Farrell-Cooper Mining Co. v. United States Department of the Interior

864 F.3d 1105, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20095, 2017 WL 3138368, 84 ERC (BNA) 2069, 2017 U.S. App. LEXIS 13396
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 25, 2017
Docket16-7061
StatusPublished
Cited by8 cases

This text of 864 F.3d 1105 (Farrell-Cooper Mining Co. v. United States Department of the Interior) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrell-Cooper Mining Co. v. United States Department of the Interior, 864 F.3d 1105, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20095, 2017 WL 3138368, 84 ERC (BNA) 2069, 2017 U.S. App. LEXIS 13396 (10th Cir. 2017).

Opinion

LUCERO, Circuit Judge.

Under the Administrative Procedure Act (“APA”), agencies may require regulated parties to pursue administrative appeals before seeking review in federal court. But as the Supreme Court explained in Darby v. Cisneros, 509 U.S. 137, 113 S.Ct. 2539, 125 L.Ed.2d 113 (1993), intra-agency review “is a prerequisite to judicial review only when expressly required by statute or when an agency rule requires appeal before review and the administrative action is made inoperative pending that review.” Id. at 154, 113 S.Ct. 2539. This rule prevents agencies from enforcing initial decisions while a mandatory administrative appeal is pending, which would effectively insulate such decisions from judicial scrutiny.

The Department of the Interior (“DOI”) has adopted an administrative appeal requirement for agency actions under the Surface Mining Control and Reclamation Act (“SMCRA”), 30 U.S.C. §§ 1201 et seq. Following an initial decision by an administrative law judge (“ALJ”), DOI regulations require an adversely affected party to concurrently file an appeal and a petition for stay pending appeal with the Interior Board of Land Appeals (“IBLA”) to exhaust administrative remedies. 43 C.F.R. § 4.21(c). However, an ALJ decision is not always rendered inoperative pending appeal. Instead, the IBLA retains discretion to grant or deny the stay. § 4.21(b).

We must decide whether the IBLA’s denial of a stay renders an ALJ’s decision final for purposes of judicial review, notwithstanding a pending IBLA appeal. This question is controlled by Darby: “Agencies may avoid the finality of an initial decision” only “by providing that the initial decision would be inoperative pending appeal. Otherwise, the initial decision becomes final and the aggrieved party is entitled to judicial review.” 509 U.S. at 152, 113 S.Ct. 2539 (quotation omitted). Because the ALJ’s decision in this case was not rendered inoperative pending appeal to the IBLA, it constitutes final agency action. Exercising jurisdiction under 28 U.S.C. § 1291, we reverse the district court’s contrary conclusion and remand for further proceedings.

*1108 I

Under SMCRA, states may submit proposed regulatory programs to. DOI and, if approved, obtain regulatory jurisdiction over surface coal mining and reclamation operations. See Farrell-Cooper Mining Co. v. U.S. DOI, 728 F.3d 1229, 1232 (10th Cir. 2013) (citing 30 U.S.C. § 1253(a)). Oklahoma has obtained such approval and has designated the Oklahoma Department of Mines (“ODM”) to administer its SMCRA program. Id. (citing .30 C.F.R. § 936.10; Okla. Admin. Code § 460:20-1-4).

Although ODM is primarily responsible for enforcing SMCRA in Oklahoma, DOI retains oversight through its Office of Surface Mining Reclamation and Enforcement (“OSM”). Whenever OSM. “has reason to believe that any person is in violation of any requirement of [SMCRA] or any permit condition required by [SMCRA],” it may issue notice to a state regulatory authority. 30 U.S.C. § 1271(a)(1). Unless a state takes “appropriate action” within ten days of the notice or shows “good cause” for failiiig to do so, OSM orders a federal inspection. Id. These notices are thus referred to as “ten-day notices.” If, following federal inspection, OSM determines a per-mittee is in violation of SMCRA or a permit condition, it issues a notice of violation (“NOV”). § 1271(a)(3). OSM then sets “a reasonable time but not more than ninety days for the abatement of the violation.” Id. A failure to abate will result in an OSM order for “cessation of surface coal mining and reclamation operations or the portion thereof relevant to the violation.” Id. Further, a mine operator foünd to be in violation will be prohibited from obtaining new permits for other mines. § 1260(c).

Farrell-Cooper Mining Co. (“Farrell-Cooper”) operates the Rock Island Mine in Leflore County, Oklahoma, pursuant to a permit issued by ODM. In July 2012, OSM issued a ten-day notice for the Rock Island Mine, alleging a violation of SMCRA’s requirement. that mine operators “restore the approximate original contour of the land.” § 1265(b)(3). OSM and ODM have been engaged in a long-running dispute regarding the propér interpretation of the approximate original contour (“AOC”) standard. ODM responded to the ten-day notice by reiterating its position that. OSM has misconstrued the AOC standard and arguing that the Rock Island Mine was compliant. By letter dated April 2, 2013, OSM rejected ODM’s response as arbitrary, capricious, or an abuse of discretion. ODM sought informal review of that decision, and OSM affirmed.

Following a federal inspection, OSM issued an NOV to Farrell-Cooper on August 19, 2013. The notice required Farrell-Cooper to abate reclamation activities, submit a new reclamation plan, diligently pursue OSM approval, and then implement the new plan. Farrell-Cooper alleges that complying with the NOV would require it to transfer millions of yards of earth, imposing an “untenable financial burden,”

On August 28, 2013, Farrell-Cooper filed a “Conditional Application for Review and Conditional Request for Temporary Relief and Stay” with DOI’s Office of Hearings and. Appeals (“OHA”). Following lengthy proceedings, an ALJ upheld the NOV on September 30, 2015, On October 19, 2015, Farrell-Cooper filed a notice of appeal and a petition for stay pending appeal with the IBLA. After the ALJ issued ah amended decision clarifying his prior order, the IBLA denied a stay, concluding that Farrell-Cooper had not demonstrated a likelihood of success on the merits. That denial—issued December 14, 2015—rendered the ALJ’s decision immediately effective. See 43 C.F.R. § 4.21(a)(3) (“A decision, or that portion of a decision, for which a stay is not granted will become effective immediately . after .... [the IBLA], denies or partially denies the, petition for a stay.”). *1109 Accordingly, OSM proceeded to enforce the NOV, issuing a document titled “Modifications of Notice of Violation or Cessation Order” that required Farrell-Cooper to undertake certain abatement measures.

On January 12, 2016, • Farrell-Cooper submitted its “Statement of Reasons” and Appellate Brief to the IBLA in the still-pending administrative appeal. The next day, it filed suit - in federal court seeking review of the ALJ’s decision under 5 U.S.C. § 706 and 30 U.S.C. §. 1276, as well as a stay of further enforcement action. In light of the federal lawsuit, OSM filed a motion before the IBLA on January 20, requesting the administrative appeal be held in abeyance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
864 F.3d 1105, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20095, 2017 WL 3138368, 84 ERC (BNA) 2069, 2017 U.S. App. LEXIS 13396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrell-cooper-mining-co-v-united-states-department-of-the-interior-ca10-2017.