Advanced Concepts Chicago, Inc. v. CDW Corporation

CourtAppellate Court of Illinois
DecidedNovember 4, 2010
Docket1-09-3563 Rel
StatusPublished

This text of Advanced Concepts Chicago, Inc. v. CDW Corporation (Advanced Concepts Chicago, Inc. v. CDW Corporation) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Concepts Chicago, Inc. v. CDW Corporation, (Ill. Ct. App. 2010).

Opinion

FOURTH DIVISION November 4, 2010

No. 1-09-3563

ADVANCED CONCEPTS CHICAGO, INC., an ) Appeal from the Illinois Corporation, ) Circuit Court of ) Cook County Plaintiff-Appellant, ) ) No. 09 L 001244 v. ) ) Honorable CDW CORPORATION, an Illinois Corporation, ) Allen Goldberg, ) Judge Presiding. Defendant-Appellee. )

PRESIDING JUSTICE GALLAGHER delivered the opinion of the court:

Plaintiff-appellant, Advanced Concepts Chicago, Inc. (Advanced), filed a complaint

against defendant-appellee CDW Corporation (CDW) to recover damages as a third-party

beneficiary to a contract between McCormick West Constructors, LLC (McCormick), and

Berbee Information Networks (Berbee). CDW later acquired Berbee. The contract required

Berbee to retain a certified minority business enterprise (MBE) to complete 40% of a computer

installation project and Advanced was listed as the MBE in a schedule attached to the contract.

The complaint alleged that Berbee submitted affidavits to McCormick as required by the

schedule, representing that Advanced had provided materials and/or labor and had received

payment according to the schedule. The complaint further alleged that Berbee breached its

contract with McCormick because it never entered into a contractual agreement with Advanced

and never made any payments to Advanced. CDW filed a motion to dismiss the complaint for 1-09-3563

failure to state a cause of action pursuant to section 2-615 of the Illinois Code of Civil Procedure

(Code) (735 ILCS 5/2-615 (West 2008)). The trial court granted the motion and denied

Advanced’s motion to reconsider. On appeal, Advanced contends that the trial court erred in

finding that the complaint failed to allege facts sufficient to state a cause of action for relief as a

third-party beneficiary of the McCormick-Berbee contract because: (1) Advanced was to be the

direct recipient of the benefit of the affirmative action requirement provisions of the contract, (2)

a third-party subcontractor can enforce the contractual promise to use its services, (3) payment

monitoring provisions provide additional evidence of an intent to directly benefit a third party,

and (4) the trial court employed an erroneous third-party beneficiary analysis. For the reasons

that follow, we reverse and remand.

BACKGROUND

On February 2, 2009, Advanced filed a complaint against CDW in the circuit court of

Cook County, alleging that CDW was the successor to the business, rights and obligations of

Berbee. The complaint further alleged that in January 2007, Berbee entered into a contract with

McCormick to supply computer equipment for the McCormick Place West expansion project. A

copy of the contract was attached to the complaint. The complaint alleged that Berbee breached

its acknowledged obligations under the contract when it failed to enter into a contractual

agreement with Advanced for the provision of services related to the project and did not pay any

of the proceeds to Advanced.

In the contract between Berbee and McCormick, the scope of work is detailed in Exhibit

B, and the affirmative action participation requirements are detailed in Exhibit G. Item (2)(f) in

2 1-09-3563

Exhibit B provides: “Supplier to retain a ‘certified’ Minority Business Enterprise (MBE) for 40%

of Cisco Computer Equipment. See Attached Exhibit G.” Item (2) in Exhibit G lists 40% as the

MBE “trade-by-trade goal” and contains a reference to the “Schedule A Subcontracting Plan

MBE/WBE Participation” that was to be returned with the subcontractor’s bid form. Schedule A

lists Berbee as the subcontractor and contains a table for listing “sub subcontractors” which

includes one entry: Advanced Concepts Chicago, Inc. “Computer equipment” is listed in the

“scope of services” column. The total contract amount of $2,042,722.66 appears at the top of the

table and the targeted amount shown for Advanced is $817,089.06. Schedule A further provides:

“The undersigned will enter into a formal agreement with MBE/WBEs for work listed in this

Schedule conditioned upon the award of a contract by [McCormick].” Finally, Schedule A

provides: “In addition to the monthly report, you must submit a status report of payments to

MBE/WBE subcontractors indicating the amount of payments made.”

The complaint further alleged that Berbee submitted two affidavits to McCormick in

which it represented that it was sharing 40% of the monies paid by McCormick with Advanced.

The affidavits were attached to the complaint. The affidavits state: “[T]he following are the

names of all parties who have furnished materials or labor, or both for said work and all parties

having contracts for specific portions of said work or for material entering into the construction

thereof and the amount due or to become due to each.” The first affidavit is dated May 4, 2007,

and lists two parties, Berbee and Advanced. It states that of the $919,225 payment Berbee

received from McCormick, Berbee was paid $577,152 and Advanced was paid $342,073. The

second affidavit is dated May 17, 2007, and again lists Berbee and Advanced, stating that of the

3 1-09-3563

$908,197 payment Berbee received from McCormick, Berbee was paid $570,227.75 and

Advanced was paid $337,969.25. The affidavit also shows that Advanced was owed an

additional $137,046.80 of the total balance due on the project of $368,274.26 from McCormick.

The complaint alleged that for the duration of the time period covered by the contract,

Advanced remained ready, willing and able to enter into an agreement with Berbee to provide

configuration and installation services for computer equipment in the McCormick expansion

project. The complaint further alleged that in breach of its obligations under the contract, Berbee

did not enter into a contractual agreement with Advanced and did not pay any of the proceeds it

received under the contract to Advanced. As a named third-party beneficiary, Advanced sought

direct recovery of its damages for Berbee’s breach.

CDW filed a motion to dismiss under section 2-615 of the Code (735 ILCS 5/2-615

(West 2008)) for failure to state a cause of action. CDW argued that Advanced was not a third-

party beneficiary because the contract was not entered into expressly for the benefit of Advanced,

nor did the contract contain any language indicating an intent of the parties to make Advanced a

third-party beneficiary. CDW further contended that the purpose behind the MBE provision in

the contract was to contribute to McCormick’s affirmative action plan and not to confer a

specific benefit on Advanced; thus, Advanced was, at best, an incidental beneficiary to the

contract.

The trial court granted CDW’s motion to dismiss with prejudice, holding that: (1)

Advanced failed to allege facts showing that the parties entered into the contract for the purpose

of directly benefitting Advanced, (2) the unambiguous terms of the contract establish that the

4 1-09-3563

parties did not intend to benefit Advanced directly, and (3) the MBE provision was included to

contribute to McCormick’s affirmative action plans and was thus incidental to the parties’

purpose of benefitting each other. The trial court denied Advanced’s motion to reconsider. This

appeal follows.

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Disposal Corp. v. John Sexton Contractors Co.
659 N.E.2d 1312 (Illinois Supreme Court, 1995)
Federal Insurance v. Turner Construction Co.
660 N.E.2d 127 (Appellate Court of Illinois, 1995)
155 Harbor Drive Condominium Ass'n v. Harbor Point Inc.
568 N.E.2d 365 (Appellate Court of Illinois, 1991)
Ball Corp. v. Bohlin Building Corp.
543 N.E.2d 106 (Appellate Court of Illinois, 1989)
Canel v. Topinka
818 N.E.2d 311 (Illinois Supreme Court, 2004)
Bates & Rogers Construction Corp. v. Greeley & Hansen
486 N.E.2d 902 (Illinois Supreme Court, 1985)
Altevogt v. Brinkoetter
421 N.E.2d 182 (Illinois Supreme Court, 1981)
Town & Country Bank v. James M. Canfield Contracting Co.
370 N.E.2d 630 (Appellate Court of Illinois, 1977)
Carson Pirie Scott & Co. v. Parrett
178 N.E. 498 (Illinois Supreme Court, 1931)
Gillespie v. Chrysler Motors Corp.
532 N.E.2d 875 (Appellate Court of Illinois, 1988)
Barney v. Unity Paving, Inc.
639 N.E.2d 592 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Advanced Concepts Chicago, Inc. v. CDW Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-concepts-chicago-inc-v-cdw-corporation-illappct-2010.