12, 1995
DocketNos. 95-3027, 95-3045
StatusPublished
Cited by37 cases

This text of 66 F.3d 604 (Duquesne Light Co. v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duquesne Light Co. v. Westinghouse Electric Corp., 66 F.3d 604 (3d Cir. 1995).

Opinion

OPINION OF THE COURT

GREENBERG, Circuit Judge.

The plaintiffs appeal from judgments entered against them on all counts of their complaint. The district court granted the defendant summary judgment on certain of the plaintiffs’ counts and dismissed others by granting defendant’s motion made pursuant to Fed.R.Civ.P. 50(a) at the close of plaintiffs’ case. On the one remaining claim, the jury returned a verdict in favor of the defendant. Because we find no merit in the myriad of issues the plaintiffs raise, we will affirm the judgment and orders of the district court.

I. INTRODUCTION

The plaintiffs — Duquesne Light Company, The Cleveland Electric Illuminating Company, The Toledo Edison Company, Ohio Edison Company, and the Pennsylvania Power Company — together constructed and own the Beaver Valley Nuclear Power Station, a two-unit nuclear energy generating facility located near Pittsburgh, Pennsylvania. Du-quesne points out that it had primary responsibility for supervising the construction of the plant, and it now “operates the plant on behalf of the co-owners.” Br. at 5 n. 2. We therefore will refer to the plaintiffs singularly as Duquesne.

In the 1960’s, Duquesne issued a request for proposals and bid specifications for equipment to be used at the plant. Westinghouse submitted a proposal, and, after negotiations, entered into a contract with Duquesne under which it agreed to supply Nuclear Steam Supply Systems (NSSS) for the Beaver Valley units. It is beyond doubt that during these negotiations the parties had sophisticated technical, commercial, and legal advice. The parties executed the contracts for the units respectively on October 3, 1967, and January 5, 1972. Each NSSS contains a nuclear reactor, three steam generators, and a number of other components that together convert heat from nuclear fission into steam. The steam generators for the first unit were [608]*608installed in 1972; those for the second unit were installed in 1981. The units began commercial operations in, respectively, April 1977 and November 1987. Duquesne contends that when it negotiated the contracts, it sought steam generators that would last approximately 40 years and it points to facts that tend to support that contention. For instance the method of installing the NSSS equipment makes removing or replacing the steam generators extremely difficult.

In the 1980s, Duquesne discovered corrosion and cracking in the generators’ “U”shaped Inconel-made tubes through which radioactive water is pumped from the reactor vessel to the steam generators. Such corrosion and cracking affect both the plant’s power output and safety. Duquesne engaged experts to examine the rapid deterioration who concluded, among other things, that the tube material — Inconel 600 — made the equipment unusually susceptible to corrosion. Du-quesne ultimately determined that it would have to replace the steam generators.

On April 30, 1991, Duquesne filed this action against Westinghouse alleging breach of contract, breach of warranty, breach of the Uniform Commercial Code duty of good faith, fraud, negligent misrepresentation, and violations of the Racketeer Influenced and Corrupt Organizations Act, 18 U.S.C. § 1962(b) and (c). On December 1, 1993, Westinghouse filed a motion for summary judgment on all counts of the complaint. The district court referred the motion to a magistrate judge who issued a thorough and detañed report and recommendation on July 18,1994. In an order dated August 29,1994, the district court adopted (with modifications) the magistrate judge’s report and recommendation, and granted Westinghouse summary judgment on Duquesne’s negligent misrepresentation claim and on its claim under 18 U.S.C. § 1962(b). The court denied the motion in all other respects,1 and rejected Westinghouse’s argument that the various statutes of limitations and repose precluded Duquesne’s claims.

The case proceeded to trial on September 12, 1994. At the close of Duquesne’s case Westinghouse moved for judgment as a matter of law, and on October 24 the district court in a bench opinion granted that motion in most respects. It dismissed Duquesne’s claims of breach of contract, breach of warranty, breach of the duty of good faith and fair dealing, and violations of RICO. It also dismissed Duquesne’s claim for punitive damages. The court permitted Duquesne’s fraud claim, however, to go to the jury. On December 6, 1994, the jury returned a verdict in favor of Westinghouse on that claim. The court entered judgment on December 7, and Duquesne timely filed a notice of appeal.2 We have jurisdiction pursuant to 28 U.S.C. § 1291. Because of the RICO claim, the district court exercised subject matter jurisdiction under 18 U.S.C. § 1964(c) and 28 U.S.C. § 1331, and supplemental jurisdiction over the state law claims pursuant to 28 U.S.C. § 1367(a).3

II. DISCUSSION

A. The Verdict

1. The Trial Time Limitations

We begin with Duquesne’s attack on the jury verdict, since the jury’s findings impact on our analysis of the other claims. Duquesne’s primary argument challenging the verdict involves the district court’s allocation of trial time. During a pretrial conference, the parties and the court agreed to limit each side’s time to 140 hours, to include the sum of that party’s case, its cross-examination of the opposing party’s witnesses, and its opening and closing arguments. App. 87. [609]*609But on the 12th day of trial the court, frustrated with what it perceived as duplication of evidence, and concerned that the complicated technical testimony was confusing the jury, concluded that “all the business I have given you about 141 hours is off now.” App. 823.4 The court ruled that each side would receive 22 days to present its case. And since Duquesne already had used up 11 days, the court allowed it only an additional 11. App. 827-28. Furthermore, a “day” did not necessarily entail an entire day. Rather, as long as some testimony was heard on a given day, it counted as a full day. Duquesne argues that because it had budgeted its trial time during the first 11 days based on the 140 hour schedule, “[t]he district court’s unilateral change in the basic trial rules caused irreparable prejudice” to its case. Br. at 34. We review a district court’s decisions in its management of a trial for abuse of discretion. See Reed v. Philadelphia, Bethlehem & New England R.R. Co., 939 F.2d 128

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GridKor, LLC v. Gorbach
E.D. Pennsylvania, 2025
Osness v. Lasko Products, Inc.
868 F. Supp. 2d 402 (E.D. Pennsylvania, 2012)
De Lage Landen Financial Services, Inc. v. Rasa Floors, LP
792 F. Supp. 2d 812 (E.D. Pennsylvania, 2011)
Adelphia Recovery Trust v. Bank of America, N.A.
624 F. Supp. 2d 292 (S.D. New York, 2009)
Bucci v. Wachovia Bank, N.A.
591 F. Supp. 2d 773 (E.D. Pennsylvania, 2008)
Agrizap, Inc. v. Woodstream Corp.
450 F. Supp. 2d 562 (E.D. Pennsylvania, 2006)
GNC Franchising, Inc. v. O'BRIEN
443 F. Supp. 2d 737 (W.D. Pennsylvania, 2006)
Joy, Lynn A. v. Hay Group Inc
Seventh Circuit, 2005
Lynn A. Joy v. Hay Group, Inc.
403 F.3d 875 (Seventh Circuit, 2005)
Utica Mutual Insurance v. Vigo Coal Co.
393 F.3d 707 (Seventh Circuit, 2004)
Gaines v. Krawczyk
354 F. Supp. 2d 573 (W.D. Pennsylvania, 2004)
Bonson v. Diocese of Altoona-Johnstown
67 Pa. D. & C.4th 419 (Westmoreland County Court of Common Pleas, 2004)
PNC Bank v. Kerr
802 A.2d 634 (Superior Court of Pennsylvania, 2002)
Haymond v. Lundy
177 F. Supp. 2d 371 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
66 F.3d 604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duquesne-light-co-v-westinghouse-electric-corp-ca3-1995.