Ball Corp. v. Bohlin Building Corp.

543 N.E.2d 106, 187 Ill. App. 3d 175, 134 Ill. Dec. 823, 1989 Ill. App. LEXIS 811
CourtAppellate Court of Illinois
DecidedJune 5, 1989
Docket1-88-0387
StatusPublished
Cited by54 cases

This text of 543 N.E.2d 106 (Ball Corp. v. Bohlin Building Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ball Corp. v. Bohlin Building Corp., 543 N.E.2d 106, 187 Ill. App. 3d 175, 134 Ill. Dec. 823, 1989 Ill. App. LEXIS 811 (Ill. Ct. App. 1989).

Opinion

JUSTICE CAMPBELL

delivered the opinion of the court:

This appeal and cross-appeal arise from damages incurred by plaintiff, Ball Corporation, to portions of its warehouse roof as the result of a windstorm on April 5, 1979. On March 18, 1982, Ball filed a complaint against defendants, Bohlin Building Corporation, general contractor for the 1973 and 1977 roof additions to Ball’s warehouse; Dexter-Mook Roofing Sheet Metal Works, Inc., the roofing subcontractor for the 1977 addition; and Boice Roofing Company, the roofing subcontractor for the 1974 addition, alleging that each defendant had been careless and negligent. Subsequently, on March 12, 1986, Ball filed an amended complaint, adding breach of contract counts predicated on a third-party beneficiary theory against Boice and DexterMook and breach of contract and breach of implied warranty counts against Bohlin. The trial court denied motions for summary judgment filed by Bohlin, Boice and Dexter-Mook. Following a jury trial, the trial court directed a verdict in favor of defendants on the negligence counts and the jury found for Ball and against all defendants on the contract counts, assessing damages in the amount of $104,913.65. Bohlin was found liable for 20% of the damages, Boice for 50% and Dexter-Mook for 30%. Boice’s post-trial motions were denied.

On appeal, Boice, sole appellant, contends that the trial court erred in finding that Ball was a third-party beneficiary to the contract between Bohlin, general contractor, and Boice, subcontractor. On cross-appeal, Ball contends that the trial court erred in directing a verdict in favor of Boice on the negligence count. For the following reasons, we reverse the trial court’s judgment as to the contract count and affirm the trial court’s judgment entering a directed verdict in Boice’s favor as to the negligence count.

With respect to the contract count, Ball contends that it is entitled to damages as a third-party beneficiary to the contract between Bohlin and Boice. In response, Boice argues that the clear and unambiguous terms of the Ball-Bohlin contract, expressly incorporated into the Bohlin-Boice contract, state that Ball has no contractual relationship with any subcontractor, including Boice.

Pursuant to Illinois law, there is a strong presumption that parties to a contract intend that the contract’s provisions apply to only them and not to third parties. In order to overcome that presumption, the implication that the contract applies to third parties must be so strong as to be practically an express declaration. (Alaniz v. Schal Associates (1988), 175 Ill. App. 3d 310, 529 N.E.2d 832.) It is the intention of the parties as evidenced by the contract that determines whether another is a third-party beneficiary. It is not enough that the beneficiary is an incidental beneficiary, i.e., that the third party will reap incidental benefits from the contract. Only a direct beneficiary has a right against the promisor or promisee. (People ex rel. Resnik v. Curtis & Davis, Architects & Planners, Inc. (1980), 78 Ill. 2d 381, 400 N.E.2d 918.) A third party is a direct rather than an incidental beneficiary when the contracting parties have manifested in their contract an intention to confer a benefit upon the third party. (Altevogt v. Brinkoetter (1981), 85 Ill. 2d 44, 421 N.E.2d 182; Santucci Construction Co. v. Baxter & Woodman, Inc. (1986), 151 Ill. App. 3d 547, 502 N.E.2d 1134.) Liability to a third-party must affirmatively appear from the contract’s language and from the circumstances surrounding the parties at the time of its execution, and cannot be expanded or enlarged simply because the situation and circumstances justify or demand further or other liability. Carson Pirie Scott & Co. v. Parrett (1931), 346 Ill. 252, 178 N.E.2d 498; Midwest Concrete Products Co. v. La Salle National Bank (1981), 94 Ill. App. 3d 394, 418 N.E.2d 988.

In the present case, the contract between Ball, the owner, and Bohlin, the general contractor, included the following specifications drafted by Ball:

“1-5 CONTRACTOR
Only one Contractor will be recognized as the other party in any specific contract, and this Contractor shall be held responsible as prime Contractor for the proper fittings of all work and for the coordination of all his tradesmen, subcontractors, materialmen, or suppliers engaged upon his part of the work. He shall also be fully and solely responsible to the Engineer for the acts or omissions of his men, his subcontractors, and of persons either directly or indirectly employed by his subcontractors or supplying materials or supplies to him or his subcontractors.
1-6 SUBCONTRACTORS
All portions of the work that the Contractor’s organization has not been accustomed to perform or that the Owner may approve shall be executed under separate subcontracts let by the Contractor.
The Contractor, being fully responsible for the work shall have full directing authority over the execution of the subcontracts under his general contract.
The Contractor shall notify the Owner in writing, the name of subcontractors and suppliers proposed for parts of his work not performed by himself, and for such other parts as the Owner may request. The Owner reserves the right of approval of all subcontractors.
Nothing contained in the contract documents shall create any contractual relation between any subcontractor and the Owner.
The subcontractor, however, under specific requirements of his contract with a prime contractor, shall be responsible through the contractor with whom he has a contract for his work, and wherever required by the specifications shall guarantee his work for a specified period of time.”

The above-stated specifications were, inter alia, expressly incorporated into the contract between Bohlin and Boice, the subcontractor. Accordingly, the Bohlin-Boice contract specifically provided that there was to be no contractual relationship between Ball, the owner, and Boice, the subcontractor. Rather, Boice’s sole contractual relationship was to be with Bohlin.

As previously stated, it is well established that in determining third-party beneficiary status, the contract is controlling. (Carson Pirie Scott & Co. v. Parrett (1931), 346 Ill. 252, 178 N.E.2d 498; People ex rel. Resnik v. Curtis & Davis, Architects & Planners, Inc. (1980), 78 Ill. 2d 381, 400 N.E.2d 918; Altevogt v. Brinkoetter (1981), 85 Ill. 2d 44, 421 N.E.2d 182

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington v. Persona Identities, Inc.
2024 IL App (3d) 240210 (Appellate Court of Illinois, 2024)
Alex Coatney v. Ancestry.com DNA, LLC
93 F.4th 1014 (Seventh Circuit, 2024)
Equipment Leasing Group of America, LLC v. MCG Cane Bay, LLC
2024 IL App (1st) 231143-U (Appellate Court of Illinois, 2024)
Zurich American Insurance Co. v. Infrastructure Engineering, Inc.
2023 IL App (1st) 230147-U (Appellate Court of Illinois, 2023)
Snyder v. Jack Schmitt Ford, Inc.
2022 IL App (5th) 210413-U (Appellate Court of Illinois, 2022)
Harleysville Insurance Co. v. Mohr Architecture, Inc.
2021 IL App (1st) 192427-U (Appellate Court of Illinois, 2021)
Raab v. Frank
2019 IL App (2d) 171040 (Appellate Court of Illinois, 2019)
Carlson v. The Rehabilitation Institute of Chicago
2016 IL App (1st) 143853 (Appellate Court of Illinois, 2016)
Cohn v. Guaranteed Rate Inc.
130 F. Supp. 3d 1198 (N.D. Illinois, 2015)
Guerrette v. Dyer
Maine Superior, 2014
Advanced Concepts Chicago, Inc. v. CDW Corp.
938 N.E.2d 577 (Appellate Court of Illinois, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
543 N.E.2d 106, 187 Ill. App. 3d 175, 134 Ill. Dec. 823, 1989 Ill. App. LEXIS 811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ball-corp-v-bohlin-building-corp-illappct-1989.