Equipment Leasing Group of America, LLC v. MCG Cane Bay, LLC

2024 IL App (1st) 231143-U
Appellate Court of Illinois·Decided January 18, 2024·No. 1-23-1143·Unpublished

Opinion

2024 IL App (1st) 231143-U

FOURTH DIVISION

Order filed: January 18, 2024

No. 1-23-1143

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT

EQUIPMENT LEASING GROUP OF AMERICA, LLC, ) Appeal from the ) Circuit Court of

Plaintiff-Appellant, ) Cook County.

)

v. ) No. 21 L 7920 )

MCG CANE BAY, LLC, BOMA, L.C., and BMB ) INVESTMENTS, LLC, ) Honorable ) Jerry Esrig,

Defendants-Appellees. ) Judge, presiding.

JUSTICE HOFFMAN delivered the judgment of the court.

Presiding Justice Rochford and Justice Ocasio III concurred in the judgment.

ORDER

¶1 Held: Lessor was not entitled to damages for lessee’s breach of contract when the lessor profited more from the breach than it would have had the contract been fully performed, and lessor was also not entitled to damages for lost depreciation tax deductions because lessor is an LLC that does not pay income taxes and, therefore, does not claim tax deductions.

¶2 In this appeal from a breach-of-contract action concerning a commercial equipment lease, plaintiff-lessor Equipment Leasing Group of America, LLC (“ELGA”), appeals a final judgment in favor of defendant-lessee MCG Cane Bay, LLC (“MCG”), and defendants-guarantors BOMA,

L.C. (“BOMA”), and BMB Investments, LLC (“BMB” and, together with BOMA, “Guarantors”). ELGA contends that the circuit court erred in concluding that it was not entitled to damages for MCG’s breach of a lease agreement on the grounds that ELGA had profited more from the breach than it would have from full performance of the contract and that ELGA was not entitled to damages for its alleged loss of a depreciation tax deduction for the leased equipment because ELGA is not a tax-paying entity. We affirm the circuit court’s judgment.

¶3 On December 30, 2015, ELGA and MCG entered into a contract (“the Lease” or “Lease 1”) providing that ELGA would purchase certain equipment to be leased by MCG for five years and installed at MCG’s planned assisted living facility in Cane Bay, South Carolina. The parties also entered into a second lease agreement (“Lease 2”) that ELGA later assigned to Lakeside Bank. Only Lease 1 is at issue in this appeal. Concurrently with the signing of Lease 1, the Guarantors executed guarantees in favor of ELGA, guaranteeing MCG’s obligations under the Lease. Around the same time, MCG also signed a “Pre-Delivery Certificate” stating that MCG “desires to commence the Lease prior to the complete delivery and installation of all the equipment” and that, in order to induce ELGA to begin making payments to the equipment vendors, MCG “hereby certifies that the portion of the Equipment that has already been delivered to [MCG], if any, is fully installed, working properly and irrevocably accepted by [MCG].”

¶4 In July 2017, MCG decided that it would no longer move forward with its Cane Bay project and ceased making payments on both leases. By that time, MCG had made monthly payments totaling $112,635.27 toward Lease 1 and ELGA had made down payments to equipment vendors totaling $90,623.43 under the Lease. Following MCG’s default on Lease 1, ELGA elected not to

complete the purchase of the equipment that it was to deliver to MCG, and it instead recovered $55,889.50 of its deposits to the equipment vendors.

¶5 On August 5, 2021, ELGA filed suit against MCG and the Guarantors for breach of contract seeking approximately $265k in damages for Lease 1 and approximately $351k in damages for Lease 2. The defendants collectively answered the complaint and raised affirmative defenses, and the parties filed cross-motions for summary judgment. In its motion for summary judgment, MCG asserted that the leases were unenforceable, that ELGA was not entitled to any damages arising from Lease 2, in which ELGA no longer had any interest after assigning it to Lakeside Bank, and that ELGA was also not entitled to damages for any lost depreciation tax deductions that it anticipated receiving for the equipment that it was to purchase for MCG. For its part, ELGA sought partial summary judgment on the issue of whether MCG had breached Lease 1.

¶6 Following a hearing, the circuit court granted ELGA’s motion for partial summary judgment, ruling that MCG breached Lease 1 by failing to make required payments. The court also granted MCG’s motion in part, ruling that ELGA’s claims relating to Lease 2 were extinguished by its assignment of that lease to Lakeside Bank and that ELGA was not entitled to damages for lost depreciation because ELGA is not a taxable entity and that any such damage would only be inflicted on its tax-paying member, LBBB, LLC (“LBBB”), which was neither a party to Lease 1 nor a third-party beneficiary. The court denied the portion of MCG’s motion relating to the enforceability of Lease 1, finding the Lease valid and enforceable. The court’s oral rulings were memorialized in a written order dated April 25, 2023.

¶7 The court then held a three-day trial on the issue of damages for MCG’s breach of Lease 1. Based on the testimony of its expert witness, ELGA sought damages totaling $482,578.16 for the

gross amount that it was to receive under the Lease, legal fees, late fees, default interest, processing fees, inspection fees, accounting fees, and the residual value of the equipment to be leased. According to ELGA, those damages were all authorized by the terms of the Lease, which, in relevant part, provided that, in the event of a default by MCG, ELGA could sue for and recover all unpaid lease payments, all accelerated future payments due, all costs of enforcement and collection, and the residual value of the equipment. MCG’s expert testified that, had the Lease been fully performed by both parties, ELGA would have received a total of $236,003 in lease payments and residual equipment value and would have expended $181,247 to acquire the equipment for MCG, for a net profit of $54,756. According to MCG’s expert, that expected profit was less than ELGA’s actual profit following MCG’s breach, which totaled $77,898 when subtracting ELGA’s net post-refund outlay to vendors from MCG’s lease payments at the time of breach.

¶8 At the conclusion of trial, the court found that ELGA was not entitled to damages because it had realized more profit following MCG’s breach than it would have had the parties fully performed the Lease. The court found MCG’s expert’s analysis to be “theoretically sound, supported by the evidence, persuasive, and *** consistent with the law.” According to the court, the only element missing from MCG’s analysis of ELGA’s damages was the cost of recovering ELGA’s deposits to vendors, but the court found that to be a consequence of ELGA’s own failure of proof, with the court noting that ELGA “produced no evidence as to what actual efforts were required, no evidence of actual or even estimated costs, and there was nothing to suggest that the cost of those efforts would have reduced the actual profits made by [ELGA] below those it expected to make had both sides faithfully performed.” Additionally, the court found that ELGA’s

evidence of its costs to prosecute the present suit was insufficient to prove that the costs were reasonable. Further, the court affirmatively found that the fees that ELGA incurred prosecuting the suit were in fact unreasonable because, as a matter of law, it was not entitled to “windfall” damages in excess of what it would have received had the contract been fully performed and, therefore, had no meritorious claim for damages to pursue. Accordingly, the court denied ELGA’s request for damages in its entirety and entered judgment in favor of MCG and the Guarantors. This appeal follows.

Free access — add to your briefcase to read the full text and ask questions with AI

Equipment Leasing Group of America, LLC v. MCG Cane Bay, LLC, 2024 IL App (1st) 231143-U (Ill. Ct. App. 2024).

2024 IL App (1st) 231143-U (Equipment Leasing Group of America, LLC v. MCG Cane Bay, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

1472 N. Milwaukee, LTD. v. Feinerman
2013 IL App (1st) 121191 (Appellate Court of Illinois, 2013)
Wheeling Trust & Savings Bank v. Tremco Inc.
505 N.E.2d 1045 (Appellate Court of Illinois, 1987)
MBC, INC. v. Space Center Minnesota, Inc.
532 N.E.2d 255 (Appellate Court of Illinois, 1988)
Aetna Insurance v. Amelio Bros. Meat Co.
538 N.E.2d 707 (Appellate Court of Illinois, 1989)
Gaiser v. Village of Skokie
648 N.E.2d 205 (Appellate Court of Illinois, 1995)
Collins v. Reynard
607 N.E.2d 1185 (Illinois Supreme Court, 1992)
155 Harbor Drive Condominium Ass'n v. Harbor Point Inc.
568 N.E.2d 365 (Appellate Court of Illinois, 1991)
Ball Corp. v. Bohlin Building Corp.
543 N.E.2d 106 (Appellate Court of Illinois, 1989)
Schatz v. Abbott Laboratories, Inc.
281 N.E.2d 323 (Illinois Supreme Court, 1972)
Pappas v. Waldron
751 N.E.2d 1276 (Appellate Court of Illinois, 2001)
Neiman v. Economy Preferred Insurance
829 N.E.2d 907 (Appellate Court of Illinois, 2005)
Ollivier v. Alden
634 N.E.2d 418 (Appellate Court of Illinois, 1994)
General Casualty Insurance v. Lacey
769 N.E.2d 18 (Illinois Supreme Court, 2002)
Themas v. Green's Tap, Inc.
2014 IL App (2d) 140023 (Appellate Court of Illinois, 2014)
CitiMortgage, Inc. v. Hoeft
2015 IL App (1st) 150459 (Appellate Court of Illinois, 2015)
Burkhart v. Wolf Motors of Naperville, Inc.
2016 IL App (2d) 151053 (Appellate Court of Illinois, 2016)