Farnsworth, III v. Towboat Nantucket Sound, Inc.

790 F.3d 90, 2015 A.M.C. 1586, 2015 U.S. App. LEXIS 10203, 2015 WL 3759285
CourtCourt of Appeals for the First Circuit
DecidedJune 17, 2015
Docket14-1903
StatusPublished
Cited by17 cases

This text of 790 F.3d 90 (Farnsworth, III v. Towboat Nantucket Sound, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farnsworth, III v. Towboat Nantucket Sound, Inc., 790 F.3d 90, 2015 A.M.C. 1586, 2015 U.S. App. LEXIS 10203, 2015 WL 3759285 (1st Cir. 2015).

Opinion

LYNCH, Circuit Judge.

Out of this maritime case come useful lessons for those who seek to challenge the validity of arbitration clauses in contracts they have signed.

Plaintiff Rodney Farnsworth, III, entered into a salvage contract with defendant Towboat Nantucket Sound; Inc. (“TNS”), to obtain help when Farnsworth’s boat went aground on rocks one night near the Weepecket Islands in Buzzards Bay. Farnsworth later tried to rescind the whole contract, claiming that he had signed it under duress, and disputed the sum owed to TNS.

The chronology of events is important. The parties by agreement submitted the dispute to a panel of three arbitrators pursuant to a binding arbitration clause in the salvage contract. After the arbitration proceeding had started, Farnsworth chose to file this lawsuit, seeking a preliminary injunction against the arbitration and a declaration that the salvage contract was unenforceable because Farnsworth had entered into it under duress. His complaint drew no distinction between the obligation to arbitrate and the merits issue of what payment was owed to TNS. The district court denied the motion for injunctive relief and stayed the case pending the outcome of the arbitration. The arbitration panel found in favor of TNS and ordered Farnsworth to pay a salvage award of $60,306.85. The district court confirmed that award over Farnsworth’s objection.

Farnsworth appeals, arguing that the district court erred in confirming the arbitration award without first addressing his duress claim as to the arbitration clause. We hold that, because Farnsworth did not challenge the validity of the arbitration clause specifically in his complaint (or indeed at any time before the conclusion of the arbitration' proceedings), 1 the district *93 court 'correctly found that the duress claim in all its aspects was for the arbitrator to resolve. Essentially, Farnsworth did too little, too late. We affirm.

I.

On the evening of July 28, 2012, Farns-worth was anchoring his boat, the M/Y AURORA, in the Weepecket Island anchorage in Buzzards Bay. The boat’s depth sounder malfunctioned and Farnsworth inadvertently allowed the vessel to drift aground. Farnsworth requested a tow over his marine radio, and TNS’s vessel the NORTHPOINT responded to his call. Farnsworth also made contact with the Coast Guard, which instructed him that, if he had any problems, he should “make the appropriate hail” and the Coast Guard would assist.

The merits issue' in this case turns on whether the contract which ensued was a towage or a salvage contract. The difference between the two is important under maritime law because towage is compensated at a contract rate, whereas a salvor is entitled to an equitable award equal to a portion of the value of the salvaged property. 2 T.J. Schoenbaum, Admiralty and Maritime Law § 16-1 (5th ed.2014); see also Faneuil Advisors, Inc. v. O/S Sea Hawk, 50 F.3d 88, 92 (1st Cir.1995) (describing the law of salvage). Salvage service generally “commands a larger award,” and a salvage contract creates a preferred maritime lien. Evanow v. M/V Neptune, 163 F.3d 1108, 1114 (9th Cir.1998). 2

The parties sharply differ over what happened in the hours after Farnsworth made contact with the NORTHPOINT. Farnsworth’s complaint alleges that the NORTHPOINT crew members “attempt[ed] to create a salvage” by taking various actions designed to make the AURORA’S situation appear worse than it actually was. The complaint maintains that the “AURORA was undamaged, completely buoyant, and watertight,” and needed only a tow, rather than a salvage. The complaint alleges that when Farns-worth resisted TNS’s efforts to create a salvage, the NORTHPOINT intentionally pulled the AURORA onto charted rocks, damaging her hull; next ordered Farns-worth to drop anchor in dangerous, unprotected waters; and then sent two large men on board the AURORA to coerce Farnsworth to sign a contract giving TNS the rights to a salvage ■ award for towing the AURORA. The complaint alleges that Farnsworth “attempted to refuse to sign the salvage contract three times,” but finally relented “because he was alone aboard the vessel with two [TNS] employees, iñ a remote location, without hope of *94 assistance, at a late hour (03:30 A.M.),” and because “[t]he employees indicated that they would not leave without the signed contract.”

During arbitration, John Mark Brown, one of the “large [TNS] employees” who Farnsworth says coerced him to sign the salvage contract, gave a starkly different account of the encounter. Brown recounted that the AURORA was in serious danger. The area in which the AURORA was stranded, Brown said, was “littered with rocks,” a danger compounded by the severe weather conditions in the area that night. Brown called Farnsworth on his cell phone and told him that, in light of those circumstances, TNS’s services would not be covered under Farnsworth’s towing policy; instead, Farnsworth would have to sign a “no cure, no pay” salvage contract. 3 Brown said Farnsworth initially agreed to accept salvage services during the phone conversation, but later balked at the arrangement when Brown boarded the AURORA, and then relented when Brown reminded him of his earlier agreement to a salvage contract. Brown also vigorously disputed Farnsworth’s allegations that he and his partner threatened Farnsworth. Brown noted that Farnsworth had earlier spoken to the Coast Guard but “never attempted to contact the Coast Guard after we left.”

The contract executed by the parties is a standard form “no cure, no pay” marine salvage agreement. Farnsworth wrote by hand the following addendum to the form contract: “Aurora was hard aground, Tow Boat prevented the Boat from going further aground, and towed the boat when the Tide floated it off.” 4

The contract contains an arbitration clause:

Read Carefully■ — Arbitration Provision — In the event of any dispute arising out of this Contract including any dispute regarding this salvage or concerning the reasonableness of any fees or charges due hereunder, all parties agree to binding arbitration in the United States in accordance with the Rules for Recreational and Small Commercial Vessel Salvage Arbitration of the Society of Maritime Arbitrators, Inc. Arbitrators shall be familiar with maritime salvage. Any award hereunder shall include interest, attorneys’ fees and costs, and arbitration administration expenses and shall be final and binding. For the purpose of enforcement, the Award may be entered for judgment in any court of competent jurisdiction.

Farnsworth’s buyers’ remorse set in quickly. Approximately five days later, on August 3, 2012, Farnsworth sent a letter to TNS purporting to rescind the salvage contract, demanding that TNS preserve evidence relating to “the prospective litigation,” and intimáting that TNS had engaged in illegal business practices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toth v. Everly Well, Inc.
118 F.4th 403 (First Circuit, 2024)
Emmanuel v. Handy Technologies, Inc.
992 F.3d 1 (First Circuit, 2021)
Peterson v. Binnacle Capital Servs. LLC
364 F. Supp. 3d 108 (District of Columbia, 2019)
Cellinfo, LLC v. Am. Tower Corp.
352 F. Supp. 3d 127 (District of Columbia, 2018)
Axia Netmedia Corp. v. Mass. Tech. Park Corp.
343 F. Supp. 3d 8 (District of Columbia, 2018)
Nat'l Fed'n of the Blind v. Container Store, Inc.
904 F.3d 70 (First Circuit, 2018)
Francisco J. Ortiz & Co. v. Masco Corp.
147 F. Supp. 3d 1 (D. Puerto Rico, 2015)
Family Endowment Partners, L.P. v. Sutow
33 Mass. L. Rptr. 120 (Massachusetts Superior Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
790 F.3d 90, 2015 A.M.C. 1586, 2015 U.S. App. LEXIS 10203, 2015 WL 3759285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farnsworth-iii-v-towboat-nantucket-sound-inc-ca1-2015.