Fischbach-Natkin Co. v. Power Process Piping, Inc.

403 N.W.2d 569, 157 Mich. App. 448
CourtMichigan Court of Appeals
DecidedFebruary 2, 1987
DocketDocket 85272
StatusPublished
Cited by24 cases

This text of 403 N.W.2d 569 (Fischbach-Natkin Co. v. Power Process Piping, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fischbach-Natkin Co. v. Power Process Piping, Inc., 403 N.W.2d 569, 157 Mich. App. 448 (Mich. Ct. App. 1987).

Opinion

Beasley, P.J.

Defendant, Power Process Piping, Inc., appeals from an order granting summary judgment to plaintiff, Fischbach-Natkin Company, under GCR 1963, 117.2(3), now MCR 2.116(0(10). The summary judgment was granted under an indemnity provision contained in a subcontract between plaintiff, as general contractor, and defendant, as subcontractor, which provided:

Section 12. The Subcontractor [Power Process Piping, Inc.] agrees to and shall indemnify, protect, defend and save harmless Company [Fischbach-Natkin Company] from and against all liabil *451 ity or claimed liability for injuries, including death, to any and all persons whomsoever and for any and all property damage arising out of or resulting from or in any way connected with the work covered by this Subcontract or the operations or acts of commission or omission of the Subcontractor, his subcontractors, agents and employees.

This case arises from a serious industrial injury that occurred on January 10, 1980, in which William Green, an employee of defendant, was seriously injured when a heavy hydraulic machine tipped over on him during installation at a Ford Motor Company plant. On August 30, 1984, Green and his wife obtained a jury verdict in the amount of $488,000 against LaSalle Machine Tool Company, which had designed and manufactured the hydraulic machine, and plaintiff, who had been hired by Ford Motor Company as general contractor to assist in installation of the hydraulic machine. The jury decided that Green was twenty-five percent negligent under a comparative negligence instruction, thus reducing the amount of the verdict to $366,000. The jury decided that LaSalle Machine Tool Company was twenty-five percent negligent and Fischbach-Natkin Company fifty percent negligent.

Prior to the jury verdict, plaintiff had requested defendant to indemnify it and to assume defense of the claim under the indemnity provision referred to above. Defendant did not respond to this request, and plaintiff was not permitted to add defendant as a third-party defendant in the Green lawsuit, presumably because Green was collecting workers’ compensation benefits from defendant’s carrier. Plaintiff then filed the within case, claiming that there was no genuine issue of material fact and alleging a right to indemnification under Section 12 of the subcontract as a matter of law. *452 The trial judge agreed and granted summary judgment in favor of plaintiff and denied defendant’s similar motion for summary judgment in its favor.

On appeal, defendant raises three issues. First, defendant claims that the trial court erred in concluding that Section 12 of the subcontract provides that defendant is to indemnify plaintiff for plaintiffs own acts of negligence. In addressing this issue, we recognize that indemnity contracts are construed strictly against the party who drafts them and against the indemnitee. However, it is also true that indemnity contracts should be construed so as to give effect to the intentions of the parties. In ascertaining the intentions of the parties, one must consider not only the language used in the contract, but also the situation of the parties and circumstances surrounding the contract. 1

The additional rule of construction, imposed in earlier cases in this Court, 2 that indemnification contracts will not be considered to indemnify the indemnitee against losses from his own negligent acts unless such an intent is expressed in the contract language itself in clear and unequivocal terms, no longer applies. 3 This Court has concluded that broad, all-inclusive indemnification language may be interpreted to protect the indemnitee against its own negligence if such intent can be ascertained from other language in the contract, surrounding circumstances, or from the purpose sought to be accomplished by the parties. 4 Thus, although an indemnity provision does not ex *453 pressly state that the indemnitee will be shielded from its own negligence, such language is not mandatory to provide such indemnification. 5

In Paquin v Harnischfeger Corp, 6 the Court cited the general rules of construction as described above in addressing whether an indemnification clause which broadly protected the indemnitee from "all claims, loss, expense, damage and liability” provided protection to the indemnitee for its own negligence as a matter of law. In ascertaining the intention of the parties, the Paquin Court relied on two separate and independent reasons for finding that the parties intended that the indemnification provision would protect the indemnitee from liability caused by its own negligence. The Court first noted that the indemnification provision expressly provided that the indemnitee would not be protected if the injury or damage was caused by its sole negligence in order to avoid a violation of MCL 691.991; MSA 26.1146(1). The Paquin Court concluded that this limitation indicated an intent to provide indemnity in all situations involving the indemnitee’s own negligence except when the indemnitee’s negligence was the sole cause of the injury or damage. 7

The first basis relied on by the Paquin Court to find that the parties intended to indemnify the indemnitee for its own negligence does not apply in the within case, since no clause specifically excluding injuries or damages caused by plaintiff’s sole negligence is included in the indemnification provision involved herein. However, the Paquin Court went on to find that the situation of the parties and the circumstances surrounding the *454 contract also indicated that indemnification for the indemnitee’s own negligence was intended. The Paquin Court supported this conclusion by noting that it was understood at the time the contract was entered into that the employees of both the indemnitee and indemnitor would be working in the same area and that the use of a crane would be shared. Thus, the possibility that an injury or damage would result from the indemnitee’s negligence was apparent. In addition, the Paquin Court noted that the indemnitor was a substantial company with between twenty-five and one hundred employees and that the company officer in charge of preparing bids was familiar with this type of indemnification provision. 8

This second basis used by the Paquin Court to ascertain the intent of the parties to indemnify the indemnitee for his own negligence is directly applicable in this case. Section 3 of the contract between plaintiff and defendant, as well as addendum No. 1 of the contract, clearly indicate that all the work connected with installing the machine would not be performed by defendant, and that the employees of plaintiff and other subcontractors would be present at the common work area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

20230221_C359580_60_359580.Opn.Pdf
Michigan Court of Appeals, 2023
Curtis v. FCA US, LLC.
N.D. Illinois, 2019
James Provenzino v. County of MacOmb
Michigan Court of Appeals, 2017
Sa v. Red Frog Events, LLC
979 F. Supp. 2d 767 (E.D. Michigan, 2013)
James Fish v. Home Depot Usa, Incorporated
455 F. App'x 575 (Sixth Circuit, 2012)
Kirschenbaum v. Spraggins
752 F. Supp. 2d 728 (E.D. Louisiana, 2010)
Badiee v. Brighton Area Schools
695 N.W.2d 521 (Michigan Court of Appeals, 2005)
Thompson v. Budd Co.
199 F.3d 799 (Sixth Circuit, 1999)
Healey v. J.B. Sheet Metal, Inc.
892 P.2d 1047 (Court of Appeals of Utah, 1995)
Chrysler Corp. v. Skyline Industrial Services, Inc.
528 N.W.2d 698 (Michigan Supreme Court, 1995)
Msi Construction Managers, Inc v. Corvo Iron Works, Inc
527 N.W.2d 79 (Michigan Court of Appeals, 1995)
Sherman v. DeMaria Building Co.
513 N.W.2d 187 (Michigan Court of Appeals, 1994)
Paul v. Bogle
484 N.W.2d 728 (Michigan Court of Appeals, 1992)
Gruett v. Total Petroleum, Inc
451 N.W.2d 608 (Michigan Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
403 N.W.2d 569, 157 Mich. App. 448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fischbach-natkin-co-v-power-process-piping-inc-michctapp-1987.