Federal Insurance v. Turner Construction Co.

660 N.E.2d 127, 213 Ill. Dec. 870, 277 Ill. App. 3d 262
CourtAppellate Court of Illinois
DecidedDecember 28, 1995
Docket1-93-2593
StatusPublished
Cited by15 cases

This text of 660 N.E.2d 127 (Federal Insurance v. Turner Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Insurance v. Turner Construction Co., 660 N.E.2d 127, 213 Ill. Dec. 870, 277 Ill. App. 3d 262 (Ill. Ct. App. 1995).

Opinion

JUSTICE THEIS

delivered the opinion of the court:

The plaintiff, Federal Insurance Company (Federal), as subrogee of Midwest Stock Exchange (Midwest), appeals the trial court’s order granting summary judgment on counts XI, XII, XIII and XIV of their complaint. Federal sued defendants, Seseo, Inc. (Seseo), and Riggio Caulking Co., Inc. (Riggio), for water damage to Midwest’s computer system. Federal alleges that the damage was caused by a water pipe that ruptured due to defendants’ failure to complete exterior caulking in a timely fashion. The trial court granted defendants’ motion for summary judgment, finding that Federal failed to establish duty, proximate cause and its status as a third-party beneficiary to the construction contracts. On appeal, Federal argues that: (1) defendants owed duties in tort to Midwest; (2) Midwest was a third-party beneficiary of the defendants’ construction contracts; and (3) the trial court erred in considering the affidavit of defendant Sesco’s construction superintendent. We affirm.

On October 12, 1982, Exchange Center Corporation (Exchange) leased space in an unconstructed development to the Midwest Stock Exchange with an occupancy date deadline of April 1,1985. Exchange then contracted with Continental / Turner for the construction of this new development at One Financial Place in Chicago, Illinois. The development included a multistory office tower and an annex to the Midwest Stock Exchange. The annex provided Midwest, the anchor tenant, with a new trading floor.

Pursuant to a subcontracting agreement, Seseo was to perform all work and provide all material for the erection of the development’s exterior granite walls. In November of 1983, Seseo entered into a subcontracting agreement with Riggio, whereby Riggio was to provide and install the sealant between the exterior granite blocks of the structure’s exterior facade. As such, Riggio was responsible for cleaning the joints between the granite blocks, installing a backer rod for the caulking and caulking the joints themselves.

Riggio began its caulking work in August of 1984. Dissatisfied with the speed of Riggio’s work, Seseo wrote to Riggio on October 5, 1984, concerning the necessity of completing the work. On November 22, 1984, the project architect, Skidmore, Owings & Merrill, drafted correspondence to the City of Chicago certifying that the building was suitable for tenant occupancy. On November 23, 1984, however, Riggio responded to Sesco’s concerns indicating that the structure would not be sealed and caulked until December 22, 1984.

The record indicates that the owner and general contractor were aware of Riggio’s performance. The architects wrote letters to the owner and general contractor expressing their concerns over the effects of the cold on the construction site. The building manager stated in his deposition that city inspectors expressed similar concerns upon their inspections of the building.

Despite this, Midwest was permitted to move into the building in mid-December. Specifically, Midwest moved an expensive computer system into the fourth floor of the Tower. There is no evidence in the record that Midwest, the owner or general contractor ever notified defendants that Midwest or any other tenant would be moving in at that time. The contracts between Riggio and Seseo and Seseo and Continental/Turner did not require completion of the insulation by December 25, 1984.

On December 25, 1984, a water supply line leading to a fifth-floor sink located immediately adjacent to the exterior east elevation froze and ruptured. In addition, three sprinkler heads activated on the seventh floor of the building. Water allegedly pouring from the ruptured waterline penetrated the floor and caused substantial damage to Midwest’s computer system below.

Michael Dust, Continental’s building manager, determined that the rupture was due to the lack of caulking on the east exterior wall behind the sink. Riggio conceded that the east elevation was not completely caulked and weather sealed as of December 25, 1984.

Federal paid its insured, Midwest, approximately $1 million to replace the damaged computer system. The terms of Midwest’s insurance policy provide that Federal is subrogated to the rights of Midwest. In addition to suing the owner, general contractor and other subcontractors for damages, Federal sued Seseo and Riggio for the damage to the computer system.

In counts XI and XIII, Federal claimed that defendants negligently performed the caulking work which was the proximate cause of the computer damage. In counts XII and XIV, Federal claimed that it could recover in contract as a third-party beneficiary to the construction subcontracting agreements. The trial court granted defendants’ motions for summary judgment as to counts XI and XIII, finding that Federal failed to establish that defendants owed Midwest a duty to complete the structure by December 25,1984. Alternatively, the court held that Federal failed to establish proximate cause. Similarly, the court granted summary judgment as to counts XII and XIV, holding that Federal was not a third-party beneficiary to the subcontracting agreements. In its motion for reconsideration, Federal abandoned its claim that the damage resulted from defendants’ improper workmanship, claiming instead that the damage was caused by defendants’ failure to complete the job in a timely fashion. The court denied Federal’s motion.

On appeal, Federal argues that: (1) the defendants owed duties in tort to Midwest; (2) Midwest was a third-party beneficiary of the defendants’ construction contracts; and (3) the trial court erred in considering the affidavit of defendant Sesco’s construction superintendent. For the reasons set forth below, we affirm.

Motions for summary judgment are reviewed under a de novo standard. (Myers v. Health Specialists, S.C. (1992), 225 Ill. App. 3d 68, 587 N.E.2d 494.) As such, this court is not bound by the trial court’s reasons for the entry of summary judgment and may affirm on other grounds. (Board of Directors of Olde Salem Homeowners’ Association v. Secretary of Veterans Affairs (1992), 226 Ill. App. 3d 281, 589 N.E.2d 761.) Because this appeal is before the court on defendants’ motions for summary judgment, all reasonable inferences will be drawn in Federal’s favor.

Federal claims that both Riggio and Seseo owed duties in tort to Midwest, not contingent upon privity of contract. Federal argues that defendants breached their duty to Midwest to perform in a good and workmanlike fashion by failing to complete their work prior to the accident. Federal claims that this court’s decision in Electronics Group, Inc. v. Central Roofing Co. (1987), 164 Ill. App. 3d 915, 518 N.E.2d 369, is dispositive of the issue before us.

In Electronics Group, the court stated that a roofing contractor who completed his work in a negligent manner was liable to the tenants for water damage caused by the leaking roof. (Electronics Group, Inc., 164 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Potek v. City of Chicago
2026 IL App (1st) 250158 (Appellate Court of Illinois, 2026)
Bledsoe v. FCA US LLC
E.D. Michigan, 2023
Biefeldt v. Wilson
2022 IL App (1st) 210336 (Appellate Court of Illinois, 2022)
Harleysville Insurance Co. v. Mohr Architecture, Inc.
2021 IL App (1st) 192427-U (Appellate Court of Illinois, 2021)
Wade v. Stewart Title Guaranty Co.
2017 IL App (1st) 161765 (Appellate Court of Illinois, 2017)
Wade v. Stewart Title Guaranty Company
2017 IL App (1st) 161765 (Appellate Court of Illinois, 2017)
Advanced Concepts Chicago, Inc. v. CDW Corp.
938 N.E.2d 577 (Appellate Court of Illinois, 2010)
Martis v. Grinnell Mutual Reinsurance Co.
905 N.E.2d 920 (Appellate Court of Illinois, 2009)
Hall v. National Collegiate Athletic Ass'n
985 F. Supp. 782 (N.D. Illinois, 1997)
Selvy v. Beigel
Appellate Court of Illinois, 1996

Cite This Page — Counsel Stack

Bluebook (online)
660 N.E.2d 127, 213 Ill. Dec. 870, 277 Ill. App. 3d 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-insurance-v-turner-construction-co-illappct-1995.