Advanced Concepts Chicago, Inc. v. CDW Corporation

Appellate Court of Illinois·Decided November 4, 2010·No. 1-09-3563 Rel·Published

Opinion

FOURTH DIVISION

November 4, 2010

No. 1-09-3563

ADVANCED CONCEPTS CHICAGO, INC., an ) Appeal from the Illinois Corporation, ) Circuit Court of ) Cook County

Plaintiff-Appellant, )

) No. 09 L 001244

v. )

) Honorable

CDW CORPORATION, an Illinois Corporation, ) Allen Goldberg, ) Judge Presiding.

Defendant-Appellee. )

PRESIDING JUSTICE GALLAGHER delivered the opinion of the court:

Plaintiff-appellant, Advanced Concepts Chicago, Inc. (Advanced), filed a complaint against defendant-appellee CDW Corporation (CDW) to recover damages as a third-party beneficiary to a contract between McCormick West Constructors, LLC (McCormick), and Berbee Information Networks (Berbee). CDW later acquired Berbee. The contract required Berbee to retain a certified minority business enterprise (MBE) to complete 40% of a computer installation project and Advanced was listed as the MBE in a schedule attached to the contract. The complaint alleged that Berbee submitted affidavits to McCormick as required by the schedule, representing that Advanced had provided materials and/or labor and had received payment according to the schedule. The complaint further alleged that Berbee breached its contract with McCormick because it never entered into a contractual agreement with Advanced and never made any payments to Advanced. CDW filed a motion to dismiss the complaint for

failure to state a cause of action pursuant to section 2-615 of the Illinois Code of Civil Procedure (Code) (735 ILCS 5/2-615 (West 2008)). The trial court granted the motion and denied Advanced’s motion to reconsider. On appeal, Advanced contends that the trial court erred in finding that the complaint failed to allege facts sufficient to state a cause of action for relief as a third-party beneficiary of the McCormick-Berbee contract because: (1) Advanced was to be the direct recipient of the benefit of the affirmative action requirement provisions of the contract, (2) a third-party subcontractor can enforce the contractual promise to use its services, (3) payment monitoring provisions provide additional evidence of an intent to directly benefit a third party, and (4) the trial court employed an erroneous third-party beneficiary analysis. For the reasons that follow, we reverse and remand.

BACKGROUND

On February 2, 2009, Advanced filed a complaint against CDW in the circuit court of Cook County, alleging that CDW was the successor to the business, rights and obligations of Berbee. The complaint further alleged that in January 2007, Berbee entered into a contract with McCormick to supply computer equipment for the McCormick Place West expansion project. A copy of the contract was attached to the complaint. The complaint alleged that Berbee breached its acknowledged obligations under the contract when it failed to enter into a contractual agreement with Advanced for the provision of services related to the project and did not pay any of the proceeds to Advanced.

In the contract between Berbee and McCormick, the scope of work is detailed in Exhibit B, and the affirmative action participation requirements are detailed in Exhibit G. Item (2)(f) in

Exhibit B provides: “Supplier to retain a ‘certified’ Minority Business Enterprise (MBE) for 40% of Cisco Computer Equipment. See Attached Exhibit G.” Item (2) in Exhibit G lists 40% as the MBE “trade-by-trade goal” and contains a reference to the “Schedule A Subcontracting Plan MBE/WBE Participation” that was to be returned with the subcontractor’s bid form. Schedule A lists Berbee as the subcontractor and contains a table for listing “sub subcontractors” which includes one entry: Advanced Concepts Chicago, Inc. “Computer equipment” is listed in the “scope of services” column. The total contract amount of $2,042,722.66 appears at the top of the table and the targeted amount shown for Advanced is $817,089.06. Schedule A further provides: “The undersigned will enter into a formal agreement with MBE/WBEs for work listed in this Schedule conditioned upon the award of a contract by [McCormick].” Finally, Schedule A provides: “In addition to the monthly report, you must submit a status report of payments to MBE/WBE subcontractors indicating the amount of payments made.”

The complaint further alleged that Berbee submitted two affidavits to McCormick in which it represented that it was sharing 40% of the monies paid by McCormick with Advanced. The affidavits were attached to the complaint. The affidavits state: “[T]he following are the names of all parties who have furnished materials or labor, or both for said work and all parties having contracts for specific portions of said work or for material entering into the construction thereof and the amount due or to become due to each.” The first affidavit is dated May 4, 2007, and lists two parties, Berbee and Advanced. It states that of the $919,225 payment Berbee received from McCormick, Berbee was paid $577,152 and Advanced was paid $342,073. The second affidavit is dated May 17, 2007, and again lists Berbee and Advanced, stating that of the

$908,197 payment Berbee received from McCormick, Berbee was paid $570,227.75 and Advanced was paid $337,969.25. The affidavit also shows that Advanced was owed an additional $137,046.80 of the total balance due on the project of $368,274.26 from McCormick.

The complaint alleged that for the duration of the time period covered by the contract, Advanced remained ready, willing and able to enter into an agreement with Berbee to provide configuration and installation services for computer equipment in the McCormick expansion project. The complaint further alleged that in breach of its obligations under the contract, Berbee did not enter into a contractual agreement with Advanced and did not pay any of the proceeds it received under the contract to Advanced. As a named third-party beneficiary, Advanced sought direct recovery of its damages for Berbee’s breach.

CDW filed a motion to dismiss under section 2-615 of the Code (735 ILCS 5/2-615 (West 2008)) for failure to state a cause of action. CDW argued that Advanced was not a third- party beneficiary because the contract was not entered into expressly for the benefit of Advanced, nor did the contract contain any language indicating an intent of the parties to make Advanced a third-party beneficiary. CDW further contended that the purpose behind the MBE provision in the contract was to contribute to McCormick’s affirmative action plan and not to confer a specific benefit on Advanced; thus, Advanced was, at best, an incidental beneficiary to the contract.

The trial court granted CDW’s motion to dismiss with prejudice, holding that: (1)

Advanced failed to allege facts showing that the parties entered into the contract for the purpose of directly benefitting Advanced, (2) the unambiguous terms of the contract establish that the

parties did not intend to benefit Advanced directly, and (3) the MBE provision was included to contribute to McCormick’s affirmative action plans and was thus incidental to the parties’ purpose of benefitting each other. The trial court denied Advanced’s motion to reconsider. This appeal follows.

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Advanced Concepts Chicago, Inc. v. CDW Corporation, (Ill. Ct. App. 2010).

Advanced Concepts Chicago, Inc. v. CDW Corporation (Advanced Concepts Chicago, Inc. v. CDW Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

XL Disposal Corp. v. John Sexton Contractors Co.
659 N.E.2d 1312 (Illinois Supreme Court, 1995)
Federal Insurance v. Turner Construction Co.
660 N.E.2d 127 (Appellate Court of Illinois, 1995)
155 Harbor Drive Condominium Ass'n v. Harbor Point Inc.
568 N.E.2d 365 (Appellate Court of Illinois, 1991)
Ball Corp. v. Bohlin Building Corp.
543 N.E.2d 106 (Appellate Court of Illinois, 1989)
Canel v. Topinka
818 N.E.2d 311 (Illinois Supreme Court, 2004)
Bates & Rogers Construction Corp. v. Greeley & Hansen
486 N.E.2d 902 (Illinois Supreme Court, 1985)
Altevogt v. Brinkoetter
421 N.E.2d 182 (Illinois Supreme Court, 1981)
Town & Country Bank v. James M. Canfield Contracting Co.
370 N.E.2d 630 (Appellate Court of Illinois, 1977)
Carson Pirie Scott & Co. v. Parrett
178 N.E. 498 (Illinois Supreme Court, 1931)
Gillespie v. Chrysler Motors Corp.
532 N.E.2d 875 (Appellate Court of Illinois, 1988)
Barney v. Unity Paving, Inc.
639 N.E.2d 592 (Appellate Court of Illinois, 1994)